Supreme Court
New South Wales
Medium Neutral Citation: The Star Entertainment Sydney Properties Pty Ltd v Buildcorp Group Pty Ltd [2023] NSWSC 241 Hearing dates: 17 March 2023 Date of orders: 17 March 2023 Decision date: 17 March 2023 Jurisdiction: Equity - Technology and Construction List Before: Rees J Decision: Grant leave to amend pleadings.
Catchwords: CIVIL PROCEDURE — pleadings — amendment — plaintiffs seek to add claims under further contract — defendant’s ability to cross-claim may be time-barred — whether leave should be refused given prejudice to defendant – plaintiffs not dilatory in identifying further claim — plaintiffs entitled to commence separate proceedings anyway – avoidance of multiplicity of proceedings — prejudice mitigated by contractual indemnity given by prospective cross-defendant.
Legislation Cited: Civil Procedure Act 2005 (NSW) s 65
Cases Cited: Owners - SP 67635 v Metlej Developments Pty Ltd [2013] NSWSC 1564
Category: Procedural rulings Parties: The Star Entertainment Sydney Properties Pty Ltd (first applicant)
The Star Pty Limited (second applicant)
Buildcorp Group Pty Limited trading as Buildcorp Interiors (respondent)Representation: Counsel:
Solicitors:
S Kanagaratnam (applicants)
B Le Plastrier (respondent)
Holding Redlich (applicants)
Colin Biggers & Paisley (respondent)
File Number(s): 2020/00112369
ex tempore Judgment - Application to amend pleading
-
Her Honour: This is an application by the plaintiffs to amend their pleading. The plaintiffs already seek damages from the contractor in respect of a contract entered into in October 2014 and a second contract entered into in May 2015, to effect construction and refurbishment works at Star Casino. The plaintiffs now seek to add a claim for damages for breach of a third contract between the plaintiffs and the defendant contractor.
-
The contractor accepts that the claim now sought to be brought is not time-barred. The problem is that a cross-claim by the contractor against its subcontractor is likely time-barred; the amendment is opposed for this reason.
Facts
-
To effect the work required under the first and second contracts, the contractor engaged with a number of subcontractors, including Ausrise Aluminium Pty Ltd (Ausrise), which saw aluminium composite panels (ACPs) installed at the casino.
-
The plaintiffs and contractor entered into the third contract in December 2015, in the form of a deed. The contractor entered into a further subcontract with Ausrise.
-
In April 2020, these proceedings were commenced in respect of the first contract, where the ACPs are said to have been non-compliant. In September 2020, the plaintiffs amended their claim to also seek damages in respect of the second contract. On 10 June 2021, the contractor filed cross-claims against five entities, including Ausrise. In October 2021, Ausrise filed a response which inter alia pleaded that the claim against it was statute-barred as the cause of action accrued more than six years before the commencement of the proceedings on 10 June 2021, being the date that the cross-claim was filed.
-
In late 2021, a consultant identified further ACPs at the casino. In March 2022, the plaintiffs notified the contractor that additional ACPs had been…
Keep reading for free
Create a free CaseChat account to read The Star Entertainment Sydney Properties Pty Ltd v Buildcorp... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NSWSC 241
- Decision Date
CaseChat Overview and Summary
The court considered the plaintiffs' promptness in identifying the new claims and the potential prejudice to the defendant if the amendment was refused. It noted that the plaintiffs could still initiate separate proceedings for the new claims, which could result in a multiplicity of proceedings. However, the court was reassured by the contractual indemnity provided by the prospective cross-defendant, which mitigated the potential prejudice to the defendant. The court found that the plaintiffs were not dilatory and that the benefits of avoiding multiple proceedings and the indemnity arrangement justified granting leave for the amendment.
Accordingly, the court granted leave for the amendment of the pleadings, allowing the plaintiffs to include the additional claims under the further contract. This decision balanced the plaintiffs' right to seek redress against the defendant's potential prejudice, while also considering practicalities such as the avoidance of multiple proceedings and the indemnity arrangement. The final orders reflected the court's decision to permit the amendment.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi