TME Group Pty Ltd v H Rolf Engineering Services Pty Ltd

Case

[2012] WADC 173

12 DECEMBER 2012

No judgment structure available for this case.

TME GROUP PTY LTD -v- H ROLF ENGINEERING SERVICES PTY LTD [2012] WADC 173
Last Update:  13/12/2012
TME GROUP PTY LTD -v- H ROLF ENGINEERING SERVICES PTY LTD [2012] WADC 173
Jurisdiction: DISTRICT COURT OF WESTERN AUSTRALIA   Citation No: [2012] WADC 173
Case No: CIV:2891/2008   Heard: 11, 12, 26 & 27 APRIL & 4 SEPTEMBER 2012
Coram: WAGER DCJ   Delivered: 12/12/2012
Location: PERTH   Supplementary Decision:
No of Pages: 35   Judgment Part: 1 of 1
Result: Preliminary issues determined
[Click here for Judgment in Adobe Acrobat Format ]
Parties: TME GROUP PTY LTD
H ROLF ENGINEERING SERVICES PTY LTD

Catchwords: Contract partly oral partly written Determination of preliminary issues Scope of works Was time of the essence Was the contract an entire contract
Legislation: Nil

Case References: Attorney General of Botswana v Aussie Diamond Products Pty Ltd [No 3] [2012] WASC 141
BP Refinery (Western Port) Pty Ltd v Hastings Shire Council (1977) 180 CLR 266
Cordon Investments Pty Ltd v Lesdor Property Pty Ltd [2012] NSWCA 184
Douglas v Cicirello [2006] WASCA 226
Masterton Homes Pty Ltd v Palm Assets Pty Ltd [2009] NSWCA 234
McCourt v Cranston [2012] WASCA 60
MR & RC Smith Pty Ltd t/as Ultra Tune (Osborne Park) v Wyatt [No 2] [2012] WASCA 110
Reed v Peridis [2005] SASC 136



JURISDICTION : DISTRICT COURT OF WESTERN AUSTRALIA

                  IN CIVIL
LOCATION : PERTH CITATION : TME GROUP PTY LTD -v- H ROLF ENGINEERING SERVICES PTY LTD [2012] WADC 173 CORAM : WAGER DCJ HEARD : 11, 12, 26 & 27 APRIL & 4 SEPTEMBER 2012 DELIVERED : 12 DECEMBER 2012 FILE NO/S : CIV 2891 of 2008 BETWEEN : TME GROUP PTY LTD
                  Plaintiff

                  AND

                  H ROLF ENGINEERING SERVICES PTY LTD
                  Defendant

Catchwords:

Contract partly oral partly written - Determination of preliminary issues - Scope of works - Was time of the essence - Was the contract an entire contract

Legislation:

Nil

Result:

Preliminary issues determined


(Page 2)

Representation:

Counsel:


    Plaintiff : Mr T H Offer
    Defendant : Mr G M Abbott

Solicitors:

    Plaintiff : Lewis Blyth & Hooper
    Defendant : Hopgood Ganim


Case(s) referred to in judgment(s):

Attorney General of Botswana v Aussie Diamond Products Pty Ltd [No 3] [2012] WASC 141
BP Refinery (Western Port) Pty Ltd v Hastings Shire Council (1977) 180 CLR 266
Cordon Investments Pty Ltd v Lesdor Property Pty Ltd [2012] NSWCA 184
Douglas v Cicirello [2006] WASCA 226
Masterton Homes Pty Ltd v Palm Assets Pty Ltd [2009] NSWCA 234
McCourt v Cranston [2012] WASCA 60
MR & RC Smith Pty Ltd t/as Ultra Tune (Osborne Park) v Wyatt [No 2] [2012] WASCA 110
Reed v Peridis [2005] SASC 136


(Page 3)

1 WAGER DCJ: H Rolf Engineering Services Pty Ltd (HRES) were engaged by Barrick Mining to assess concrete remediation work that they needed to have performed at the Plutonic Gold Mine processing plant. TME Group Pty Ltd (TME) conducted business in concrete remediation. TME entered into a contract with HRES to carry out the required remediation work at the Plutonic gold mining process plant. The parties agreed that a contract in relation to the remediation work was formed on or about 30 August 2007 and that the agreement was partly written and partly oral however the terms of the contract are in issue.

2 This matter was listed as a trial of preliminary issues to resolve 20 questions relevant to the contract proposed by the parties in an agreement of orders dated 20 June 2011.

3 Although the preliminary hearing related to 20 questions, once the trial of preliminary issues had commenced it became clear that those questions were not the relevant ones. Both parties sought to amend their pleadings and vary the questions to be answered. After a protracted period I made orders on 4 September 2011 allowing the parties to have leave to file substituted preliminary issue questions and to file a minute of amended substituted statement of claim and an amended substituted defence and counterclaim. The filed documents stand as substituted documents for the purposes of these proceedings.

4 Accordingly the matters to be determined at the trial of preliminary issues are:

      1. the identification of the scope of the works that was to be performed pursuant to the contract (the Contract);

      2. the identification of the works, if any, that were agreed to be performed pursuant to any of the 'variations' and which were not included in the works under the Contract;

      3. whether the Contract included a term that the plaintiff was to perform the works in accordance with Australian standards or industry standards;

      4. whether the Contract included a term that all works had to be carried out by skilled tradespeople or under the supervision of a skilled tradesperson;

      5. whether the Contract included a term that all works had to be completed by the end of the shutdown of the processing operation

(Page 4)
          on the site, and whether, if it was, time was of the essence in that regard;
      6. whether the Contract included a term that the works be carried out in accordance with a fixed timetable and whether, if it was, time was of the essence in that regard;

      7. whether the Contract was an 'entire' or 'divisible' agreement; and

      8. whether the rate for any of the 'variations' planned as in 'variations 4, 4A and 4B' was fixed by agreement or whether it was determined on some other basis and, if so, how was the relevant rate to be determined.

5 I will set out the agreed factual history between the parties, the evidence led in relation to matters in dispute and my findings in relation to the eight matters to be determined.


Factual history - matters not in dispute

6 In 2006 and 2007 Barrick Mining operated the Plutonic gold processing plant. The processing plant had been constructed in 1994 and was situated 600 km north-east of Perth. Structurally the plant consisted of two ball mills, the east ball mill and the west ball mill, a semi-autogenous grinding mill (SAG) and a primary crusher that contained a steel structure known as a run of mine (ROM) bin.

7 In 2006 Barrick Mining engaged Savcor Finn Pty Ltd to perform a reinforced concrete condition survey and prepare a report about the state of the concrete works at the plant (report August 2006, exhibit 1).

8 The report concluded that there was concrete deterioration at the processing plant and that remedial resolution to areas of concrete deterioration and corrosion of embedded reinforcing steel needed to be completed in the near future to prevent further concrete deterioration.

9 The deterioration reported was noted as being expansive cracking, delamination and spalling of covered concrete associated with embedded reinforcement corrosion. It was evident in various areas along the structure but was most significant in the SAG mill (exhibit 1, page 11 and pages 3 - 5). The report recommended that conventional repairs should be undertaken utilising sacrificial anodes to optimise the repair life expectancy and delay the formation of insipient anodes. The application of an anti-chloride penetrating primer and elastomeric topcoat to the

(Page 5)
      concrete surfaces to prevent the ingress of saline process/wash water was highly recommended (exhibit 1, page 11).
10 Barrick Mining engaged HRES to perform, amongst other things, the recommended concrete remediation works at the processing plant. The director of HRES, Mr Rolf, formed the opinion that the work required on the plant included:
      (i) removal of all delaminating and spalling cover concrete;

      (ii) removal of all loose grout and all grout higher than the associated underside of all steel plates for the mill's drive trains;

      (iii) removal of all concrete subjected to impact from the ROM bin by way of a rectangular cut-out and placement of a 50 mm grout cover; and

      (iv) treatment of all exposed reinforcement steel work and the replacement of all cover concrete.

11 Mr Rolf chose to engage a sub-contractor to perform the remediation work and arranged for Mr Gray who was the manager of TME's concrete repair division to attend the site on behalf of TME in order to physically assess the work. TME was also to confirm the areas that required concrete remediation. Mr Gray attended the site in July 2007 and carried out an assessment of the areas requiring remediation by looking at the area to see if it had deteriorated or by carrying out a drummy test that involved tapping on the concrete with a hammer to determine whether it gave off a hollow sound consistent with deterioration. Mr Gray carried out the breakout work on the damaged areas with the assistance of Mr Dieter Posthausen who was an engineering consultant and the owner of DIMA Consulting that had also been engaged by HRES to determine the scope of work that needed to be undertaken in order to remediate the deteriorated concrete at the plant.

12 The areas identified by Mr Gray and Mr Posthausen were marked by paint from a spray can that was applied to the outer extent of the drummy concrete. However some other areas requiring remediation were marked with a painted cross and there were also areas that were so obviously in a poor condition that they were clearly to be the subject of remediation regardless of whether they were marked by paint or not. TME charged and was paid an hourly rate in respect of the breakout work that was carried out and completed over a three-day period in July 2007.

(Page 6)

13 While Mr Gray was carrying out the breakout work HRES invited TME to quote on the remediation work required to be carried out on the two ball mills and the SAG mill, however HRES was not clear about the precise details or quantity of work that HRES wanted performed. Mr Gray had a general idea of what was required because he had carried out the breakout work in July 2007 and had had a three-day opportunity to assess the full scope of the concrete remediation work that would have to be performed and determine the depth to which the concrete needed to be remediated.

14 Mr Gray agreed to provide a quotation in relation to the remediation work on the ball mills being quotation C61. After providing C61 Mr Gray was then asked to provide a further quotation for repairs to the primary crusher. The quotation included remediation work, the preparation of a void and the related finishing of the surface. Scaffolding was required for the work to be carried out. The quotation document prepared relating to the primary crusher was C66.

15 Mr Gray returned to the mine site again in late August 2007. At this time he was requested to provide a combined quotation in respect of all of the work to be performed. He prepared a single draft quotation being C76 that addressed the scope of works in respect of the earlier quotations and incorporated the quotation C66. The contract price proposed in respect of C76 was $138,000 plus GST.

16 Following the presentation of C76 to HRES Mr Gray and Mr Rolf carried out a further inspection of the site and, as a result of discussions during their inspection, Mr Gray increased the quotation price by $12,000 to $150,000 plus GST.

(Page 7)

17 The budget estimate for (C66) was as follows:

(Page 8)
(Page 9)
      18 The final budget estimate (C76) was as follows:
(Page 10)
19 There is no dispute that C76 (incorporating C66) is the written part of the contract between the two parties. The parties also agreed that some terms of the contract were oral. The scope of the terms and the oral terms are in dispute.


The disputed issues


The evidence

20 The only evidence called at the trial of the preliminary issues was from Mr Gray on behalf of the plaintiff and from Mr Rolf on behalf of the defendant.

(Page 11)

Mr Gray

21 Mr Gray was employed from April 2007 until April 2008 as the manager of both TME's concrete repair division and the blasting and painting division. TME's core business worldwide was relining of mills. The divisions he managed were quite small, separate niche divisions. Mr Gray had skills and experience in concrete remediation having had 22 years of technical experience.

22 Mr Gray had an opportunity to assess the work required when he carried out the breakout work in July 2007 however he stated that he did not have an opportunity to assess the full scope of the concrete remediation that was required nor was the full scope of the work clarified by HRES at that time. Mr Gray said that it was only after he completed the breakout work in July 2007 that Mr Posthausen telephoned him and advised that TME would be asked to quote on the concrete remediation work however no specific details of what was required were provided over the telephone.

23 Mr Gray's evidence was that he went to the site on a second occasion in July 2007 after completing the breakout work and after preparing a first budget estimate C61 in respect of remediation work on the mills. C61 refers to a 'plutonic mine and the upcoming 3 day shutdown' consistent with an understanding that the work would have to be performed during the shutdown. The duration quoted is 'we to complete the above scope of work within 3 days'.

24 On the second occasion in July 2007 Mr Gray inspected the primary crusher and prepared TME budget estimate C66 in respect of the primary crusher. In order to prepare the C66 quotation Mr Gray calculated an estimate of the hours required to undertake the work over a four-day period taking into account the scope of the work that had been specified by HRES. Prior to the preparation of C66 Mr Gray had been advised that the mine site would be shut down for a period of 18 days so that the work on the primary crusher could be carried out because the work could only be performed when the site was shut down.

25 It is for this reason that C66 states 'We to complete the above scope of work within 4 days' in respect of the primary crusher however the words in relation to the shutdown commitment are the same as on C61, that is, plutonic mine future four-day shutdown. The word 'future' rather than 'upcoming' is used. I find that in the circumstances the meaning is identical. The duration quoted is 'we to complete the above scope of work within 4 days'.

(Page 12)

26 In cross-examination Mr Gray initially denied that he had factored in to the quotation that at least some of the work to be performed pursuant to C66 would have to be performed on nightshift, however he accepted that the TME quotation that referred to a breakdown of costs of $51,736, being an identical sum to that quoted in C66, related to quotation C66. The breakdown of costs quotation made reference to a night crew supervisor being required for 55 hours and a nightshift special applicator being required for 55 hours. In cross-examination Mr Gray conceded that the quotation in respect of nightshift was consistent with HRES requesting that at least part of the work be performed at night. The quotation also included a breakdown of labour costs for dayshift. The dayshift hours were the majority of the hours quoted. The quotation is consistent with an understanding that the work had to be performed over a four-day period with night work and day work being required. Given that 55 hours, when divided by four, provides for 14 hours each night over a four-day period was quoted.

27 Mr Gray returned to the site again after the end of July but before 30 August 2007 in order to take core samples of the concrete supporting the SAG mill. He carried out the work at the request of the maintenance manager from Barrick Mining, Mr Reynolds. Mr Gray did not receive any further direction in relation to the scope of the work from HRES relevant to the final quotation at that time.

28 On 28 August 2007 Mr Gray returned to the site again and met up again with Mr Rolf. He accepted in evidence that he had been asked to combine the quotations of C61 and C66 and he had therefore drafted budget estimate C76 in respect of all work to be performed on site. The draft C76 had a quotation price of $138,000.

29 Mr Gray took photographs of the areas where concrete remediation had to be performed and of the lead up work that had already been performed as part of the breakout contract. After either providing a copy of the draft C76 quotation to Mr Rolf or discussing the contents of it with Mr Rolf, Mr Gray and Mr Rolf carried out a further inspection of the mine site. Mr Gray stated that Mr Rolf pointed out additional minor concrete remediation repairs to be undertaken to the primary crusher and additional grout replacement works to be undertaken on the SAG mill and ball mills during the course of this inspection. Mr Gray stated that these areas identified in the final inspection had not been included in the draft C76 quotation and accordingly he redrafted C76 adding an additional cost of $12,000 to cover the additional work identified on or after 28 August 2007 so that the final estimate to carry out the full scope of work was

(Page 13)
      $150,000 plus GST. The additional sums are added to the quotation for the primary crusher wall breakout and repair and the SAG and ball mill grout removal and plate preparation.
30 In cross-examination Mr Gray rejected the proposition that the increase in the total cost of C76 was due to Mr Rolf suggesting to him that his quotation was too low and that an additional sum needed to be added to it to cover scaffolding and to ensure that TME had sufficient labour on site in order to complete all works by the end of the shutdown period. Mr Gray said that the estimated cost of scaffolding had already been included in the budget estimate C66, relevant only to the primary crusher, and that C66 was simply adopted in full in budget estimate C76. Accordingly the price of $51,736 for work to be performed on the primary crusher included the cost of scaffolding.

31 Mr Gray also said that when he prepared C66 and C76 he did not know the length of the proposed shutdown or the date of the shutdown and that he was not advised of these dates until September 2007. He anticipated there would be some work at night and he anticipated that he would do his best to complete the work in the shutdown period but he did not accept that there was a set timeframe in which the work was to be performed. His understanding at the time of drafting C76 was that the shutdown would be for 18 days. Ultimately the shutdown was for 14 days only.

32 Mr Gray accepts that the major works were planned around the shutdown and that the work on the primary crusher and the SAG mill had to be completed in the shutdown period because there would be no other opportunity to complete it. When he was advised that the shutdown was for a period of 14 days and not 18 days he accepted that the work on the SAG mill had to be completed within the 14-day period but he did not agree that all work TME had contracted to perform had to be completed by the end of the shutdown period. In relation to being bound by the shutdown period Mr Gray said (t 68):

          Not strictly no, no. As I understand it we still had time after the shutdown to finish off any lower priority works that were peripheral if you like as in not being directly under the mills and therefore not a danger to anyone.
33 Despite not being bound by a set timeframe Mr Gray stated that it was the aim of TME to complete the work as soon as possible and that he personally carried out jackhammer work, inspection supervision and coordination in order to complete the job by the end of the shutdown. He stated however (t 160) that had he known that all of the work that did (Page 14)
      not require the site to be shutdown had to be completed before the shutdown then he would have increased the price of his quotation. As a new manager with TME he did not want to get a bad name in the industry. It was important to Mr Gray to complete the job promptly but he thought that he had time after the shutdown to complete the work the subject of C76. Unlike C61 and C66, C76 refers only to the opportunity to quote for Plutonic mine. There is no reference to a shutdown. In relation to duration it states 'we anticipate completing the above scope of works within Sept/Oct shuts 18 days'.
34 Mr Gray had an excellent recall of the work that he was required to perform on the site in 2007 however his recollection of dates, meetings and conversations was vague. Mr Gray is a truthful witness. I accept that he had difficulty in remembering dates, meetings and discussions and that this is in part due to the passing of time given that the events occurred in 2007. He completed his witness statement on 16 August 2011 and gave evidence in April 2012.


Mr Rolf

35 Mr Rolf carried out a first inspection of the site with Mr Gray and confirmed the scope of the concrete remediation required at the plant. During that inspection he said that he pointed out the areas of the plant that required work and told Mr Gray that the concrete remediation needed to be performed immediately due to the criticality of the repair work. Mr Rolf said that he told Mr Gray that all work that did not require the shutdown of the plant was to be completed before the scheduled shutdown of the plant in late September/early October 2007 (witness statement dated 8 June 2010, exhibit 10).

36 Mr Rolf confirmed with Mr Gray that during the shutdown the machinery at the SAG mill would be lifted from its foundation in order to allow remediation work and that all work, except for the work to the top of the SAG mill area and the rectangular cut-out near the ROM bin (primary crusher) should be completed before the shutdown in late September/early October 2007 (witness statement dated 8 June 2010 exhibit 10, page 16 par 19).

37 Mr Rolf said that Mr Rob Taylor, a representative of Plutonic Operations Ltd, was present during the first inspection with Mr Gray and said words to the effect that all loose grout and all grout higher than the underside of each steel base plate of the SAG mill had to be removed. Mr Gray appeared to nod his head or say yes when these matters were raised.

(Page 15)

38 Mr Rolf said that he requested Mr Gray to issue separate quotations from TME for the mills and for the primary crusher area of the plant and that on or about 21 July 2007 he received from Mr Posthausen Mr Gray's quotation C61 in relation to the mills and C66 in relation to the plant's primary crusher.

39 On 28 August 2007 Mr Rolf again met with Mr Gray in order to discuss the full scope of the works. Mr Rolf requested that TME issue one single quotation in respect of all of the concrete remediation work to be performed on site. After a second inspection of the site on about 29 August 2007 that was conducted in order to clarify the scope of the works Mr Gray calculated a final inclusive quotation of $138,000 plus GST consistent with the draft quotation C76. This sum was greater than C61 added to C66. It included all of C66 but also additional work that had been identified since the time when C61 was drafted.

40 Mr Rolf said that he then asked Mr Gray to accompany him for a final inspection of the plant during which they visited the primary crusher/ROM bin area. Mr Rolf said that he pointed to the area of the plant wall behind the ROM bin which was to be cut-out and said words to the effect that sufficient safe scaffolding would need to be used to reach the area that had to be cut-out. He said that Mr Gray then said words to the effect that he had allowed approximately $10,000 to cover the costs of scaffolding for the area in the draft C76 quotation.

41 Mr Gray and Mr Rolf then continued with the inspection by walking to the SAG mill area where Mr Rolf said words to the effect that all loose grout and all grout higher than the underside of all steel base plates must be removed, all rust cleaned off the steel base plates, grout re-applied and a slot 3 mm wide and 30 mm deep cut around the perimeter of all steel base plates. Mr Rolf said that Mr Gray again responded by nodding his head and saying words like 'yes' and 'yeah'. They then walked back to the office where Mr Rolf proceeded to sketch the area to be cut out of the plant wall behind the ROM bin. Mr Rolf said that he suggested to Mr Gray that TME's quotation of $138,000 for draft C76 should be increased to $150,000 to allow TME to work efficiently to ensure that all possible work was done before the plant shutdown in late September/early October and to do the work safely without compromising on quality. Mr Rolf said that it was after this discussion that the final quotation budget estimate C76 dated 30 October 2007 that the final figure of $150,000 (an increase of $12,000) was produced by Mr Gray and provided to him.

(Page 16)

42 Mr Rolf said that prior to the shutdown in September 2007 he handed a copy of the provisional timetable for the shutdown of the plant to Mr Gray. Mr Rolf said that Mr Gray told him that he had requested more personnel from the head office of TME and that he would therefore be able to complete all of the work that did not require the site to be shutdown before the shutdown started. Mr Rolf said that a final timetable that was similar to the provisional timetable was provided to Mr Gray although Mr Gray denied that he ever received a final timetable.

43 In cross-examination Mr Rolf confirmed that although he asserted that time was of the essence in relation to the contract with TME, HRES' contracts with Barrick Mining and with Plutonic Operations Ltd did not set out that HRES was to complete the concrete remediation work by a particular date. Mr Rolf denied that when he carried out negotiations with TME those negotiations were in the same vein and that arranging work that had been identified in a report dated August 2006 approximately one year later indicated that the work was not considered urgent. He denied that there had been no discussions in relation to a requirement to complete all work by the end of the shutdown period prior to Mr Gray compiling the final C76. Mr Rolf was emphatic that there could not have been any ambiguity in relation to the need to complete the work by the end of the shutdown because he said this constantly to Mr Gray.

44 Mr Rolf said that the reason why he went around the site with Mr Gray for the third and final inspection at the end of August 2007 prior to the preparation of the final C76 document was because of his concerns about safety not because there was a need for him to clarify the scope of the works. He said that the scope of the works had already been agreed through the provisional C61 and C66. In cross-examination Mr Rolf said (t 215):

          And you say that you had this additional conversation just to be sure? --- Yes. I felt in a crusher area - looking at the scaffold plans, his price seemed very low. It just didn't - didn't make sense to me, because the scaffold itself, that cost about 10 to $20,000 if you do it right. And because of - that's the concern I have, because the price didn't seem to fit what I felt needed to be done.
45 Mr Rolf denied adding the requirement to remove loose grout and grouting higher than the underside of steel plates on the SAG mill to the scope of works during the course of the final site inspection in August 2007. He stated that the full scope of works had been made clear to Mr Gray from the beginning of the negotiations in July 2007. Mr Rolf agreed however that he went around the site with Mr Gray for the (Page 17)
      final inspection because he wanted to ensure that everything was included and he did not want to be caught with variations for 'odds and sods' afterwards as well as wanting to make sure that the work would be performed safely on site (t 215).
46 In cross-examination Mr Rolf said that he was pretty sure that he provided a portion of the major shutdown schedule that was relevant to Mr Gray. He cannot recall how it was transmitted but he believed that it was sent. He accepted that he had not included the fact that only a portion of the timetable was provided to Mr Gray in the statement Mr Rolf prepared for these proceedings. He said that he omitted to include the detail that only a portion of the timetable was provided because it had not crossed his mind that a shortened version of the document had been provided to Mr Gray until he was asked specific questions in cross-examination.

47 Mr Rolf said that the shutdown schedule was shown on the wall of his office on site via a projector and that Mr Gray and others came together to coordinate the whole framework of the shutdown. As a result of the coordination, communication, meetings and discussions he disputed that once the timetable was prepared Mr Gray would have been unaware of the dates and the length of the shutdown period.

48 I find Mr Rolf to be an honest witness however he delivered his answers in a verbose and blustery manner. He did not always answer the question that was asked in cross-examination and repeated answers that were favourable to HRES. I accept that his anxiety was in part due to this matter relating to discussions and events that are now four years old. I find that Mr Rolf's recollection of conversations is unlikely to be totally accurate because his recollection is of very clear discussions and instructions between the parties. It would be unlikely that the documentation would fail to note matters relevant to the agreement that has now become the subject of this trial if the discussions between the parties were so clear and concise and had been clear and concise from July until 30 August 2007.


The identification of the scope of the works that was to be performed pursuant to the contract

49 The written quotations are inconsistent with the scope of works being agreed in July 2007 because C61 had a price of $54,215.60 and C66 had a price of $51,736. The first draft of C76 was for $138,528 (and $51,736 is included in that sum).

(Page 18)

50 The quotation for the entire scope of works (before discussion on 30 August 2007) in relation to the areas other than the primary crusher had therefore increased from $54,215.60 to $86,792 consistent with oral agreements to carrying out a significant amount of additional work prior to the final agreement on 30 August 2007.

51 C61 and C66 refer to the work being completed within the shutdown period. The total time is seven days. However C76 does not include this requirement. C76 (both in first draft and in final draft) states that TME anticipate completing the scope of work within the 'Sept/Oct shuts 18 days'. There is no reference to starting the work prior to the shutdown period and no undertaking to complete within the shutdown.

52 In Masterton Homes Pty Ltd v Palm Assets Pty Ltd [2009] NSWCA 234, Campbell JA summarised the principles that apply to the interpretation of contracts that are partly written and partly oral. His Honour said at [90] (4) and [90] (5):

          (4) Where a contract is partly written and partly oral, the terms of the contract are to be ascertained from the whole of the circumstances as a matter of fact: [case citations omitted] …

          (5) In determining what are the terms of a contract that is partly written and partly oral, surrounding circumstances may be used as an aid to finding what the terms of the contract are: Stones v Dowler at LJ Ex 124; RR 884 per Martin B; Deane v The City Bank of Sydney at 209 per Griffith CJ, Barton and O'Connor JJ; Handbury v Nolan at 341-2 per Barwick CJ, at 346 per Stephen J, at 348 -9 per Jacobs J; Liverpool City Council v Irwin [1977] AC 239 at 253C-E per Lord Wilberforce. If it is possible to make a finding about what were the words the parties said to each other, the meaning of those words is ascertained in the light of the surrounding circumstances: Dean v The City Bank of Sydney at 209; Handbury v Nolan at 341-2, 346, 348-9. If it is not possible to make a finding about the particular words that were used (as sometimes happens when a contract is partly written, partly oral and partly inferred from conduct) the surrounding circumstances can be looked at to find what in substance the parties agreed: County Securities v Challenger Group Holdings at [7] - [8] per Spigelman CJ.

53 In submissions both parties referred to the interpretation of written contracts. I have considered the matters recently raised by Templeman J in McCourt v Cranston [2012] WASCA 60 however the current contract is not solely in writing.

(Page 19)

54 Given that the contract is partly written and partly oral I have considered the surrounding circumstances in order to determine the terms of the contract consistent with the approach of Campbell JA.

55 The discussions in relation to the scope of works are essentially agreed. The parties disagree on the timing of their discussions in that Mr Rolf said that the primary crusher rectangular cut-out was raised early in negotiations whereas Mr Gray referred to these discussions occurring immediately prior to the final draft of C76 however ultimately there is very little dispute about the scope of works.

56 I find that the scope of works included that TME:

      1. Mobilise the crew and equipment to site, attend inductions, complete JSA Toolbox QA.

      2. In areas identified of the east ball mill, west ball mill, SAG mill and primary crusher breakout defective concrete to a reasonable depth behind the reinforcing bar, replace reinforcement where necessary and carry out a basic blast steel reinforcing. Apply Nitoprime Zincrich or equivalent primer to blasted steel. Apply Shotcrete micro-concrete grout or high build repair mortar as necessary and apply Concure WB compound where necessary.

      3. Remove concrete and reinforcing bar from the north wall of the primary crusher to leave a void that measures 8 m by 2 m and smooth off the edges, sandblast and treat any exposed reinforcing bars and apply appropriate products to the edges of the cut-out.

      4. Strip any formwork from treated area; and immobilise from site.

57 TME was also required to remove concrete and reinforcing bar from the northern wall of the primary crusher to leave a void of approximately 8 m by 2 m and smooth off the edges, sandblast and treat any reinforcing bars that were exposed, apply an appropriate product to the edges of their rectangular cut-out.


The identification of the works, if any, that were agreed to be performed pursuant to any of the 'Variations' and which were not included in the works under the contract

58 The parties accept that if the work performed had not been identified as being within the scope of works with the contract then it was additional to the contract and did not alter or affect the party's obligations under the contract.

(Page 20)

Variation 1

59 The parties agreed that TME would perform variation 1 for the price of $5,322 (including GST).


Variation 2

Description
Units
Charge Rate
Total Costs
Rhesure 58 fibres
60.00
$9.50
$570
Tetraguard AS21
(shrinkage reducing admixture)
60.00
$8.50
$510
Rhocure 736
(internal curing compound)
40.00
$7.00
$280
Total
$1,360

60 Barrick Mining operated, a concrete batching plant near to the site and orally advised TME that it could use the batched concrete when carrying out the remediation work. TME stated in C76 that 'TME will be responsible for the provision of consumables'. C76 did not state that HRES had an obligation to provide concrete.

61 During one of the inspections on site prior to 30 August 2007, Mr Gray provided a blank copy of TME's concrete works sheet to Mr Posthausen. The blank sheet set out 15 topics relevant to concrete. Mr Gray accepted that it was very likely that he said the words that have been handwritten onto the concrete works sheet and he accepts that the words handwritten onto it are consistent with the discussion between him and Mr Posthausen.

62 The words noted include 'concrete/shotcrete MP and 40' and 'Renderoc HB70 trowelled, Renderoc LA55 poured'. These notes are consistent with the names and types of treatment that would be applied to concrete. The words 'tests with batching plant' are also written on the sheet.

63 Problems arose when TME applied the concrete from the batch onsite during remediation. Mr Gray sent an email to Mr Rolf (exhibit 7, 4 September 2012) suggesting a solution:

(Page 21)
          From: TME - Wayne Gray

          Sent: 11 September 2007, 5.23 pm

          To: (Harald Rolf)

          Cc: (Peter Brown)

          Subject: Concrete Shrinkage Controls

          Attachments: Rheocure 736.pdf; Tetraguard AS21.pdf; Rheosure 58.pdf

          Harald,

          Following unsatisfactory early age shrinkage of the sprayed concrete at Plutonic last Thursday night we nominate the following controls in an effort to ensure shrinkage of this magnitude does not occur in future.

          1. The use of a polypropylene fibre to provide crack control;

          2. The use of a shrinkage reducing agent;

          3 The use of an internal curing admixture;

          4. Thorough Wet Hessian curing through the first 24 hours and beyond.

          Nominated products and dosages are as follows:

          1. Rheosure 58 - polypropylene fibre (8 kilograms per metres cubed)

          2. Tetraguard AS21 - shrinkage reducing agent (6 litres per metre cubed)

          3. Rheocure 736 - internal curing admixture (5 litres per metres cubed)

          I attach technical datasheets for these DASF (formally known as MBT) products. Our aim would be for us to add these products on-site to the batch concrete and agitate for the nominated period.

          This would place the control in our hands rather than with the concrete batch plant.

          Regards,

          Wayne Gray

64 Mr Gray stated in evidence that he had provided information in the email in relation to the price of the provision of the admixtures because HRES would ultimately be paying for the products in order to ensure that the concrete was up to standard. However in cross-examination Mr Gray acknowledged that he did not refer to pricing in the email.

(Page 22)

65 Mr Rolf said in his responsive witness statement at par 28:

          During one of the inspections, most probably the first inspection, I said to Wayne Gray words to the effect that the plaintiff was responsible for the quality of the concrete they obtained from the onsite batching facilities. Wayne Gray then said to me words to the effect that he agreed and explained that he would follow TME's usual quality assurance procedures and hand me TME's concrete pour check sheet.
66 The concrete batching plant was on site because it was convenient. TME however always had the responsibility of ensuring that the concrete was satisfactory so that the work that they had been contracted to perform would be of a reasonable standard. I find that TME is responsible for the charges listed on variation 2 because:
      1. In C76, TME stated that it would be responsible for the provision of consumables.

      2. I accept that Mr Gray told Mr Rolf that he would follow TME's usual quality assurance procedures.

      3. The notes on the concrete pour check sheet are consistent with Mr Gray giving an undertaking prior to 30 August 2007 that admixtures would be used if required.

      4. The email from Mr Gray to Mr Rolf dated 11 September 2007 does not refer to cost. It is consistent with TME taking control of the quality of the concrete. There is no suggestion in the email that HRES would have this obligation.

67 Variation 2 is not work performed in addition to the contract.


Variation 3

68 HRES states in par 15(c)(iii) further amended substituted defence and counterclaim dated 4 September 2012:

          (iii) the defendant denies that the plaintiff has any entitlement to that planned by the plaintiff in 'variation 3' and says that the plaintiff and defendant made an agreement that the defendant would reimburse the plaintiff for the cost of the hire of concrete agitator truck for three days at the cost of $6,600 (inclusive of GST).
69 HRES has agreed to reimburse TME the sum of $6,600 (inclusive of GST).

(Page 23)

Variation 4

Description
Units m2
Charge Rate
Total Costs
Southern Plinth
2.50
$3,500
$8,750
Southern Plinth
1.90
$3,500
$6,650
Pinion Motor (Conbextra EP65 Apoxy)
5.00
$350
$1,750
Total
$17,150

70 Mr Gray conceded in cross-examination (ts 101) that the portion of the variation claim relevant to Pinion Motor (Conbextra EP65 Apoxy) at a cost of $1,750 is not a variation and is included in the scope of the works.

71 HRES conceded that the area of the southern plinth relating to 2.5 sqm at a cost of $8,750 is not within the scope of the works and is therefore a properly claimable variation although the rate charged for that work is not agreed between the parties.

72 In his signed statement, Mr Rolf said at pars 223 – 225 (exhibit 2):

          As each further area requiring concrete remediation was made known to me, I pointed this out to Rolf and asked him 'do you want us to break these out, or do you want us to leave them?'

          In all instances Rolf authorised me to break out the area I had indicated to him and acknowledged on each occasion that the additional breakout would be a variation.

          Rolf asked me when an initial additional area for breakout was pointed out to him, words to the effect 'what will that cost?' and I said '$3,500 for every additional square metre is TME's rate'. That rate was exclusive of GST.

          I do not recall Rolf's specific response to the $3,500 per sqm rate but he gave me the go ahead to break out that initial area at that price. Thereafter when additional areas were discovered, I had individual discussions with Rolf and on those further occasions, Rolf gave me an instruction to proceed with a further concrete breakout but the rate of $3,500 was not again discussed.

