TSOTSIS v KHNEIGER
[2003] SADC 138Judge Robertson
CivilNature of the Proceedings
In July 2001 the Plaintiff and the Defendants entered into a written agreement, (“the Contract”) whereby the Defendants, trading as BJ Home Constructions, (some times called “the Builder”) agreed to undertake building works at the premises of the Plaintiff at Cumberland Park. It turned out to be a most unhappy association. The Plaintiff terminated the services of the Defendants in December 2001. The termination of those services has ultimately brought the parties to this Court.
The Plaintiff seeks damages against the Defendants alleging breach of contract, breach of statutory duties under the Building Work Contractors Act 1995 (“the Act”) and negligence.
The Defendants have cross-claimed against the Plaintiff seeking compensation for the cost of variations to work forming part of the contractual work and the cost of work performed by them, which it is alleged was not included in the Contract but was requested by the Plaintiff whilst the building works were being undertaken. The Defendants also seek compensation for what they describe as the cost of work performed by the Defendants’ sub-contractors pursuant to contracts entered into directly between the Plaintiff and those sub-contractors. It seems that with respect to this latter part of the case the Defendants’ assert that, whilst they were not a party to these separate contracts, they are liable to meet the costs of each of the sub-contractors.
I should point out at this point that I have deliberately used the expression “cross-claim”. In accordance with the procedure of the Court it would be expected that I would use the term “counter-claim”. However, this action proceeded without pleadings and on affidavits. I will have more to say about that procedure shortly. At this point all I wish to say is that such a procedure was completely unwarranted and made a case which was by its nature a difficult one to manage even more difficult.
The Plaintiff’s Claim
The Plaintiff’s claims for damages were set out in her affidavits. The first part of her claim was described in the following terms:
· Costs met by the plaintiff in completing work required to be completed by the Builder under the Contract $9,686.81
· Costs of rectifying defective work, and completing other works still outstanding under the Contract
$30, 912.29
The Plaintiff also claims damages for the Builder’s breach of the statutory duty, under the Act, in failing to obtain building indemnity insurance as required by Division 3 of the Act. Furthermore, the Plaintiff also claims damages in negligence arising out of rain damage to various personal items, which it is alleged, occurred when the Builder failed to place a covering over an exposed portion of the roof of the Plaintiff’s premises during the course of the building work. Finally, the Plaintiff also claims damages for inconvenience resulting from the Defendants’ breach of Contract.
Due to the absence of pleadings, I required the Plaintiff to produce a Schedule itemizing the costs alleged to have been…
Keep reading for free
Create a free CaseChat account to read Tsotsis v Khneiger & Khneiger No. DCCIV-02-1364 and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] SADC 138
- Decision Date
CaseChat Overview and Summary
The legal issues that the court was required to decide included the identification of the work required to be undertaken pursuant to the contract, the costs incurred by the Plaintiff in completing works required to be done under the contract, the cost of rectifying defective work and completing other works still outstanding under the contract, the cost of work performed by the sub-contractors, and the damages for breach of statutory duty and inconvenience resulting from the Defendants’ breach of contract.
The court found that the work to be done under the contract was the work identified in the plans, specifications and other contract documents. The court allowed the Plaintiff’s claim for the cost of work required to be done under the contract and disallowed the Defendants’ claim for the cost of work performed by their sub-contractors. The court also found that the Plaintiff was entitled to damages for defective work and work not in accordance with specifications, but disallowed the claim for damages for breach of statutory duty and inconvenience resulting from the Defendants’ breach of contract.
The final orders of the court were that there will be judgment for the Plaintiff against the Defendants for the sum of $971 which sum includes interest, and there will be no order as to costs.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.