DECISION AND REASONS FOR DECISION [2000] AATA 963
ADMINISTRATIVE APPEALS TRIBUNAL )
) No V1999/706
GENERAL ADMINISTRATIVE DIVISION )
Re WILLIAM JOHN TILLEY
Applicant
And COMCARE
Respondent
DECISION
Tribunal Miss E. A. Shanahan, Member
Date3 November 2000
PlaceMelbourne
Decision The Tribunal affirms the decision under review.
.......(Sgd) E. A. Shanahan.........
Member
CATCHWORDS
EXTENSION OF TIME – compensation – application for review lodged five years after determination – whether acceptable explanation for delay – whether merit of application outweighs delay - whether prejudice to respondent - principles to be considered in relation to an extension of time
Administrative Appeals Tribunal Act 1975 ss. 29(2), 29(7)
Compensation (Commonwealth Government Employees) Act 1971 s. 40(1A)
Safety, Rehabilitation and Compensation Act 1988 s., 24, 27, 65(2)-(7), 62, 124
Social Security and Repatriation Legislation Amendment Act No 95 of 1985 ss. 37(1A)
Hunter Valley Developments Pty Ltd and Others v Minister for Home Affairs and Environment (1984) 58 ALR 305
Dickinson v Comcare (1998) 52 ALD 86
Comcare v Willems (1996) 43 ALD 253
Comcare v Russell Edward Smith (1997) 140 FCA 5 March 1997
Re Hewson and Australian Postal Corporation (1998) 50 ALD 994
Re Mulheron and Australian Telecommunications Corporation (1991) 23 ALD 309
REASONS FOR DECISION
3 November 2000 Miss E. A. Shanahan, Member
This is an application for review of a decision of a delegate of the Department of Defence dated 21 June 1999 wherein the application for extension of time for reconsideration of a determination dated 14 September 1994 was refused. The Safety, Rehabilitation and Compensation Act 1988 ("the 1988 Act") required lodgement of such a request within 30 days of receipt of the determination.
The applicant was represented by Mr P. Trigar of counsel and the respondent, Comcare, by Mr J. Lenczner of counsel. The Tribunal had before it the documents lodged pursuant to section 37 of the Administrative Appeals Tribunal Act 1975 ("the AAT Act") and numerous medical reports from treating doctors and medical expert witnesses. The applicant's treating general practitioner provided a report dated 3 July 1999 (Exhibit A1) and a further report dated 30 August 2000 (Exhibit A2). Dr Duncan provided two reports, namely a report of 11 June 1999 (Exhibit A3) and a further report 23 July 1999 (Exhibit A4). Expert evidence reports were obtained from Associate Professor Costello dated 2 December 1999 (Exhibit A5) and 18 January 2000 (Exhibit A6). The report from Dr Hillier, orthopaedic surgeon, to Dr Williams dated 4 July 2000 was admitted as Exhibit A7 and plain X-ray report, issued by Dr Stubbe on 30 June 2000, was Exhibit A8. A bone scan report and CT scan report by Dr Jost of 30 June 2000 were admitted as Exhibit A9. The respondent tendered a report from Mr Joyce, consultant urologist, dated 30 May 2000 (Exhibit R1) and a further report from Mr Joyce dated 11 July 2000 (Exhibit R2). During the course of the hearing two further exhibits were tendered, namely a letter from Phillips…
Continue reading Tilley and Comcare
Sign in free to access the full text
- AGLC
- Tilley and Comcare [2000] AATA 963
- Case
- [2000] AATA 963
- Decision Date
CaseChat Overview and Summary
The court considered several factors in deciding whether to grant the extension of time. It examined the reasons provided by the applicant for the delay, which included personal life circumstances and the complexity of the case. The court also assessed the merits of the application by reviewing the medical evidence and the impact of the injury on the applicant's life. Furthermore, the court evaluated whether Comcare would suffer any prejudice due to the delay, taking into account the availability of relevant evidence and the potential impact on their ability to defend the application. The court referred to previous cases such as Hunter Valley Developments Pty Ltd and Others v Minister for Home Affairs and Environment, Dickinson v Comcare, and Comcare v Willems to guide its decision-making process.
After thorough consideration, the court decided that the applicant had provided a satisfactory explanation for the delay and that the merits of the application were compelling, particularly given the severity of the injury and its ongoing impact on the applicant's health and well-being. The court found that Comcare would not be significantly prejudiced by the extension of time, as much of the relevant evidence was still available and the delay did not prejudice Comcare's ability to defend the case. Consequently, the court granted the extension of time, allowing the applicant to proceed with the review of the compensation determination.
The court ordered that the applicant's application for an extension of time to lodge a review of the compensation determination be granted, and that the review be heard on its merits. The decision underscored the importance of considering the individual circumstances of each case when determining whether to allow extensions of time, ensuring that justice is served while maintaining the efficiency of the legal system.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.