PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION:
Trinity Park Investments Pty Ltd & Anor v Cairns Regional Council & Anor [2019] QPEC 68
PARTIES:
TRINITY PARK INVESTMENTS PTY LTD (ACN 123 732 525) AS TRUSTEE AND L’ARMONIA PTY LTD (ACN 140 784 756) AS TRUSTEE
(Appellant/Second Respondent)v
CAIRNS REGIONAL COUNCIL
(Respondent)and
FABCOT PTY LTD (ACN 002 960 983)
(Second Respondent/Applicant)FILE NO:
5434 and 3643 and 4171 of 2019
DIVISION:
Planning and Environment Court
PROCEEDING:
Hearing of applications
ORIGINATING COURT:
Planning and Environment Court of Queensland, Brisbane
DELIVERED ON:
20 December 2019
DELIVERED AT:
Brisbane
HEARING DATE:
4 December 2019
JUDGE:
RS Jones DCJ
ORDER:
The answers to the questions asked by the parties are:
1. The July 2019 development application was impact assessable.
2. The November 2019 development application is code assessable.
3. For the reasons given I will defer answering question 3.
4. The respondent did not have the authority to issue the not properly made notice.
5. If necessary I will hear from the parties as to any consequential orders.
CATCHWORDS:
PLANNING AND ENVIRONMENT – whether two development applications made by the appellant were impact assessable or code assessable – whether the respondent Council had the authority to issue the Not Properly Made Notice issued in respect of the first development application lodged by the appellant.
Planning Act 2016
Royal Agricultural Council Society of New South Wales v Sydney Municipal Council 61 LGRA 305
Food Barn Ltd v Solicitor General 32 LGRA 157COUNSEL:
Mr E Morzone for the appellant
Mr R Litster QC with Ms K Buckley for the respondent
Mr B Job QC for the second respondent/applicantSOLICITORS:
Emanate Legal for the appellant
McCulloch Robertson for the respondent
Keir Steele Walden Lawyers for the second respondent
This proceeding is concerned with the determination of a number of issues raised by way of originating applications filed firstly by Trinity Park Investments Pty Ltd and L’Armonia Pty Ltd (hereafter referred to as TPI) and, subsequently, by Fabcot Pty Ltd (“Fabcot”). On 30 September 2019, TPI filed an originating application seeking declaratory relief concerning a development application lodged with the Cairns Regional Council (“the Council”) initially seeking approval for a shopping centre together with show rooms, a child care centre and food and drink outlets. On 8 October 2019, it filed a further originating application again seeking declaratory relief. On 20 November 2019, Fabcot filed its originating application seeking declaratory relief and consequential orders in contradiction to the relief sought by TPI. The issues required to be determined were agreed:[1]
[1]Exhibit A.
1. First, what is the correct characterisation of, and level of assessment for, the development proposed by the July Application?
2. Second, what is the correct characterisation of, and level of assessment for, the development proposed by November Application?
3. Third, does the zoning of Easement A render the July Application and November Application impact assessable?
4. Fourth, whether the Council had authority to issue the not made notice?
For the reasons set…
Keep reading for free
Create a free CaseChat account to read Trinity Park Investments Pty Ltd v Cairns Regional Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] QPEC 68
- Decision Date
CaseChat Overview and Summary
The primary legal issues addressed by the court were the categorisation of the two development applications, specifically whether they were subject to impact assessment or code assessment under the Planning Act 2016. Additionally, the court had to determine if the respondent Council had the authority to issue a "Not Properly Made Notice" concerning the first application. The court's decision was pivotal in establishing the correct procedural path for the appellant's development projects.
The court found that the July 2019 development application was indeed impact assessable, while the November 2019 application was code assessable. The court held that the respondent Council did not possess the authority to issue the "Not Properly Made Notice" in respect of the first application. The reasoning behind the decisions was based on the provisions of the Planning Act 2016 and relevant case law. The court's detailed analysis provided clarity on the categorisation of the development applications and the procedural rights of the parties involved.
The final orders made by the court were that the July 2019 development application was impact assessable, the November 2019 application was code assessable, and the respondent Council did not have the authority to issue the "Not Properly Made Notice." The court deferred answering the third question and indicated that it would hear from the parties regarding any consequential orders if necessary.
Orders
Orders of the court
The answers to the questions asked by the parties are:
1. The July 2019 development application was impact assessable.
2. The November 2019 development application is code assessable.
3. For the reasons given I will defer answering question 3.
4. The respondent did not have the authority to issue the not properly made notice.
5. If necessary I will hear from the parties as to any consequential orders.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi