SUPREME COURT OF QUEENSLAND
CITATION:
Treton Pty Ltd v HM Australia Holdings Pty Ltd and Anor [2011] QSC 38
PARTIES:
TRETON PTY LTD
ACN 105 339 580
(Plaintiff)v
HM AUSTRALIA HOLDINGS PTY LTD
ACN 101 854 817
(First Defendant)and
LEI LEI LU
(Second Defendant)FILE NO/S:
BS 11091 of 2009
DIVISION:
Trial Division
PROCEEDING:
Claim
ORIGINATING COURT:
Supreme Court of Queensland
DELIVERED ON:
21 March 2011
DELIVERED AT:
Brisbane
HEARING DATE:
25-26 and 29-30 November 2010
JUDGE:
McMurdo J
ORDER:
On the claim against the first defendant, there will be a decree of specific performance of each contract and an award of damages against the first defendant in the sum of $35,499.49, together with interest upon that sum at 9% from 15 January 2010.
The claim against the second defendant is dismissed.
CATCHWORDS:
CONVEYANCING – STATUTORY OBLIGATIONS OR RESTRICTIONS RELATING TO CONTRACT FOR SALE – PROTECTION OF PURCHASERS – OBLIGATIONS ON VENDOR: DISCLOSURE, WARNINGS AND LIKE MATTERS – where the plaintiff contracted to sell two proposed allotments of land to the first defendant – where the plaintiff was required to provide the first defendant with a disclosure plan including contour maps of the proposed allotments pursuant to s 9(2)(c) of the Land Sales Act 1984 (Qld) – whether the disclosure plan provided by the plaintiff was sufficient
CONVEYANCING – BREACH OF CONTRACT FOR SALE AND REMEDIES – VENDOR’S REMEDIES – DAMAGES – MEASURE OF DAMAGES – where the first defendant invalidly terminated contracts for the sale of land – where the second defendant signed a form of guarantee and indemnity in favour of the plaintiff – what quantum is available to a vendor pursuant to that indemnity where the contract for the sale of land has been invalidly terminated by a purchaserActs Interpretation Act 1954 (Qld), s 14
Integrated Planning Act 1997 (Qld), s 1.3.5
Integrated Planning and Other Legislation Amendment Act 2003 (Qld), s 36, s 122
Land Act 1994 (Qld)
Land Sales Act 1984 (Qld), s 6, s 8, s 9, s 10, s 31
Land Title Act 1994 (Qld)Supreme Court Act 1995 (Qld), s 47
COUNSEL:
LF Kelly SC with D O’Sullivan for the plaintiff
A Crowe SC with D Thomae for the defendants
SOLICITORS:
McInnes Wilson for the plaintiff
Cooper Grace Ward for the defendants
On 14 March 2008, the plaintiff contracted to sell two parcels of land to the first defendant. This was vacant industrial land at Parkinson near Brisbane. The land was not the subject of a separate title. The plaintiff proposed to create these two parcels, one described as lot 10 having an area of 5,700 square metres and the other described as lot 11 having an area of 2,267 square metres, by a subdivision. A separate contract was made for each parcel, lot 10 being sold for $1,572,120 and lot 11 for $1,296,000. The contracts were otherwise in identical terms and provided for completion 14 days from notice of the registration of the plan of subdivision.
Because there…
Keep reading for free
Create a free CaseChat account to read Treton Pty Ltd v HM Australia Holdings Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2011] QSC 38
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the disclosure plan provided by the plaintiff was adequate under the statutory obligations and whether the first defendant was entitled to terminate the contracts. Additionally, the court had to assess the quantum of damages available to the plaintiff under the indemnity provided by the second defendant.
The court found that the disclosure plan provided by the plaintiff was not sufficient as it failed to include contour maps of the proposed allotments, which were required by the statutory provisions. Consequently, the court ruled that the first defendant was entitled to terminate the contracts. However, the court also held that the measure of damages under the indemnity provided by the second defendant was limited to the actual loss incurred by the plaintiff, which was quantified at $35,499.49. The claim against the second defendant was dismissed as there was no basis to hold the second defendant liable beyond the guarantee and indemnity provided.
The court ordered that specific performance be granted in respect of each contract, and damages of $35,499.49, together with interest at 9% from 15 January 2010, be awarded against the first defendant. The claim against the second defendant was dismissed, and no further orders were made in respect of the second defendant.
Orders
Orders of the court
On the claim against the first defendant, there will be a decree of specific performance of each contract and an award of damages against the first defendant in the sum of $35,499.49, together with interest upon that sum at 9% from 15 January 2010. The claim against the second defendant is dismissed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi