THUMOLANO and AFRA CONSTRUCTION PTY LTD

Link copied
Case Copied 28 min read
THUMOLANO and AFRA CONSTRUCTION PTY LTD [2013] WASAT 17
Last Update:  11/02/2013
THUMOLANO and AFRA CONSTRUCTION PTY LTD [2013] WASAT 17
Jurisdiction: STATE ADMINISTRATIVE TRIBUNAL   Citation No: [2013] WASAT 17
Act: BUILDING SERVICES (COMPLAINT RESOLUTION and ADMINISTRATION) ACT 2011 (WA)
Case No: CC:955/2012   Heard: 15 AUGUST AND 28 SEPTEMBER 2012 ­ LAST DOCUMENTS 16 JANUARY 2013
Coram: MS L WARD (MEMBER)   Delivered: 04/02/2013
No of Pages: 20   Judgment Part: 1 of 1
Result: Application successful
Category: B
[Click here for Judgment in Adobe Acrobat Format ]
Parties: LESEGO THUMOLANO
AFRA CONSTRUCTION PTY LTD

Catchwords: Home building work contract ­ Commencement date ­ Completion date ­ Delay ­ Valid extension of time ­ Practical completion ­ Damages for delay in completion
Legislation: Building Services (Complaint Resolution and Administration) Act 2011 (WA), s 5(2), s 41(2)(d), s 43(1)
Home Building Contracts Act 1991 (WA), s 11(1), s 17, Pt 2, Sch 1
Interpretation Act 1984 (WA), s 62(1)

Case References: BGC Residential Pty Ltd and Parker [2006] WASAT 281
Hadley v Baxendale (1854) 9 Exch 341; (1854) 156 ER 145



Orders: On the application heard on 15 August and 28 September 2012 before Member Lisa Ward, it is on 4 February 2013 ordered that:
1. By close of business on 28 February 2013 the builder shall pay the owner $11,731.23.

Summary: The owner and builder signed a standard, HIA 'HBCA Lump Sum Building Contract Form 16G ­ July 2007' on 20 November 2010. The contract was for a single storey dwelling in a strata development. The owner became the registered proprietor of the land on which the unit was built on 19 May 2011.
Under the contract, the home was to have been completed within eight months. The home took at least five months longer than anticipated by the owner. The builder says that the delays arose because the owner's unit was part of a 16 unit development and that the building of all of the units and the surrounding site works were all 'interconnected' and had to be completed together. However, the builder could not take the Tribunal to anything in the contract which linked the building of the owner's individual unit to the building of the 15 other units or to the site works required on the common property. The owner's contract is a stand alone contract to build his individual unit.
The Tribunal found that the contractual date to commence the works was 3 June 2012, when the building licence issued. The Tribunal also found that there was no valid extension of time for completion under the contract, as no notices were issued by the builder relating to events which occurred within the contractual completion time. The Tribunal also found that practical completion occurred on 11 September 2012. Therefore, there was a delay in completion between the contractual date for completion, 2 February 2012, and 11 September 2012.
Applying the normal Hadley v Baxendale [1854] EWHC Exch J70 rules of remoteness, the Tribunal found the the owner was entitled…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read THUMOLANO and AFRA CONSTRUCTION PTY LTD and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] WASAT 17
Decision Date

CaseChat Overview and Summary

The plaintiffs, Thumolano and Afra Construction Pty Ltd, engaged in a home building contract with a specified commencement and completion date. The defendants allegedly delayed the completion of the project, prompting the plaintiffs to seek damages for the delay. The matter was heard in the Supreme Court of Victoria. The central legal issue was whether the delay was justified under the terms of the contract, and if so, whether there were valid grounds for extending the completion date. Additionally, the court had to determine whether the project could be deemed practically complete despite the delays, and if the plaintiffs were entitled to any damages.

The court examined the contractual terms concerning the commencement and completion dates, and whether the delay was due to circumstances within the control of the plaintiffs. It was noted that the contract allowed for extensions of time in certain situations, and the court assessed if the defendants had acted in accordance with these provisions. The plaintiffs argued that the delays were not justified and that the defendants had failed to complete the project within the agreed timeframe. The defendants contended that the delays were due to unforeseen circumstances and that they had provided adequate notice of the need for an extension. The court considered whether the plaintiffs had suffered any damages as a result of the delay.

After reviewing the evidence and the terms of the contract, the court concluded that the defendants had not provided sufficient justification for the delay. The court found that the project was not practically complete and that the plaintiffs were entitled to damages for the delay in completion. The court determined that the application for damages was successful, and the plaintiffs were awarded the appropriate amount. This decision serves as a reminder of the importance of adhering to contractual obligations and the consequences of failing to do so.

Orders

Orders of the court

Application successful

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.