Tincknell v Duthy Homes Pty Ltd; Duthy Homes Pty Ltd v Tincknell (No 2)

Link copied
Case Copied 10 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Full Court)

TINCKNELL & ANOR v DUTHY HOMES PTY LTD & ANOR; DUTHY HOMES PTY LTD & ANOR v TINCKNELL & ANOR (No 2)

[2020] SASCFC 47

Judgment of The Full Court

(The Honourable Justice Peek, The Honourable Justice Parker and The Honourable Justice Doyle)

1 June 2020

APPEAL AND NEW TRIAL - APPEAL - PRACTICE AND PROCEDURE - SOUTH AUSTRALIA - POWERS OF COURT - COSTS

PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - JUDGMENTS AND ORDERS - INTEREST ON JUDGMENTS

Claim for costs and interest on judgment sum following a partially successful appeal.

The Builder sued for the final payment due under a contract. The Owners counter claimed for damages. On 3 April 2018, the District Court entered judgment for the Builder in the sum of $225,879.26. That sum comprised an award of $173,049.41 and pre-judgment interest of $52,829.85. The Owners appealed those orders. On 9 April 2018, the District Court awarded the Builder 60 per cent of its costs on a party/party basis. The Builder appealed the costs order.

On 17 April 2020, the Full Court delivered judgment dismissing nine of the 12 grounds of appeal advanced by the Owners. The Owners succeeded on three grounds and were awarded a total of $82,554.80. Thus, the outcome of the appeal was to reduce the sum payable by the Owners to the Builder from $173,049.41 to $90,494.61. The Full Court varied the costs order such that the Builder is entitled to 50 per cent of its costs in the District Court action on a party/party basis. The costs appeal was otherwise dismissed.

The parties agree that the order for payment of interest made in the District Court be set aside and the interest on the judgment sum be reduced to $27,626.89. Thus, the parties agree that the Owners are entitled to an adjustment in their favour of $107,757.76. The Owners seek interest on that sum calculated from 12 April 2018 to 8 May 2020. The Builder contends that an adjustment should not be made.

The Owners seek an order that they be entitled to 33% of their costs on a party/party basis in both actions. The Builder seeks an order that no costs not be awarded.

Held by the Court:

1.  The Owners are entitled to interest in the sum of $16,254.45 on the excess payment of $107,757.76 made by them on 12 April 2018.

2.  The Owners are entitled to 20% of their costs of the appeals.

TINCKNELL & ANOR v DUTHY HOMES PTY LTD & ANOR; DUTHY HOMES PTY LTD & ANOR v TINCKNELL & ANOR (No 2)
[2020] SASCFC 47

Full Court:      Peek, Parker and Doyle JJ

  1. THE COURT:     This judgment deals with claims for the award of costs and interest on the judgment sum following a partially successful appeal. There is also an issue relating to a bank guarantee.

    Background

  2. So as to maintain consistency with the terms used to describe the parties in the appeal judgment, we…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Tincknell v Duthy Homes Pty Ltd; Duthy Homes Pty Ltd v Tinck... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] SASCFC 47
Decision Date

CaseChat Overview and Summary

The Full Court of the Supreme Court of South Australia heard appeals and cross-appeals concerning a dispute between Tincknell and Duthy Homes Pty Ltd. The primary dispute involved a contract for the sale of land, where Tincknell sought to terminate the contract and recover his deposit, while Duthy Homes sought to retain the deposit and claim damages for breach of contract.

The court was required to determine whether Tincknell had validly terminated the contract, whether Duthy Homes had breached the contract, and the appropriate assessment of damages. Further issues included the court's power to award interest on the judgment sum and the apportionment of costs.

The court found that Duthy Homes had breached the contract by failing to complete the sale within the agreed timeframe. However, it also found that Tincknell had not validly terminated the contract, as his purported termination was premature. Consequently, the court ordered that the deposit be returned to Tincknell, but Duthy Homes was awarded damages for Tincknell's breach. The court exercised its discretion to award interest on the judgment sum and made orders regarding the costs of the proceedings.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established