| CITATION: | Turner and Anor v Zachary Developments Pty Ltd [2010] QCAT 706 |
| PARTIES: | Wayne Turner Judith Elaine Turner |
| v | |
| Zachary Developments Pty Ltd |
| APPLICATION NUMBER: | B455-05 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 2, 3, 4, 5 and 9 August 2010 |
| HEARD AT: | Brisbane |
| DECISION OF: | John Bertelsen, Adjudicator |
| DELIVERED ON: | 23 December 2010 |
| DELIVERED AT: | Brisbane |
ORDERS MADE: | (1) That the Respondent pay to the Applicants the sum of $31,878.26 by 31 January 2011. (2) That the Applicants file and serve submissions in relation to costs by 11 February 2011. (3) That the Respondent file and serve submissions in relation to costs by 25 February 2011. (4) That the issue of costs be determined on the papers. |
| CATCHWORDS: | Building contract dispute – termination – abandonment – rectification – expert assessment of works |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Mr Wayne Turner and Mrs Judith Elaine Turner represented by Mr Poiner of counsel |
| RESPONDENT: | Zachary Developments Pty Ltd represented by Mr Hackett of counsel instructed by Wilson Lawyers |
REASONS FOR DECISION
Application
This application sought loss and damage suffered by reason of the Respondent’s alleged breach of a building contract dated 16 July 2001, that breach allegedly occurring in early 2002. The events, the subject of the application, occurred over 8 years ago with this application originally being filed on 4 August 2005.
Background
The parties entered into a Queensland Master Builders Residential Building Contract dated 16 July 2001.[1] It is not contentious that contract documents consisted of the following:
[1] Exhibit 48 paragraph 3.
a 17 page bundle of plans prepared by Robert Ayers Design and Drafting and Soil Test Australia signed by Mrs Turner on or about 16 July 2001;
impliedly, a 12 page bundle of plans by Robert Ayers Design and Drafting numbered 4198 and tables stamped “approved” by Brisbane Certification Group 18 December 2000;
specification prepared by Wayne Turner dated 8 June 2001 as amended in handwriting by the Respondent’s Wayne Johnstone (the Builder) and signed by Mrs Turner on or about 16 July 2001;
and finally engineering drawings dated 13 June 2000 prepared by Soil Test Australia approved by Brisbane Certification Group 18 December 2000 (the Contract).
Additionally the Applicants signed a letter from the Respondent dated 16 July 2001 that contained a quotation.[2] Construction was to take 120 days or as extended pursuant to the contract. Progress payments[3] were payable in accordance with method A, appendix part D of the contract as follows:
Deposit $ 6,600
Ground floor $ 13,200
First floor $ 19,800
Enclosed stage $ 46,200
Fixing stage $ 26,400
Practical completion $ 19,800
Total $132,000
[2] Exhibit 48 paragraph 4.
[3] Exhibit 48 paragraph 11.
The contract works consisted of the construction of a four bedroom extension joined by a breezeway to the rear of the existing dwelling situated at 14 Corsica St, Moorooka as well as some minor remediation to the existing dwelling. Construction was to commence on 31 July 2001. The deposit was paid. Construction commenced about 1 August 2001…
Keep reading for free
Create a free CaseChat account to read Turner v Zachary Developments Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] QCAT 706
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the Respondent had a valid reason to terminate the contract under the terms set forth. Additionally, it was necessary to assess whether the Applicant's actions constituted abandonment of the project, which could potentially absolve the Respondent of any further obligations. The court also needed to consider whether the contract permitted rectification of defects and if an expert assessment of the works was mandatory before any rectification could be carried out.
The court found that the Respondent was not justified in terminating the contract as the actions of the Applicant did not warrant such a response under the contract terms. The Applicant had not abandoned the project, as evidenced by their continued engagement and efforts to complete the works. The contract did provide for rectification of defects, but it did not explicitly require an expert assessment before proceeding with rectification. The court ruled in favour of the Applicant, ordering the Respondent to pay the sum of $31,878.26 by 31 January 2011. The issue of costs was to be determined on the papers, with submissions from both parties to be filed by specified dates.
The final orders of the court included the payment by the Respondent to the Applicant, the submission of costs by both parties, and the determination of costs on the papers. This ruling provided clarity on the rights and obligations of both parties under the contract, ensuring that the dispute was resolved efficiently.
Orders
Orders of the court
(1) That the Respondent pay to the Applicants the sum of $31,878.26 by 31 January 2011.
(2) That the Applicants file and serve submissions in relation to costs by 11 February 2011.
(3) That the Respondent file and serve submissions in relation to costs by 25 February 2011.
(4) That the issue of costs be determined on the papers.