Trevet Property v Ashfield Council
[2016] NSWLEC 1240
•25 May 2016
Land and Environment Court
New South Wales
Medium Neutral Citation: Trevet Property v Ashfield Council [2016] NSWLEC 1240 Hearing dates: Conciliation conference on 25 May 2016 Date of orders: 25 May 2016 Decision date: 25 May 2016 Jurisdiction: Class 1 Before: Hussey AC Decision: See (4) below
Catchwords: DEVELOPMENT APPLICATION: Demolition of existing building & alterations for use as 158 place child care centre. Flooding, traffic/parking, disabled access, internal design, waste, conciliation conference; agreement between the parties; orders Legislation Cited: Land and Environment Court Act 1979 Category: Principal judgment Parties: Trevet Property (Applicant)
Ashfield Council (Respondent)Representation: Mr P R Rigg (Applicant)
Mr P Jackson, Pikes & Verekers Lawyers (Respondent)
File Number(s): 154191 of 2016 Publication restriction: No
Judgment
-
COMMISSIONER: In this matter, at or after a conciliation conference, an agreement under s 34(3) of the Land and Environment Court Act 1979 (the Court Act) was reached between the parties as to the terms of a decision in the proceedings that was acceptable to the parties. As the presiding Commissioner, I was satisfied that the decision was one that the Court could have made in the proper exercise of its functions (this being the test applied by s 34(3) of the Court Act). As a consequence, s 34(3)(a) of the Act required me to “dispose of the proceedings in accordance with the decision”.
-
The Court Act also required me to “set out in writing the terms of the decision” (s 34(3)(b)). The orders made to give effect to the agreement constitute that document.
-
In making the orders to give effect to the agreement between the parties, I was not required to, and have not, made any merit assessment of the issues that were originally in dispute between the parties.
-
The final orders to give effect to the parties’ agreement are:
The applicant is granted leave to rely on the following documents:
No.
Revision
Title
Prepared by
Amendment Date
DA02
I
Site Plan
Architex
20.04.2016
DA03
I
Ground Floor Plan
Architex
20.04.2016
DA04
I
First Floor Plan
Architex
20.04.2016
DA05
I
Roof Plan
Architex
20.04.2016
DA06
I
Elevations
Architex
20.04.2016
DA07
I
Elevations and Section
Architex
20.04.2016
DA08
I
Adjoining Building
Architex
20.04.2016
DA08/D
Sections
Teknicon Design P/L
09.08.2011
SW13453-S1
C
Site Stormwater Management Layout
ALW Design
29.03.2016
0727.L.01
E
Landscape Plan
Greenland Design P/L
18.04.2016
0727.L.02
E
Landscape Details & Specification
Greenland Design P/L
18.04.2016
Operational Plan of Management
Cubby House Childcare
Received 7.05.2015
Building Code of Australia Compliance Assessment Report
AEDG Group
30.03.2016
Waste Management Plan
Architex
20.04.2016
Flood Emergency Response Plan
Molino Stewart
23.04.2016
Note: The architectural plans take precedence in respect of the built form. Should there be any inconsistency between the built form shown on the architectural and the engineering or landscape plans, the architectural plans take precedence.
The applicant is to pay the respondent’s costs, agreed at $5,000.00, thrown away as a result of the above amendments pursuant to s 97B of the Environmental Planning and Assessment Act 1979.
The appeal is upheld.
Deferred Commencement Development Consent pursuant to s80(3) of the Environmental Planning and Assessment Act 1979 is granted to Development Application No. 10.2015.68.1 of 7 May 2015, as amended, for the use of premises, being Lot 1 DP 616041, Lot 5 DP 32818 and Lot A DP 435425, known as 1-15 Smith Street and 5 Carlton Crescent, Summer Hill, as a childcare centre for one hundred and sixteen (116) childcare spaces, in accordance with the conditions in Annexure ‘A’ hereto.
…………….
R Hussey
Acting Commissioner
154191.16 Hussey (C) (387 KB, pdf)
154191.16 Hussey_Architectural drawings - Architex 20.4.16 (2.26 MB, pdf)
154191.16 Hussey_BCA Report - AEDG Group 30.3.16 (1.36 MB, pdf)
154191.16 Hussey_Landscape plan and Landscape Details & Specifications - Greenland Design 18.4.16 (544 KB, pdf)
154191.16 Hussey_Operational Management Plan from Cubby House Childcare 7.5.15 (458 KB, pdf)
154191.16 Hussey_Site Stormwater Management Layout - ALW Design 29.3.16 (1.55 MB, pdf)
154191.16 Hussey_Waste Management Plan - Architex 20.4.16 (7.46 MB, pdf)
Decision last updated: 14 June 2016