Total Lifestyle Windows Pty Ltd v Aniko Constructions Pty Ltd

Link copied
Case Copied 16 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Total Lifestyle Windows Pty Ltd v Aniko Constructions Pty Ltd & Anor [2021] QSC 92

PARTIES:

TOTAL LIFESTYLE WINDOWS PTY LTD

(applicant)

v

ANIKO CONSTRUCTIONS PTY LTD

(first respondent)

COLIN HAMMOND BOND

(second respondent)

FILE NO/S:

BS No 3436 of 2020

DIVISION:

Trial Division

PROCEEDING:

Application

ORIGINATING COURT:

Supreme Court of Queensland

DELIVERED ON:

10 May 2021

DELIVERED AT:

Brisbane

HEARING DATE:

2 April 2020, further submissions filed 11 and 18 February 2021

JUDGE:

Martin J

ORDER:

1. It is declared that the decision of the second respondent dated 15 March 2020 in relation to adjudication matter QBCC 733622 is void to the extent of paragraphs 48 to 65, 66 to 84, 85(b), 85(c), 86 and 87 of the decision.

2.   The applicant’s adjudication application dated 15 March 2020 be remitted to the second respondent to be decided according to law.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where adjudicator determined against claimant’s payment claim to reach adjudicated amount of nil – whether respondent’s reasons were “new reasons” not raised in payment schedule – whether adjudicator, in improperly considering new reasons, fell into jurisdictional error – whether adjudicator, failing to consider a relevant document, fell into jurisdictional error

Building Industry Fairness (Security of Payment) Act 2017, s 69, s 82, s 88, s 98(3)

Acciona Agua Australia Pty Ltd v Monadelphous Engineering Pty Ltd (2020) 4 QR 410

John Holland Pty Ltd v TAC Pacific Pty Ltd [2010] 1 Qd R 302

COUNSEL:

M R Bland for the applicant
S M McNeil for the first respondent

No appearance for the second defendant

SOLICITORS:

QBM Lawyers for the applicant
Short Punch & Greatorix for the first respondent

No appearance for the second respondent

  1. In June 2018, the plaintiff (Total) and the first defendant (Aniko) entered into an agreement under which Total was to supply and install aluminium framed windows and doors and internal sliding aluminium doors to an apartment building being constructed in Labrador.

  2. Total made a claim against Aniko for certain payments for work said to have been done and for expenses incurred. Aniko denied that it was liable and that led to Total making an adjudication application under the Building Industry Fairness (Security of Payment) Act 2017 (the Act). Pursuant to the provisions of the Act, an adjudicator was appointed.

  3. The three claims considered by the adjudicator were:

    (a)for work undertaken on levels 13 and 14 of the building,

    (b)for retention money, and

    (c)for loss or expense incurred because of Aniko’s removal of the work from Total pursuant to s 98(3) of the Act.

  4. The adjudicator found in favour of Aniko on each of the claims and held that there was no payment required to be made by Aniko to Total.

  5. The issues which arise on this application by Total are whether:

    (a)the adjudicator’s determination of the claim with respect to retention money was…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Total Lifestyle Windows Pty Ltd v Aniko Constructions Pty Lt... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] QSC 92
Decision Date

CaseChat Overview and Summary

In the case of Total Lifestyle Windows Pty Ltd v Aniko Constructions Pty Ltd, the applicant contested the adjudicator's decision that resulted in a zero amount for their payment claim. The dispute was lodged with the Queensland Civil and Administrative Tribunal, which referred the matter to the Supreme Court of Queensland for determination of jurisdictional error. The key issues for the court to decide were whether the adjudicator considered new reasons not raised in the payment schedule and whether the adjudicator failed to consider a relevant document, both of which could constitute jurisdictional error.

The court found that the adjudicator had indeed made three jurisdictional errors. Firstly, the adjudicator considered a new reason concerning the claim for retention money that had not been raised in the payment schedule, which was a breach of the statutory requirements. Secondly, the adjudicator also considered a new reason concerning the claim for loss or expense for removal of work. Lastly, the adjudicator failed to consider a relevant document concerning the same claim for loss or expense for removal of work. The court held that these errors rendered the adjudicator's decision invalid.

The court declared the decision of the adjudicator void to the extent of the identified paragraphs and remitted the applicant's adjudication application to be decided according to law. This decision highlights the importance of adherence to statutory requirements and the potential consequences of failing to do so in adjudication proceedings.

Orders

Orders of the court

1. It is declared that the decision of the second respondent dated 15 March 2020 in relation to adjudication matter QBCC 733622 is void to the extent of paragraphs 48 to 65, 66 to 84, 85(b), 85(c), 86 and 87 of the decision.

2. The applicant’s adjudication application dated 15 March 2020 be remitted to the second respondent to be decided according to law.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

The Applicant’s case for jurisdictional error may be categorised in the following way:(a)First jurisdictional error: consideration of a new reason concerning the claim for retention money;(b)Second jurisdictional error: consideration of a new reason concerning the claim for loss or expense for removal of work; and(c)Third jurisdictional error: failure to consider a relevant document concerning the claim for loss or expense for removal of work.The power to set aside an adjudicator’s decision on the ground of jurisdictional error An adjudicator’s decision can be reviewed for jurisdictional error and this Court can grant declaratory relief based on the invalidity of the decision.[1][1]Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd [2012] 1 Qd R 525, 550-556 [67]-[80] per White JA (McMurdo P and Chesterman JA agreeing). In Acciona Agua Australia Pty Ltd v Monadelphous Engineering Pty Ltd[2] Bond J meticulously analysed the principles which guide review on the basis of jurisdictional error. I respectfully agree with that analysis and will apply it in the consideration of the grounds advanced by Total.[2](2020) 4 QR 410 at 422-428 [32]-[42].First jurisdictional error Total submitted that the adjudicator did not comply with s 88(3) of the Act because he considered, and gave effect to, a reason he was required not to consider. As a result, so far as the claim for retention money is concerned, the adjudicator failed to exercise his jurisdiction within the limits of his authority. The adjudicator gave a nil value to Total’s claim for retention money for several reasons including that, on its proper construction, cl 18 of the construction contract afforded the right to Aniko (but not Total) to terminate the construction contract. Total contended that that reason was included in the adjudication response, but it had not appeared in the payment schedule. First, what did the adjudicator decide? In his reasons, the adjudicator says:“[60] I have reviewed the submissions from both the parties and agree with the respondent’s position that Clause 18 of the Contract afforded the right to the respondent to terminate the Contract and not the claimant.[61]At paragraph 120 of the Adjudication Application states “these breaches by the respondent justified termination by the claimant.[62]I concur with the Respondent’s position that the Contract was terminated by the Claimant and it follows, that the criteria of clause 18 has not been met to avail the Claimant of the relief it seeks.[63]I also agree that Clause 16 provides that the parties must agree to alter the Defects Liability Period and has no such agreement has been demonstrated, I conclude that the Defects Liability Period is 52 weeks.[63]Hence, I concur with the respondent’s position that the claim for Release of Retention is premature.[64] Therefore, I value the Release of Retention as NIL” Secondly, was that ground – the application of cl 18 – contained in the payment schedule? I conclude that it was not, for the following reasons.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.