| CITATION: | Tracey & Anor v Olinderidge Pty Ltd & Anor [2013] QCAT 401 |
| PARTIES: | Martha-lee Tracey and Todd Anthony Tracey (Applicants) |
| v | |
| Olinderidge Pty Ltd and Rodney Wagner (Respondents) |
| APPLICATION NUMBER: | BDL136-11 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 9, 10 August 2012, 7, 27 March 2013 |
| HEARD AT: | Bundaberg, Hervey Bay |
| DECISION OF: | David Lewis, Member |
| DELIVERED ON: | 5 August 2013 |
| DELIVERED AT: | Hervey Bay |
| ORDERS MADE: | 1. The respondents Olindaridge Pty Ltd and Rodney Wagner pay the applicants Martha-lee Tracey and Todd Anthony Tracey the sum of $98,600.00 within 28 days. 2. The applicants must file and serve on the respondents by 6 September 2013, any claim for their costs of the application, together with their submissions on that claim, full particulars of the amounts claimed, and copies of relevant invoices. 3. The respondents may file and serve on the applicants any submissions with respect to the claim for costs by 27 September 2013. 4. Unless the tribunal otherwise orders, the claim for costs will be decided by the tribunal on the papers, and without an oral hearing, not before 27 September 2013. |
| CATCHWORDS: | Domestic building dispute – severe termite damage – defects in slab construction – defects in termite barrier – whether infestation arose from the defects. Queensland Building Services Act 1999, s 72(8). |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Martha-lee Tracey and Todd Anthony Tracey represented by Mrs Martha-lee Tracey in person. |
| RESPONDENT: | Olinderidge Pty Ltd and Rodney Wagner represented by Mr C M Hall of Hall Lawyers. |
REASONS FOR DECISION
The applicants Mr and Mrs Tracey purchased a block of land in the attractive little seaside town of Woodgate, south of Bundaberg, in October 2001, intending to build their home there.
The respondent Olindaridge Pty Ltd (in the proceedings misnamed as Olinderidge Pty Ltd) was a licensed builder, trading as RK & CA Wagner, and Mr Wagner was its nominee and one of its directors.
On 12 November 2001, Mr and Mrs Tracey and Mr Wagner on behalf of Olindaridge as builder signed a contract for it to build a house for them. Construction began at about the same time, and practical completion was reached on 21 December 2001. The house was a typical low set brick veneer building on a concrete slab.
While the builder was the company Olindaridge, the construction was carried out by Mr Wagner and of course the builder’s subcontractors. One of those was Termimesh. Its role was to install a product called termimesh around the perimeter of the slab, and to penetrations in the slab. The product is a stainless steel mesh, which forms part of the physical barrier against termite penetration. The other part of that barrier is the slab itself.
In April 2008, the Traceys noticed odd things about their house. The cornices were dropping in places, and doors were binding. They did not understand the problem. However in September that year they discovered what looked like dirt coming…
Continue reading Tracey v Olinderidge Pty Ltd
Sign in free to access the full text
- AGLC
- Tracey v Olinderidge Pty Ltd [2013] QCAT 401
- Case
- [2013] QCAT 401
- Decision Date
CaseChat Overview and Summary
The tribunal found that the evidence pointed to two points of entry for the termites: a hole in the ensuite shower floor and a point near a vent pipe close to the main bathroom. The respondents argued that these points had not been conclusively proven as entry points and that there may have been other causes of the infestation. The tribunal rejected these arguments, finding that the evidence overwhelmingly supported the applicants' case and that the respondents were liable for the damage caused by the termite infestation due to the defects in construction.
The tribunal calculated the amount of compensation to be awarded to the applicants. It considered various quotes for rectification costs and ultimately decided on an amount of $93,000, with an additional 10% allowance for contingencies. The tribunal also allowed $3,000 for alternative accommodation during the reconstruction and $2,600 for termite treatment costs. The tribunal ordered the respondents to pay the applicants the sum of $98,600 within 28 days, and set out procedures for the applicants to claim their costs and for the respondents to respond to that claim.
The tribunal found that the respondents owed a duty of care to the applicants and were in breach of that duty, resulting in the termite damage to the house. The applicants were awarded compensation in the amount of $98,600, to be paid within 28 days of the decision. The tribunal also set out procedures for the applicants to claim their costs and for the respondents to respond to that claim.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.