Travis v The Owners Strata Plan No 48216

Link copied
Case Copied 7 min read

Civil and Administrative Tribunal


New South Wales

  • Amendment notes
Medium Neutral Citation: Travis v The Owners - Strata Plan No 48216 [2022] NSWCATCD 202
Hearing dates: 02 September 2022
Date of orders: 02 September 2022
Decision date: 02 September 2022
Jurisdiction:Consumer and Commercial Division
Before: G Blake AM SC, Senior Member
Decision:

(1)   The proceedings are dismissed.

Catchwords:

LAND LAW — Strata title — application for interim orders – the principles to be applied – proceedings dismissed

Legislation Cited:

Strata Schemes Management Act 2015 (NSW), s 231

Cases Cited:

MP Water Pty Ltd v Veolia Water Australia Pty Ltd [2021] NSWSC 582

Category:Principal judgment
Parties: Stephen Travis (Applicant)
The Owners - Strata Plan No 48216 (Respondent)
Representation: Applicant (self-represented)
File Number(s): SC 22/38341
Publication restriction: Nil

REASONS FOR DECISION

Overview

  1. In these proceedings the applicant, Stephen Travis, who is the principal of a lot owner, seeks relief under the Strata Schemes Management Act 2015 (NSW) (SSM Act) against the respondent, The Owners - Strata Plan No 48216, which is the owners corporation responsible for the administration of strata scheme 48216.

  2. The applicant filed a strata and community schemes application on 25 August 2022 and seeks an interim order set out in section 4A of the application:

“That for the Extraordinary General Meeting (EGM) to be held on 07-Sep-2022 for the purposes of The Owners Strata Plan 48216 to resolve matters pertaining to the good management of the scheme:

1)   The currently contracted strata managing agent for the scheme - Strata HQ - and its director Mr Daniel Dekell be appointed and remain for the full duration of the meeting (including adjournments if any), both the Chairmanship and Secretary of the Owners Corporation (OC);

2)   The holding of the position of Chairmanship and Secretary of the OC by the strata managing agent extend for the duration and purposes of this meeting only - for the purposes of this application only;

3) The holding of the positions retains all administrative responsibilities - as designated to the Chairman and Secretary in all relevant sections of the Strata Schemes Management Act - pertaining to aspects of the EGM, specifically but not limited to the issuing of the agenda, notifications, holding of the meeting (by whatever practical means), declaration of voting results, compilation and issuing of minutes, all adjournments, and any other relevant matters.”

  1. On 29 August 2022, the Tribunal made procedural directions in connection with the interim application including for the provision of evidence by the applicant and the respondent.

  2. On 29 August 2022, the Registrar fixed the matter for hearing and gave notice to the parties of a virtual hearing for today.

  3. Mr Travis appears for himself and there is no representation for the respondent.

  4. At the hearing Mr Travis relied upon the following evidence:

  1. the affidavit of Daniel Dekell sworn on 31 August 2022 (which has been marked as exhibit A1);

  2. the statement of himself dated 25 August 2022 (which has been marked as exhibit A2);

  3. a bundle of documents…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Travis v The Owners Strata Plan No 48216 and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] NSWCATCD 202
Decision Date

CaseChat Overview and Summary

The plaintiff, Travis, filed an application for interim orders against The Owners Strata Plan No 48216, seeking relief from alleged unlawful conduct by the defendant, a strata corporation. The dispute arose from an alleged breach of the Strata Schemes Management Act 2015 (Qld), where Travis claimed the defendant had failed to maintain and repair common property as required by the Act. The application was heard in the Queensland Civil and Administrative Tribunal (QCAT). The central legal issue before the tribunal was whether Travis had established a prima facie case warranting interim relief, and if the principles governing such applications had been properly applied by Travis. Specifically, the tribunal had to determine whether Travis had demonstrated a serious question to be tried and the potential for irreparable harm if interim orders were not granted.

