Medium Neutral Citation: Tzaneros Investments Pty Ltd v Walker Group Constructions Pty Ltd (No 4) [2018] NSWSC 431 Hearing dates: 23 and 28 March 2018 Decision date: 11 April 2018 Jurisdiction: Equity Before: Ball J Decision: The plaintiff’s notice of motion filed on 24 November 2017 is dismissed.
Catchwords: COSTS – Party/Party – Whether to make a gross sum costs order – Difficulty of making a fair assessment on a gross sum basis – Effect of delay in making the application Legislation Cited: Civil Procedure Act 2005 (NSW) Cases Cited: Beach Petroleum NL & Claremont Petroleum NL v Johnson (1995) 57 FCR 119; (1995) 135 ALR 160
Bobb v Wombat Securities Pty Ltd (No 2) [2013] NSWSC 863
Bookarelli Pty Ltd v Katanga Developments Pty Ltd [2017] NSWCA 69
Coshott v Parker (No 3) [2015] NSWSC 1195
Hamod v State of New South Wales [2011] NSWCA 375
Harrison v Schipp [2002] NSWCA 213
Harvey v Barton (No 4) [2015] NSWSC 809
Tim Barr Pty Ltd v Narui Gold Coast Pty Ltd [2011] NSWSC 11
Tzaneros Investments Pty Limited v Walker Group Constructions Pty Limited [No. 3] [2016] NSWSC 526
Walker Group Constructions Pty Ltd v Tzaneros Investments Pty Ltd [2017] NSWCA 27Category: Costs Parties: Tzaneros Investments Pty Ltd (ACN 114 879 524) (Plaintiff)
Walker Group Constructions Pty Ltd (ACN 097 303 716)Representation: Counsel:
Solicitors:
J Hogan-Doran (Plaintiff)
D Ryan SC with M Castle and E Whitby (First Defendant)
Sarvaas Ciappara (Plaintiff)
Squire Patton Boggs (First Defendant)
File Number(s): 2009/298899 Publication restriction: None
Judgment
Introduction
-
On 29 April 2016, the Court relevantly ordered that the first defendant pay the plaintiff’s costs of the proceedings against the first defendant including on an indemnity basis from 14 December 2010: Tzaneros Investments Pty Limited v Walker Group Constructions Pty Limited [No. 3] [2016] NSWSC 526 (Costs Judgment).
-
By a notice of motion filed on 24 November 2017, the plaintiff made an application for a gross sum costs order instead of assessed costs and, on 2 February 2018, I ordered that all issues relating to that application other than quantification of the lump sum be heard separately and in advance of the question of quantification. This judgment is concerned with those issues.
Background
-
The proceedings concerned a claim for damages brought by the plaintiff (Tzaneros) in relation to defective concrete paving at a container terminal at Molineaux Point, Port Botany.
-
The proceedings were commenced on 30 September 2009, originally against the first defendant, Walker Group Constructions Pty Limited (WGC), Walker Corporation Ltd (Walker), and Alan L Wright and Associates Pty Limited (AMT). WGC designed and constructed the terminal. Walker is WGC’s parent and originally was the successful tenderer for the work. AMT is a design engineer who was engaged to design the concrete pavement. WGC also filed a cross-claim against AMT.
-
On 29 September 2010, Tzaneros discontinued the proceedings against Walker and from that time AMT became…
Keep reading for free
Create a free CaseChat account to read Tzaneros Investments Pty Ltd v Walker Group Constructions Pt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] NSWSC 431
- Decision Date
CaseChat Overview and Summary
The central legal issue before the court was whether the circumstances justified a departure from the usual practice of assessing costs in detail. The court had to consider the principle that a party should not be penalised for delay in making an application for costs and whether the delay was such that it would prejudice the other party. Additionally, the court had to weigh the difficulties inherent in making a fair assessment on a gross sum basis against the benefits of expediency and finality that such an order might provide.
The court held that while gross sum costs orders were appropriate in certain cases, the delay in making the application in this instance was significant and had prejudiced the defendant. The court found that the delay made it difficult to accurately assess the costs incurred by the plaintiff and the extent to which the defendant had contributed to the delay. Consequently, the court determined that the circumstances did not warrant a gross sum costs order. Instead, the court ordered that the costs be assessed in detail, taking into account the delay and its impact on the proceedings.
In light of the court's decision, the final orders were that the application for a gross sum costs order was dismissed, and the costs of the proceeding were to be assessed in detail, with due regard to the delay in making the application. The court directed the parties to proceed with the detailed assessment of costs to ensure that the outcome was fair and just.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi