Tweed Local Environmental Plan 2000 (Amendment No 46) (2005-2) [GG No 3 of 7.1.2005, p 23] (NSW)
2005 No 2
| New South Wales |
Tweed Local Environmental Plan 2000
(Amendment No 46)
under the
Environmental Planning and Assessment Act 1979
I, the Minister Assisting the Minister for Infrastructure and Planning (Planning Administration), make the following local environmental plan under the Environmental Planning and Assessment Act 1979. (G03/00062/PC)
DIANE BEAMER, M.P.,
Minister Assisting the Minister for Infrastructure
and Planning (Planning Administration)
| Published in Gazette No 3 of 7 January 2005, page 23 | Page 1 |
| 2005 No 2 |
| Clause 1 | Tweed Local Environmental Plan 2000 (Amendment No 46) |
Tweed Local Environmental Plan 2000 (Amendment
No 46)
under the
Environmental Planning and Assessment Act 1979
1 Name of plan
This plan is Tweed Local Environmental Plan 2000 (Amendment
No 46).
2 Aims of plan
This plan aims to amend Tweed Local Environmental Plan 2000 so
as:
| (a) | to change the interpretation of building height to reflect finished ground level rather than natural ground level, and |
| (b) | to change the definition of storey so that a storey that exceeds a specified height is counted as two storeys. |
3 Land to which plan applies
This plan applies to all land to which Tweed Local Environmental
Plan 2000 applies.
4 Amendment of Tweed Local Environmental Plan 2000
Tweed Local Environmental Plan 2000 is amended as set out in
Schedule 1.
2005 No 2
Tweed Local Environmental Plan 2000 (Amendment No 46)
| Amendments | Schedule 1 |
| Schedule 1 Amendments |
(Clause 4)
[1] Clause 16 Height of buildings
Insert after clause 16 (2):
| (3) | If an application for development consent made to the consent authority prior to the commencement of Tweed Local Environmental Plan 2000 (Amendment No 46) is not determined by the consent authority before that date: | |||
|
[2] Schedule 1 Meanings of terms
Insert in alphabetical order:
| ||||||
|
| (b) | the level of the land approved by the consent authority as the finished ground level of the land prior to the commencement of Tweed Local Environmental Plan 2000 (Amendment No 46), |
2005 No 2
Tweed Local Environmental Plan 2000 (Amendment No 46)
| Schedule 1 | Amendments |
| (c) | if the land is within an area identified by the Council as flood liable land, the level of the land after filling the land in accordance with the consent of the consent authority to the adopted design flood level under Tweed Development Control Plan No 5—Development of Flood Liable Land, as adopted by the Council on 6 March 1996. |
[3] Schedule 1, definition of “height” in relation to a building
Omit “natural ground level”. Insert instead “finished ground level”.
[4] Schedule 1, definition of “storey”
Omit the definition. Insert instead:
|
| (a) | the space between two floors, or |
| (b) | the space between a floor and any ceiling or roof immediately above it, or |
| (c) | foundation areas, garages, workshops, storerooms and the like, excluding access paths to basement areas, where the height between the finished ground level and the top of the floor immediately above them exceeds 1.5 metres in |
height.
A storey which exceeds 4.5 metres for residential buildings is the number is to be the maximum number of storeys of the building which may be intersected by the same vertical line, not being a line which passes through any wall of the building.
counted as two storeys.
A storey which exceeds 5 metres for commercial buildings is
counted as two storeys.