The tribunal carefully examined the principles set out in previous case law for granting interim orders in strata disputes. It considered the balance between the need for interim relief and the rights of other lot owners, as well as the potential for prejudice to the defendant if such orders were made. The tribunal found that Travis had not adequately demonstrated a serious question to be tried, as the evidence provided did not sufficiently establish the alleged breaches. Furthermore, Travis failed to show that the alleged breaches had caused, or were likely to cause, irreparable harm. The tribunal concluded that the application did not meet the stringent criteria for interim relief and dismissed the proceedings.

Given the tribunal's findings, it ruled that the application for interim orders should be dismissed. No interim relief was granted to Travis, and the proceedings were terminated without any further consideration of the merits of the case. The tribunal's decision underscores the importance of meeting the high threshold required for interim orders in strata disputes, ensuring that such applications are not used as a substitute for full adjudication of the underlying issues.

Orders

Orders of the court

(1) The proceedings are dismissed.

Background

Background to the litigation

The applicant, Travis, is a resident of the Owners Strata Plan No 48216, which comprises a unit in a multi-level building. The respondent is the body corporate responsible for managing the strata plan. Travis brought an application for interim orders seeking to prevent the respondent from taking certain actions related to the maintenance and repair of the building. Travis alleged that the respondent was planning to carry out works that would cause significant damage to his unit. The respondent denied Travis's claims and argued that the works were necessary and would not cause any damage to Travis's unit.

In response to the application, the respondent provided evidence to demonstrate that the works were necessary to address structural issues with the building. The respondent also argued that Travis's claims were unfounded and that the works would not cause any damage to Travis's unit. Travis did not provide any evidence to support his claims and did not file a sworn statement in support of his application.

This matter came before the court as an application for interim orders. The application was heard by a judge of the Supreme Court of New South Wales. The court considered the evidence and submissions provided by both parties and dismissed the application. The court found that Travis had not made out a prima facie case for the relief sought and that the respondent was entitled to carry out the necessary works. The court also noted that Travis had not provided any evidence to support his claims and had not filed a sworn statement in support of his application.

Decision

Reasons for decision

Issues
1. What principles should be applied when considering an application for interim orders in strata title proceedings?
2. Has the applicant made out a prima facie case for the relief sought?
3. Are the works proposed by the respondent necessary and will they cause damage to the applicant's unit?

Held
1. The court concluded that the principles to be applied when considering an application for interim orders in strata title proceedings were correctly articulated by the existing authority.
2. The applicant had not made out a prima facie case for the relief sought.
3. The court found that the proposed works by the respondent were necessary and would not cause damage to the applicant's unit.

Ratio Decidendi

Legal Principle Established

In Travis v The Owners Strata Plan No 48216, the court addressed the application for interim orders in strata title proceedings, considering the principles to be applied, the making out of a prima facie case, and the necessity and potential damage of the proposed works. The court first examined the principles applicable to interim orders in strata title proceedings, noting that the principles articulated in previous cases were still valid. The court emphasized the importance of a balance between the rights of all parties involved and the need to avoid unnecessary delay or expense.

Regarding the prima facie case, the court assessed the evidence and submissions presented by the applicant. The court found that the applicant had not provided sufficient evidence to establish a prima facie case for the relief sought. The court held that the applicant needed to demonstrate a strong likelihood of success on the merits to be granted interim relief, and this threshold had not been met.

Lastly, the court turned to the necessity and potential damage of the proposed works by the respondent. The court considered expert evidence and the respondent's submissions, concluding that the proposed works were necessary for the maintenance and upkeep of the strata scheme. The court was satisfied that the respondent had demonstrated that the proposed works would not cause damage to the applicant's unit, based on the evidence provided.

The ratio decidendi of this decision is that in strata title proceedings, the court will apply established principles when considering interim orders, requiring the applicant to demonstrate a prima facie case for relief. Additionally, the court will consider the necessity of proposed works and potential damage to other units when assessing interim applications. This decision follows existing authority and does not depart from prior jurisprudence on these matters.