(Page 24)

73 Mr Rolf denied that he agreed to the rate of $3,500 per sqm and stated that the rate was unreasonable.

74 I do not accept that Mr Rolf agreed to a rate of $3,500 per sqm for each and every variation because it is a sum that is greater than a reasonable rate that would be charged per square metre. There is no evidence of the exact rate per square metre in respect of C76 however Mr Rolf's evidence in cross-examination is that if a rate of $3,500 applied to each square metre of the contract then that would mean that the contract would cost $800,000 to $900,000. Given that the cost of the contract including scaffolding and other matters is $150,000 I accept that $3,500 is not a reasonable rate and that it is not a rate that would have been accepted by Mr Rolf. Mr Rolf suggested a rate of $1,500 to $1,700 would be reasonable however there is no evidence other than Mr Rolf's opinion that this sum is a reasonable rate. Given the ongoing oral discussions about the work to be performed, the remote location of the mine site and HRES's request that the variations be performed I find that it was an implied condition that if TME agreed to carry out a variation then a reasonable rate applied to the work performed by way of variation however I am not in a position to set a rate on the evidence I have seen and heard.

75 The 1.9 sqm relating to the southern plinth was the subject of a hand drawn plan by Mr Gray (exhibit 8). Mr Gray said that it became apparent in the course of removing the concrete that the deterioration of the concrete extended beyond the area that had been marked up and therefore he made the calculation in respect of the additional 1.9 sqm. He accepted that the area showed some exposed reinforced bar consistent with it being part of the scope of the works but said that the eventual depth and width of the area had not been clear prior to commencing the work. He claimed that the area was therefore a variation.

76 I accept that Mr Gray's evidence in relation to the workings on-site because his recollection was clear and he had a good recollection of the work performed although he did not have a good recollection of the dates, meetings and identities who attended the meetings during the course of negotiations and work on site. Mr Gray was able to clarify that he had measured the area of 1.9 sqm once he was shown the drawing of exhibit 8 during the course of cross-examination. Prior to considering exhibit 8, Mr Gray gave an estimate as to how he had determined the size of the variation by multiplying the width by the height, given that both methods provided a similar calculation of 1.9 sqm. Rather than the two

(Page 25)
      explanations diminishing Mr Gray's credibility in relation to the area I find that, given the two answers were very similar, it supports the claim.
77 The 1.9 sqm southern plinth variation is additional to the contract. A reasonable charge rate applies.


Variation 4A

Description
Units m2
Charge Rate
Total Cost
Motor support
4.25
$3,500
$14,875
Back wall NE corner
0.80
$3,500
$2,800
North wall corner
0.75
$3,500
$2,625
$20,300

78 HRES admit that the motor support area, being 4.25 sqm was not included in the contract and was remediation work in the vicinity of the ball mill that Mr Rolf recalled as being outside the scope of the works. A reasonable rate of remuneration applies to the 4.25 sqm.

79 The 0.8 sqm and 0.75 sqm portions are not identified in the photographs tendered in evidence. Both parties acknowledged that the tendered photographs showed most of the areas that were the subject of the contract. Mr Gray agreed in cross-examination that it was possible that the area was part of the scope of the works.

80 Counsel for TME relied on the absence of a photograph to support his submission that the areas of work were performed and were variations and submitted that I should be satisfied on the balance of probabilities that Mr Gray had proven the variations. However given Mr Gray's inconclusive evidence about the two areas, I am not satisfied on the balance of probabilities that they are variations. The area of 0.8 sqm and 0.7 sqm are part of the contract.

(Page 26)

Variation 4B

Description
Units m2
Charge Rate
Total Cost
South wall
1.75
$3,500
$6,125
North wall corner
0.75
$3,500
$2,625
$8,750

81 In his responsive witness statement at par 42, page 14 Mr Rolf admitted that the area of 1.75 sqm was not included in the scope of works. Mr Rolf's evidence was that the 0.75 m was included in the scope of works.

82 Mr Gray in cross-examination in respect of the 0.75 sqm relevant to the north wall corner (ts 139) agreed that it was possible that the area had been identified before the end of August during one of the inspections. I am not satisfied that TME has discharged its onus of proving the variation of the 0.75 sqm area.

83 In respect of the variation to the south wall being an area of 1.75 sqm a reasonable charge rate applies.


Variation 5

84 Variation 5, 5A, 5B and 5C are admitted as variations to the contract (amended defence and counterclaim 15 and 8).


Variation 6, 6A and 6B

Description
Qty
Price
GST
Total
C076 - VARIATION 6

ABRASIVE BLAST AND PROTECTIVE COATING FOR PRIMARY CRUSHER STEEL PLATE

1
2,010.80
201.08
$2,211.88

(Page 27)

Variation 6A

Description
Qty
Price
GST
Total
C076 - VARIATION 6A

SECOND COAT OF PAINT TO STEEL PLATE FOR PRIMARY CRUSH

1
729.80
72.98
$802.78

85 Variations 6 and 6A are admitted as variations because they are not included in the contract price however Mr Rolf has asserted that the work was only required due to TME's non-performance of work in accordance with the contract (amended defence and counterclaim 15(iv)).

86 In relation to variation 6 Mr Rolf said in evidence at ts 259:

          I did not expect to be charged, I expected it to be taken into consideration of work not completed on the end.
87 He also stated that he did not agree to the price being $65 per hour and that a non-supervisor rate of $48 per hour should apply.

88 Although Mr Rolf does not agree that he should have been charged for the work in variation 6 he does not dispute that it was a variation. There is no evidence that a supervisor rate should apply. The variation is allowed but at the rate of a non-supervisor being $48 per hour.

89 Similarly with variation 6A Mr Rolf conceded that the work performed was a variation. He disputed the charge out rate. There is no evidence that a supervisor rate should apply and accordingly a non-supervisor rate of $48 per hour is appropriate.


Variations 7, 7A and 7B

90 Variation 7, 7A and 7B are admitted as variations to the contract to the value of $5,435 (inclusive of GST) (amended defence and counterclaim 15(x)).

(Page 28)

Variations 8, 8A, 8B, 8C and 8D

91 Variations 8, 8A, 8B, 8C and 8D are admitted as variations to the contract to the value of $5,394 (inclusive of GST) (amended defence and counterclaim par 15(xi)).


Whether the contract included a term that the plaintiff was to perform the works in accordance with Australian standards or Australian industry standards


Australian standards

92 Concreting issues are covered by Australian standards however Mr Gray does not recall any discussion about Australian standards with any representatives of HRES. Mr Gray said (t 65):

          Our standards would normally exceed the Australian standards so we think we would go beyond Australian standards anyway in a lot of instances.
93 In evidence Mr Gray did not accept the proposition that TME would hold itself out as being the leader in the industry however in cross-examination he accepted that quotation C76 contained the paragraph:
          At TME we take great pride in our depth of experience and our commitment to safety. We would be more than happy to supply you with a reference list of our current clients in order to backup the claim that we are 'Leaders in the Industry'.
94 Mr Gray accepted that a team working on concrete remediation required skill. He did not consider that the work needed to be performed by qualified tradesmen. Mr Gray himself was not a tradesman although he had 22 years technical experience. He held the view that the majority of the crew carrying out remediation work for a job of this type simply required energy and direction. Mr Gray stated that it was never a condition of C76 that the remediation work would be performed by qualified tradesmen.

