ACT CIVIL & ADMINISTRATIVE TRIBUNAL
THE OWNERS – UNITS PLAN NO 68 v HAUGHEY (Unit Titles) [2016] ACAT 131
UT 13/2016
Catchwords: UNIT TITLES – removal of hot water system from common property wall – approval of installation of hot water system – proxy nomination forms – motion raised at owners corporation meeting – type of motion needed to authorise installation of hot water system – ‘special privilege’ under s 49 of UTA 2001 and s 22 of UTM Act – ‘special privilege’ in circumstances where the use is other than ‘minor’ – permission via special resolution – principles governing meeting practice – interim application – application statute barred
Legislation cited: ACT Civil and Administrative Appeals Tribunal Act 2008 s 32
Legislation Act 2001s 140
Limitation Act 1985 s 11
Unit Titles Act 1970Unit Titles Act 2001 ss 44, 47, 49, 88B, 97, 126, 128
Unit Titles Amendment Act 2008 (No 2)
Unit Titles (Management) Act 2011 ss 22, 49, 125, 129
Subordinate
Legislation cited: Body Corporate and Community Management (CommercialModule) Regulation 1997 (Qld) s 91
Cases cited: Brown v The Owners of Units Plan 2737 [2001] ACAT 2
General Steel Industries Inc v Commissioner for Railways
(NSW) (1964) 112 CLR 125
Katsikalis v Body Corporate for “The Centre” [2009] QCA
77
Owners Corporation Units Plan 202 v Brudenell & Ors [2015]
ACAT 64
Owners Unit Plan 78 v Lokusooriya [2013] ACAT 80
Owners Units Plan No 116 & Nicholson and Ors [2012] ACAT63
List of
Texts/Papers cited: Butt, P, Land Law (sixth edition)Explanatory Memorandum to the Unit Titles Ordinance 1970
Explanatory Memorandum to the Unit Titles Bill 2000
Magner, Ellis S, Joske’s Law and Procedure at Meetings in
Australia, 11th ed
Tribunal: Senior Member H Robinson
Date of Orders: 28 November 2016
Date of Reasons for Decision: 28 November 2016
AUSTRALIAN CAPITAL TERRITORY )
CIVIL & ADMINISTRATIVE TRIBUNAL ) UT 13/2016
BETWEEN:
THE OWNERS – UNITS PLAN NO 68
Applicant
AND:
REGAN JOHN HAUGHEY
Respondent
TRIBUNAL: Senior Member H Robinson
DATE:28 November 2016
ORDER
The Tribunal orders that:
1.Pursuant to subsections 129(1)(a) and 129(2) of the Unit Titles (Management) Act 2011 (UTM Act), within 90 days of the date of this order, the respondent must either:
a)obtain the necessary authority under the UTM Act for the installation or continued presence of the hot water system on the rear wall of the common property; or
b)remove the hot water system from the rear wall of the common property.
………………………………..
Senior Member H Robinson
REASONS FOR DECISION
1.This is an application by the Owners – Units Plan No 68 (Owners Corporation) for an order that the respondent, Mr Haughey, remove a hot water system from the common property wall of the unit complex.
2.The application is made pursuant to section 129 of the Unit Titles (Management) Act 2011 (ACT)…
Keep reading for free
Create a free CaseChat account to read The Owners - Units Plan No 68 v Haughey (Unit Titles) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] ACAT 131
- Decision Date
CaseChat Overview and Summary
The primary legal issues concerned whether the installation of the hot water system required approval from the owners corporation and, if so, what type of motion was necessary to authorise it. Specifically, the court had to determine whether the installation constituted a minor use that could be authorised by a simple majority vote or whether it required a special resolution. The court also had to consider the principles governing meeting practice, including the validity of proxy nomination forms and the effect of the respondent’s failure to attend the meeting where the motion was raised.
The Tribunal concluded that the installation of the hot water system did require approval from the owners corporation and that the use was not minor, necessitating a special resolution. The Tribunal found that the meeting where the motion was raised was not properly conducted, primarily due to the use of proxy nomination forms, which were not in accordance with the statutory requirements. The Tribunal also held that the respondent’s failure to attend the meeting meant that the motion to approve the installation was not validly passed. Consequently, the Tribunal ruled that the respondent must either obtain the necessary authority for the installation or remove the hot water system within 90 days of the order.
The Tribunal ordered that within 90 days of the date of the order, the respondent must either obtain the necessary authority for the installation of the hot water system on the rear wall of the common property or remove the system from the common property. The Tribunal found the respondent's interim application statute barred, meaning it could not be considered further.
Orders
Orders of the court
The Tribunal orders that:
1. Pursuant to subsections 129(1)(a) and 129(2) of the Unit Titles (Management) Act 2011 (UTM Act), within 90 days of the date of this order, the respondent must either:
a) obtain the necessary authority under the UTM Act for the installation or continued presence of the hot water system on the rear wall of the common property; or
b) remove the hot water system from the rear wall of the common property.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.