Medium Neutral Citation: Tonk Sydney Pty Ltd v ILend Capital Pty Ltd [2024] NSWSC 1350 Hearing dates: 21 & 22 October 2024 Decision date: 25 October 2024 Jurisdiction: Equity Before: Richmond J Decision: See [103]
Catchwords: CONTRACTS — Formation — Intention to create legal relations
CONTRACTS — Formation — Condition precedent
CONTRACTS — Construction — Inconsistent provisions
CIVIL PROCEDURE — Hearings — Application for adjournment
Legislation Cited: Competition and Consumer Act 2010 (Cth), Sch 2 – Australian Consumer Law
Evidence Act 1995 (NSW)
Personal Properties Securities Act 2009 (Cth)
Real Property Act1900 (NSW)
Civil Procedure Act 2005 (NSW)
Cases Cited: Air Great Lakes Pty Ltd v KS Easter (Holdings) Pty Ltd (1985) 2 NSWLR 309
Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99; [1873] HCA 36
Ermogenous v Greek Orthodox Community of SA Inc (2002) 209 CLR 95; [2002] HCA 8
Hamod v State of New South Wales [2011] NSWCA 375
McGowan v Commissioner of Stamp Duties [2002] 2 Qd R 499; [2001] QCA 36
Raftland Pty Ltd as Trustee of Raftland Trustv Commissioner of Taxation (2008) 238 CLR 516; [2008] HCA 21
Taylor v Dexta Corp Ltd [2006] NSWCA 310
GEC Marconi Systems Pty Ltd v BHP Information Technology Pty Ltd (2003) 128 FCR 1; [2003] FCA 50
Texts Cited: NC Seddon & RA Bigwood, Cheshire & Fifoot Law of Contract (12th Australian Edition, 2023, LexisNexis Australia)
JD Heydon, Heydon on Contract (2019, Lawbook Co)
P Herzfeld & T Prince, Interpretation (2nd ed, 2020, Lawbook Co)
Category: Procedural rulings Parties: Tonk Sydney Pty Ltd (First Plaintiff)
ILend Capital Pty Ltd (First Defendant)
JDC Project Management Pty Ltd (Second Plaintiff)
Domenico Ciliegi (Third Plaintiff)
Matthew Martino (Fourth Plaintiff)
Marwan Salim (Second Defendant)Representation: Counsel:
Solicitors:
S Reuben (Plaintiff)
Pitcher Walton Lawyers (Plaintiff)
File Number(s): 2022/00259521 Publication restriction: Nil
JUDGMENT
-
These proceedings concern a dispute between the plaintiffs and the defendants as to whether the plaintiffs are liable to the first defendant, ILend Capital Pty Ltd (ILend), to pay the amounts of $173,800 and $316,800 each described as a ‘brokerage fee’ and an amount of $33,000, described as a ‘commitment fee’, together with interest for late payment.
-
ILend claims the amounts pursuant to two alleged agreements (together, the Mandates):
The ‘brokerage fee’ of $173,800 is said to be payable pursuant to an agreement entitled ‘Mandate, Brokerage Agreement and Irrevocable Authority to Pay on First Drawdown or Settlement, whichever occurs first’ dated 15 March 2022 between the plaintiffs and ILend, relating to a proposed loan of $7,900,000 by a third party to the first and second plaintiffs (Mandate 1);
The ‘brokerage fee’ of $316,800 and the ‘commitment fee’ of $33,000 is said to be payable pursuant to another agreement also entitled ‘Mandate, Brokerage Agreement and Irrevocable Authority to Pay on First Drawdown or Settlement, whichever occurs first’ and dated 15 March 2022 between the plaintiffs and ILend, relating to a proposed…
Keep reading for free
Create a free CaseChat account to read Tonk Sydney Pty Ltd v ILend Capital Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NSWSC 1350
- Decision Date
CaseChat Overview and Summary
The court examined the communications between the parties to assess whether there was a mutual intention to create legal relations. It found that the correspondence indicated an intention to be bound, despite the absence of a formal written agreement. The court also considered whether certain conditions precedent, such as the satisfactory completion of due diligence, had been fulfilled. After reviewing the evidence, the court concluded that the condition precedent had not been satisfied, thus rendering the contract unenforceable. Furthermore, the court addressed the inconsistency between the draft agreement and other communications, determining that the terms in the draft agreement took precedence. Lastly, the court assessed the application for adjournment, finding it was not necessary to grant an adjournment based on the evidence and submissions presented.
The Federal Court held that while the parties had the intention to create legal relations, the absence of a completed condition precedent rendered the contract unenforceable. The court found in favour of Tonk Sydney, ruling that the contract was not binding due to the unfulfilled condition precedent. The court further clarified the precedence of terms within the draft agreement over other communications. The application for adjournment was dismissed, and no orders were made in relation to the adjournment.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.