95 In MR & RC Smith Pty Ltd t/as Ultra Tune (Osborne Park) v Wyatt [No 2] [2012] WASCA 110 Pullin JA referred to the relevance an Australian standard can have in determining whether some aspect (in that case in relation to the construction of a building) constitutes a danger which must be guarded against by the exercise of reasonable care however his Honour stated that standards published by Standards Australia have no legal application unless adopted and applied by statute or by contract.

(Page 29)
      The Australian standards or industry standards were not an express term of the contract.
96 The test for whether a term should be implied into a contract is set out in the passage of the majority of the privy council in BP Refinery (Western Port) Pty Ltd v Hastings Shire Council (1977) 180 CLR 266, 282 - 283:
          Their Lordships do not think it is necessary to review exhaustively the authorities on the implication of a term in a contract which the parties have not thought fit to express. In their view for a term to be implied, the following conditions (which may overlap) must be satisfied:

          1. it must be reasonable and equitable;

          2. it must be necessary to give business efficacy to the contract, so that no term will be implied if the contract is effective without it;

          3. it must be so obvious that 'it goes without saying';

          4. it must be capable of clear expression;

          5. it must not contradict any express term of the contract.

97 The contract has business efficacy without reference to Australian standards. The subject of the contract must be performed to a reasonable and professional standard that is likely to be the industry standard. The Australian standards can assist in determining what would be reasonable and professional in the circumstances however there is no contractual requirement that the work be performed to a specific Australian standard or industry standard.


Whether the contract included a term that all works had to be carried out by skilled tradespeople or under the supervision of a skilled tradesperson

98 Mr Gray had skills and experience in concrete remediation having had 22 years of technical experience. He did not consider that his crew needed to be qualified tradesmen. It was never a written condition of C76 that the remediation work would be performed by qualified tradespeople nor has any evidence been led to establish that it was a term of the contract that the work would be performed by qualified tradespeople or under the supervision of qualified tradespeople.

99 It is not a condition of the contract that the work be carried out by skilled tradespeople or under the supervision of skilled tradespeople.

(Page 30)

100 However the work did have to be performed to a reasonable and professional standard. This implied term is necessary for the reasonable or effective operation of the contract. TME in C76 stated that they could back up the claim that they were 'leaders in the industry'. Although Mr Gray's evidence was that skilled tradespeople were not required he acknowledged that supervision and direction were required. It was an implied term of the contract that reasonable care and skill would be exercised: Cheshire and Fifoot, Law of Contract, 10th Australian ed, 10.53; Reed v Peridis [2005] SASC 136 [27].


Whether the contract included a term that all works had to be completed by the end of the shutdown of the processing operation on the site, and whether, if it was, time was of the essence in that regard

101 Counsel for the defendant submitted that time was of the essence in relation to the performance of all work on-site making completion by the end of shutdown an essential term of the contract. Steytler P in Douglas v Cicirello [2006] WASCA 226 when dealing with the trial judge's finding in respect of an essential term said at [13] - [15]:

          The importance of a fundamental or essential term is, of course, that its breach entitles the other party to terminate the contract immediately. The test of essentiality ordinarily applied is that expounded by Jordan CJ in Tramways Advertising Pty Ltd v Luna Park (NSW) Ltd (1938) 38 SR(NSW) 632 at 641 - 642, being:

            ' … whether it appears from the general nature of the contract considered as a whole, or from some particular term or terms, that the promise is of such importance to the promisee that he would not have entered into the contract unless he had been assured of a strict or a substantial performance of the promise, as the case may be, and that this ought to have been apparent to the promisor … '

          (See also DTR Nominees Pty Ltd v Mona Homes Pty Ltd (1978) 138 CLR 423 at 430 - 431; Shevill v Builders Licensing Board (1982) 149 CLR 620 at 627, 636; and Ankar Pty Ltd v National Westminster Finance (Australia) Ltd (1987) 162 CLR 549 at 556.) Of course, it is always open to the parties to stipulate that the performance of an obligation is essential. Where that is not done, and where the relevant considerations are finally balanced, courts will ordinarily hold that a term does not give rise to an automatic right to rescind: Ankar, above, at 556.

          Where the stipulation is one as to time, if, according to the rules of equity, that stipulation is not deemed to be or to have become of the essence of the contract, the stipulation will be construed and have effect at law in accordance with the rule of equity: s 21 of the Property Law Act 1969 (WA). Consequently, performance on time will be an essential term only if

(Page 31)
          that is agreed or is reasonably to be implied (see, for example, Ballas v Theophilos [No 2] (1957) 98 CLR 193 at 197 and Wacal Investments Pty Ltd v Hurley [1992] 2 Qd R 455 at 458; and see, generally, Cheshire & Fifoot Law of Contract 8th Aust ed [21.15] - [21.17]).

          In the case of commercial or mercantile contracts, stipulations as to time (other than those as regards time of payment) are usually regarded as being of the essence of the contract: Harrington v Browne (1917) 23 CLR 297 at 304 - 305. As Pullin JA has pointed out, generally speaking at least, where a term does not fix a time for performance, with the consequence that a reasonable time is implied, the obligation to perform in that time is unlikely to be held to be an essential term: Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623 and Earnshaw v Gorman & Sons Pty Ltd [2001] WASCA 50 at [26]. However, these are only prima facie rules, capable in any given case of being defeated by the application of the test in Tramways Advertising.

102 C76 does not refer to the contract being completed by a particular date rather that TME anticipated completion within the shutdown. Mr Gray understood that the work to be performed in respect of the primary crusher that required shutdown had to be completed in the shutdown period and this is clear from C66. The work notes in respect of C66 support that TME quoted on night work and understood that the primary crusher work had to be performed within a four-day period regardless of the date of the shutdown consistent with the duration clause.

103 I make the following comments on the evidence in relation to the work that did not require the shutdown:

      1. The only evidence that there was an agreement that all of the work had to be performed by the end of the shutdown comes from Mr Rolf's evidence. Mr Rolf's recollection is that the conversations he had with Mr Gray were clear and concise and that the terms were not ambiguous. He said that he repeatedly made it clear that all work had to be performed by the end of the shutdown. I do not accept that this message in respect of all work was as clear as Mr Rolf has asserted. HRES could have insisted that the wording of the duration clause was consistent with the duration clauses of C61 and C66. This did not happen.

      2. HRES's other contracts relating to the remediation of the concrete did not have set time periods as conditions of the contracts. If time was of the essence in the contract between TME and HRES then, given that it differed from the other contracts HRES had entered into, the term would be more likely to be in writing and should have been in writing.

(Page 32)
      3. There is no evidence other than Mr Rolf's evidence that the total sum of the quotation for C76 included the completion of all works by the end of the shutdown period.
104 It is clear from the general nature of the contract considered as a whole that it was important to complete the remediation work as soon as possible. It was however not stipulated that all work had to be completed by the end of the shutdown period.


Whether the contract included a term that the works be carried out in accordance with a fixed timetable and whether, if it was, time was of the essence in that regard

105 Mr Gray stated that he did not accept that there was a set timeframe in which work during the shutdown was to be performed. However quotation C66 was consistent with Mr Gray factoring in 55 hours of nightshift being 14 hours each night for the estimated four-day period required for the work that TME was to perform during the shutdown.

