Thiess Contractors Pty Ltd v Placer (Granny Smith) Pty Ltd

Link copied
Case Copied 9 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

TITLE OF COURT :   THE FULL COURT (WA)

CITATION:   THIESS CONTRACTORS PTY LTD -v- PLACER (GRANNY SMITH) PTY LTD [2001] WASCA 166

CORAM:   STEYTLER J

WHEELER J

HEARD:   8 MAY 2001

DELIVERED          :   30 MAY 2001

FILE NO/S:   FUL 55 of 1999

BETWEEN:   THIESS CONTRACTORS PTY LTD (ACN 010 221 486)

Appellant

AND

PLACER (GRANNY SMITH) PTY LTD (ACN 009 466 175)
Respondent

Catchwords:

Appeal - Appellant appealed against dismissal of claim and upholding of respondent's counterclaim - Respondent failed to prove damages - Appellant ordered to pay respondent nominal damages of $100

Costs - Trial costs left undisturbed - Appellant ordered to pay respondent one fifth of its costs of the appeal

Legislation:

Nil

Result:

Costs orders made

Representation:

Counsel:

Appellant:     Mr P G Clifford

Respondent:     Mr J Gilmour QC & Mr R J Ainslie

Solicitors:

Appellant:     Hollingdales

Respondent:     Mallesons Stephen Jaques

Case(s) referred to in judgment(s):

Alltrans Express Ltd v CVA Holdings Ltd [1984] 1 WLR 394

Anglo‑Cyprian Trade Agencies Ltd v Paphos Wine Industries Ltd [1951] 1 All ER 873

Giannarelli & Shulkes v Wraith (1988) 165 CLR 543

Case(s) also cited:

Nil

  1. JUDGMENT OF THE COURT:  These are applications for costs arising out of the judgment of this Court in an appeal brought by the appellant.  The appellant had been unsuccessful, at trial, both in its claim against the respondent and in the respondent's counterclaim against it.  It appealed against the decision in each case.

  2. The claim and counterclaim centred around a contract made between the appellant and the respondent in July 1992 and incorporated in a formal document executed by them in July 1993.  That contract was terminated by the respondent.  The appellant commenced proceedings against it alleging, amongst other things, that the termination of the contract was unlawful.  It claimed substantial damages.  The respondent denied that the termination was unlawful.  It alleged, amongst other things, that the appellant had breached an obligation of good faith which had been expressly provided for by the contract.  It brought a counterclaim against the appellant, relying essentially upon the same facts as had been raised by it in answer to the appellant's claim against it.  It, too, claimed substantial damages.  The trial Judge dismissed the appellant's claim and upheld the respondent's counterclaim.  He awarded to the respondent damages of $4,853,000.

  3. The appellant appealed, as we have said, against both the dismissal of its claim and the upholding of the counterclaim.  Its appeal against the dismissal of its claim was dismissed.  So far as its appeal against the decision on the counterclaim was concerned, this Court found that no basis had been shown for upsetting any of the findings of fact made by the trial Judge with respect to the merits of the counterclaim or in respect of various issues of causation.  However we held that his Honour had erred in finding that the respondent had proved its damages.  We found, on the appeal, that there was a crucial lacuna in…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Thiess Contractors Pty Ltd v Placer (Granny Smith) Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2001] WASCA 166
Decision Date

CaseChat Overview and Summary

The case of Thiess Contractors Pty Ltd v Placer (Granny Smith) Pty Ltd involved an appeal against the dismissal of a claim and the upholding of a counterclaim by the respondent. The dispute centred on a contract made in 1992 and formalised in 1993 between the parties, which was terminated by the respondent. The appellant, Thiess Contractors, alleged that the termination was unlawful and sought substantial damages. The respondent, Placer, denied this and brought a counterclaim for breach of an obligation of good faith, also seeking substantial damages. The trial judge dismissed the appellant’s claim and upheld the counterclaim, awarding damages of $4,853,000 to Placer. The appellant appealed against both the dismissal of its claim and the upholding of the counterclaim. The appeal court found no basis to overturn the trial judge’s findings on the counterclaim but determined that Placer had not proved its damages. Consequently, the appeal court awarded nominal damages of $100 instead of the $4,853,000 awarded at trial.

