Three P/L v Body Corporate for Savoir Faire

Link copied
Case Copied 29 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Three P/L v Body Corporate for Savoir Faire Community Titles Scheme 3841 [2008] QCA 167

PARTIES:

THREE PTY LTD ACN 069 497 516
(respondent/plaintiff/respondent)
v
BODY CORPORATE FOR SAVOIR FAIRE COMMUNITY TITLES SCHEME 3841
(applicant/defendant/appellant)

FILE NO/S:

Appeal No 11825 of 2007
SC No 11051 of 2005

DIVISION:

Court of Appeal

PROCEEDING:

General Civil Appeal

ORIGINATING COURT:

Supreme Court at Brisbane

DELIVERED ON:

20 June 2008

DELIVERED AT:

Brisbane

HEARING DATE:

19 May 2008

JUDGES:

de Jersey CJ, Fraser JA and Mackenzie AJA
Separate reasons for judgment of each member of the Court, each concurring as to the orders made.

ORDERS:

Allow the appeal and set aside the judgment of
6 December 2007.
1.    

In lieu thereof judgment be entered in favour of the defendant against the plaintiff on its claim. 2.    

It be declared that the contract described in the plaintiff’s claim was rendered void by subsection 19(8) of the Land Sales Act 1984 (Qld). 3.    

The plaintiff pay the defendant’s costs of and incidental to the proceedings, including the defendant’s application for summary judgment, to be assessed. 4.    

The respondent pay the appellant’s costs of the appeal to be assessed. 5.    

CATCHWORDS:

CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – ILLEGAL AND VOID CONTRACTS – ILLEGAL BY STATUTE – PARTICULAR STATUTES – where the appellant made a contract to sell a proposed allotment to the respondent – where no effective development approval for the proposed allotment existed at the time of the contract – where by operation of section 8 of the Land Sales Act 1984 (Qld) the contract was void – where subsection 19(6) provided an exception to the invalidity created by section 8 in circumstances where an application for a grant of exemption from development approval had been made – where subsection 19(7) required that such an application be made within “30 days after the event that marks the entry of a purchaser upon the purchase of the proposed allotment” – where the purchaser signed the contract before it was executed by the vendor – where the application for exemption was made more than 30 days after the purchaser signed the contract but less than 30 days after the vendor executed it – whether the application for exemption had been made in time – consideration of the meaning of the term “the event” as described in s 19(7) – consideration of when a person “enters upon a purchase” for the purposes of the Act – consideration of the meaning of purchaser as defined in s 6A(1)(a) of the Act

Acts Interpretation Act 1954 (Qld), s 14A, s 14B, s 32, s 32A, s 32AA
Auctioneers and Agents Act
1971 (Qld), s 67, s 67A
Land Sales Act
1984 (Qld), s 6, s 6A, s 8, s 9, s 10A, s 11,
s 19, s 21

Francis v NPD Property Development Pty Ltd [2004] QSC 202, referred to
IVI P/L v Baycrown P/L [2005] QCA 205, cited
Noble v The Public Trustee…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Three P/L v Body Corporate for Savoir Faire and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2008] QCA 167
Decision Date

CaseChat Overview and Summary

The dispute between Three P/L and the Body Corporate for Savoir Faire centred around a contract for the sale of a proposed allotment that lacked effective development approval. The case was heard in the Queensland Court of Appeal, where the central issue was whether the contract was rendered void by statute and, if so, whether an application for exemption from the development approval requirement was made in a timely manner. The Body Corporate sought a declaration that the contract was void, and Three P/L appealed against this decision.

The court had to determine whether the application for exemption from the development approval requirement was made within the stipulated 30-day period as required by subsection 19(7) of the Land Sales Act 1984 (Qld). The court examined the definition of "the event" as described in subsection 19(7) and considered when a person "enters upon a purchase" for the purposes of the Act. Additionally, the court interpreted the term "purchaser" as defined in section 6A(1)(a) of the Act. The court found that the application for exemption had been made in time, as the relevant event occurred when the purchaser signed the contract, not when the vendor executed it.

The Queensland Court of Appeal allowed the appeal and set aside the previous judgment. The court entered judgment in favour of the Body Corporate, declaring that the contract was rendered void by subsection 19(8) of the Land Sales Act 1984 (Qld). The court ordered that Three P/L pay the Body Corporate's costs of and incidental to the proceedings, including their application for summary judgment. The Body Corporate, in turn, was ordered to pay Three P/L's costs of the appeal.

Orders

Orders of the court

Allow the appeal and set aside the judgment of

6 December 2007. 1.

In lieu thereof judgment be entered in favour of the defendant against the plaintiff on its claim. 2.

It be declared that the contract described in the plaintiff’s claim was rendered void by subsection 19(8) of the Land Sales Act 1984 (Qld). 3.

The plaintiff pay the defendant’s costs of and incidental to the proceedings, including the defendant’s application for summary judgment, to be assessed. 4.

The respondent pay the appellant’s costs of the appeal to be assessed. 5.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established