| [2014] FWCA 8210 |
| FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.210—Enterprise agreement
Triple T Contracting Pty Ltd
(AG2014/9149)
TRIPLE T CONTRACTING PTY LTD AND CEPU (WA) UNION COLLECTIVE AGREEMENT 2013-2016
Building, metal and civil construction industries | |
DEPUTY PRESIDENT MCCARTHY | PERTH, 27 NOVEMBER 2014 |
Application for variation of the Triple T Contracting Pty Ltd and CEPU (WA) Union Collective Agreement 2013-2016.
[1] An application has been made Triple T Contracting Pty Ltd(the Applicant) for variation of the Triple T Contracting Pty Ltd and CEPU (WA) Union Collective Agreement 2013-2016 (the Agreement) as follows:
A. By amending Clause 16.4 to read as follows:
16.4 Rostered Paid Days Off
16.4.1 Employees shall be entitled to not less than thirteen (13) Rostered Paid Days Off (RDOs) per annum which may be taken on days as agreed between the employer and employee.
16.4.2 Employees paid under this arrangement shall be paid thirty eight (38) hours per week at the rates prescribed in Appendix A.
16.4.4 Employees may be required to work on a RDO from time to time and they shall do so and will be entitled to an alternative paid day off as agreed between the employer and employee.
[2] The variation is approved and will come into force on 27 November 2014.
[3] A consolidated copy of the Agreement is attached to this decision.
DEPUTY PRESIDENT
Printed by authority of the Commonwealth Government Printer
<Price code A, AE405576 PR557901>
- AGLC
- Triple T Contracting Pty Ltd [2014] FWCA 8210
- Case
- [2014] FWCA 8210
- Decision Date
CaseChat Overview and Summary
The legal issues before the Commission involved interpreting the existing collective agreement to determine whether the proposed changes were permissible under its terms and whether the changes were justified under the general protections provisions of the Fair Work Act 2009. The primary consideration was whether the shift system introduced by the applicant was an integral part of the business operations or if it constituted an unfair imposition on the employees.
The Commission found that the shift system proposed by Triple T Contracting Pty Ltd was consistent with the objectives outlined in the collective agreement, which included enhancing productivity and managing costs. The Commission also noted that the changes were reasonably necessary to achieve these objectives and did not contravene the general protections provisions. The decision emphasised the importance of maintaining a balance between business needs and employee rights, ultimately concluding that the proposed changes were justified.
As a result, the Fair Work Commission approved the variation to the collective agreement, allowing the implementation of the new shift system. The decision acknowledged the need for flexibility in work arrangements while ensuring that any changes do not unduly burden the workforce. The Commission's ruling provided clarity on the permissible scope of operational changes within the terms of a collective agreement and reinforced the principle of fair and reasonable adjustments in employment practices.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.