The legal issues in the case revolved around the validity of the respondent's claims and counterclaims, the assessment of damages, and the allocation of costs between the parties. The court had to determine whether the respondent had adequately proven its damages as part of its counterclaim and whether the trial judge's assessment of damages was correct. Additionally, the court needed to decide on the appropriate allocation of costs between the appellant and the respondent for the appeal and the trial. The appeal court found that while the respondent had succeeded on the merits of the counterclaim, it had failed to prove its damages, leading to an adjustment in the amount awarded. The court also needed to consider the costs incurred by both parties in the appeal and the trial, determining how they should be apportioned.

The appeal court held that the respondent was entitled to nominal damages of $100 in lieu of the $4,853,000 awarded at trial because of the deficiency in the damages proof. The court further determined that the costs of the trial should remain as ordered by the trial judge. Regarding the appeal costs, the court found that Placer should be awarded one fifth of its costs of the appeal, rejecting the appellant's request to pay its own costs and the respondent's request to pay two-thirds of its appeal costs. The court reasoned that less than one third of the appeal was related to the damages issue and that the respondent had been unduly burdened by the appellant's deficient notice of appeal. The appeal court concluded that the costs should be apportioned to reflect the limited scope of the appeal concerning the damages issue and the respondent's difficulties in preparing for the appeal due to the appellant’s deficient notice.

The final orders of the court were that Thiess Contractors was to pay nominal damages of $100 to Placer and one fifth of Placer's costs of the appeal. The costs of the trial were left undisturbed as ordered by the trial judge. This decision highlighted the importance of proving damages in legal claims and the consequences of procedural deficiencies in court proceedings.

Decision

Reasons for decision

JUDGMENT OF THE COURT: These are applications for costs arising out of the judgment of this Court in an appeal brought by the appellant. The appellant had been unsuccessful, at trial, both in its claim against the respondent and in the respondent's counterclaim against it. It appealed against the decision in each case. The claim and counterclaim centred around a contract made between the appellant and the respondent in July 1992 and incorporated in a formal document executed by them in July 1993. That contract was terminated by the respondent. The appellant commenced proceedings against it alleging, amongst other things, that the termination of the contract was unlawful. It claimed substantial damages. The respondent denied that the termination was unlawful. It alleged, amongst other things, that the appellant had breached an obligation of good faith which had been expressly provided for by the contract. It brought a counterclaim against the appellant, relying essentially upon the same facts as had been raised by it in answer to the appellant's claim against it. It, too, claimed substantial damages. The trial Judge dismissed the appellant's claim and upheld the respondent's counterclaim. He awarded to the respondent damages of $4,853,000. The appellant appealed, as we have said, against both the dismissal of its claim and the upholding of the counterclaim. Its appeal against the dismissal of its claim was dismissed. So far as its appeal against the decision on the counterclaim was concerned, this Court found that no basis had been shown for upsetting any of the findings of fact made by the trial Judge with respect to the merits of the counterclaim or in respect of various issues of causation. However we held that his Honour had erred in finding that the respondent had proved its damages. We found, on the appeal, that there was a crucial lacuna in the damages formula which the respondent had attempted to prove at trial. We awarded to Placer, in lieu of the sum of $4,853,000 awarded by the trial Judge, nominal damages fixed at $100. The appellant now seeks an order that it be paid its costs of the whole of the appeal. So far as the costs of the trial are concerned, it submits that, while the respondent should have the costs (already ordered by the trial Judge) of defending the appellant's claim, the appellant should have its costs of defending the counterclaim (which were awarded by the trial Judge in favour of the respondent). The respondent, on the other hand, contends, firstly, that the appellant should pay the whole of its costs of getting up the appeal and two thirds of its costs of the hearing of the appeal. This submission was based upon two propositions. The first was that less than one third of the time taken up on the hearing of the appeal was expended on issues going to the proof of the respondent's damages in its counterclaim. The second was that the respondent had been faced with a 38 page notice of appeal which this Court has already found to have been deficient in form and which, the respondent said, caused it great difficulty in the preparation of the appeal. The notice of appeal was abandoned on the first day of the appeal.