106 Although Mr Gray was only shown a portion of the shutdown schedule by Mr Rolf, Mr Gray was well aware of the time limits on the work that he had to perform and was therefore well aware that he would have to fit in with a timetable.

107 Mr Gray knew that the work on the primary crusher and as much work as could be completed on the mills had to be completed by the end of the shutdown period. Mr Gray was experienced at working on sites. It would have been clear to him that TME was not the only contractor involved in the shutdown process. Given that the estimate for the work that he was to perform was well under 14 or 18 days and given that he drafted C66 to include nightshift I find that he would have anticipated that he would have to fit in with a timetable.

108 I find that Mr Gray promised to complete the work to the primary crusher that required the site to be shutdown during the shutdown period consistent with C66. I find that given his regular visits to site and familiarity with the site he was well aware that he would have to work with others in order to meet this obligation. It is irrelevant that he was only shown part of the timetable because Mr Gray should have expected there to be a timetable for the shutdown period.

109 Considering the contract as a whole the promise to complete the work relevant to the primary crusher during the shutdown period was of

(Page 33)
      such importance that I find that HRES would not have entered into the contract unless it had been assured that the primary crusher work would be completed prior to the end of the shutdown. However there is no evidence that HRES would not have entered into the contract had it known that the work on the mills could not be completed by the end of the shutdown period.



Whether the contract was an 'entire' or 'divisible' agreement

110 Counsel for HRES submits that because C76 provides for a contract price of $150,000 plus GST the contract price is payable only upon complete performance of the contract because it is an entire contract. Unless there is substantial performance in the sense of the performance that was bargained for there is no obligation to pay the contract price. Inadequate performance of the entire contract would mean that none of the contract price was due.

111 Counsel for TME submit that it is not an entire contract.

112 In Attorney General of Botswana v Aussie Diamond Products Pty Ltd [No 3] [2012] WASC 141 Murphy J summarised principles relevant to the issue of entire contracts and said at [321] and [322]:

          An entire contract, or more accurately an entire obligation, is one in which the consideration to be provided in return for the payment of money is entire and indivisible: Baltic Shipping v Dillon (350). If a contract or obligation is entire, its complete performance is a condition precedent to payment or counter performance: GEC Marconi Systems v BHP [703].

          In Baltic Shipping v Dillon Mason CJ said (350):


            The concept of an entire contract is material when a court is called upon to decide whether complete performance by one party is a condition precedent to the other's liability to pay the stipulated price or to render an agreement counter-performance. If this were a case in which the appellant sought to enforce a promise to pay the cruise fare at the conclusion of the voyage the concept would have a part to play; then, if the appellant's obligations were entire, on the facts as I have stated them, the appellant's incomplete performance of its obligations would not entitle it to recover.

            When, however, an innocent party seeks to recover money paid in advance under a contract in expectation of the entire performance by the contract-breaker of its obligations under the contract and the contract-breaker renders an incomplete performance, in general, the innocent party cannot recover unless there has been a total failure of consideration. If the incomplete performance results in

(Page 34)
            the innocent party receiving and retaining any substantial part of the benefit expected under the contract, there will not be a total failure of consideration.
113 Recently in Cordon Investments Pty Ltd v Lesdor Property Pty Ltd [2012] NSWCA 184 [94] Bathurst CJ said:
          In the case of contracts which at least on their face appear to be entire contracts, particular lump sum building contracts, courts have been reluctant to construe complete performance of the works as an essential pre-condition for payment. Rather, in circumstances where there has been substantial performance, they have treated a failure to complete as a breach of a non-essential term of the contract not disentitling the builder to contractual payment for the work done but, rather, giving the proprietor a right of setoff or claim for damages for the cost of completing the work or rectifying any defects. The position was summarised by Denning LJ in Hoeing v Isaacs supra at 180 - 181:

            'the first question is whether, on the true construction of the contract, entire performance was a condition precedent to payment. It was a lump sum contract, but that does not mean that entire performance was a condition precedent to payment. When a contract provides for a specific sum to be paid on completion of specified work, the courts lean against a construction of the contract which would deprive the contractor of any payment at all simply because there are some defects or omissions. The promise to complete the work is, therefore, construed as a term of the contract, but not as a condition. It is not every breach of that term which absolves the employer from his promise to pay the price, but only a breach which goes to the root of the contract, such as an abandonment of the work when it is only half done. Unless the breach does go to the root of the matter, the employer cannot resist payment of the price. He must pay it and bring a cross-claim for the defects and omissions, or, alternatively, set them up in diminution of the price. The measure is the amount which the work is worth less by reason of the defects and omissions, and is usually calculated by the cost of making them good. [Citation of authorities omitted.] It is, of course, always open to the parties by express words to make entire performance a condition precedent.'

          See also Dakin v Lee supra at 574, 578 - 579; Connor v Stainton(1924) 27 WALR 72 at 73; Williamson v Murdoch(1912) 14 WALR 54 at 56 - 58; Bolton v Mahadeva supra at 1012 - 1013; ACN 002 804 702 (formerly Brooks Building) v McDonald supra at [100] - [106].
114 In Cordon Investments Pty Ltd the issue was whether the requirement to execute a strata plan arose only on completion of the building and construction works. In that case failure to complete went to the root of the contract.

(Page 35)

115 The mine site was 600 km from Perth and needed to be shutdown for the primary crusher work to be carried out. The primary crusher component of the contract had to be completed as scheduled during the shutdown. Had that part not been completed to a reasonable standard then the entire mine site would have had to have been shutdown on a second occasion. The need to complete the primary crusher work to a reasonable standard was an essential term. However although it was clearly desirable to have all of the mill work completed by the end of the shutdown I do not accept that completion by the end of the shutdown was an essential term of the contract. Entire performance of all of the works on-site by the end of the shutdown was not a condition precedent to payment.

116 Failure to complete all of the works on-site by the end of the shutdown period would not constitute a total failure of consideration. The requirement to complete the whole of the scope of works to a reasonable standard was a term of the contract however TME would be entitled to payment for work performed. The breach of the term however would give HRES the right of set-off and the right to claim damages for the cost of completing the work or rectifying any defects.


Whether rates for any of the variations 'claimed' as 'variation 4, 4A and 4B' was fixed by agreement or whether it was to be determined on some other basis and, if so, how was the relevant rate to be determined

117 For the reasons I have outlined in relation to the preliminary issue on variations I do not accept that there was agreement in relation to the rate to be fixed for variations. The sum of $3,500 per sqm was, when compared to the total contract price of $150,000, excessive. There was no evidence to challenge Mr Rolf's calculation that had the contract been charged at $3,500 per sqm the appropriate cost would have been $800,000 to $900,000 rather than $150,000. Mr Gray asserted that $3,500 per sqm was the correct rate. Mr Rolf asserted that a sum of $1,500 to $1,700 was appropriate.

118 For the reasons I have stated I find that it was an implied term of each of the variation agreements the subject of dispute that a reasonable rate per square metre would apply however I am not in a position to set that rate given the limited evidence received in relation to the determination of preliminary issues.


 |   | 
Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

15

Statutory Material Cited

1

Reed v Peridis [2005] SASC 136