The Owners Strata Plan No 76502 v Waterpoint Shepherds Bay Pty Limited

Link copied
Case Copied 12 min read

Supreme Court


New South Wales

Medium Neutral Citation: The Owners Strata Plan No 76502 v Waterpoint Shepherds Bay Pty Limited [2015] NSWSC 1129
Hearing dates:7 August 2015
Decision date: 07 August 2015
Jurisdiction:Equity Division - Technology and Construction List
Before: McDougall J
Decision:

Declare that there is a binding agreement to settle litigation. Order defendants to perform.

Catchwords:

CONTRACT – offer to settle litigation – time – where defendant made a ‘walk away’ offer, open for 28 days – where that offer accepted on 28th day – whether relevant that time of acceptance was later than time of offer – common law position on taking fractions of days into account

 

CONTRACT – offer to settle litigation – counter-offers – where, before acceptance, plaintiff inquired of the defendant whether it might be able to get a better offer – whether that inquiry amounted to a counter-offer such that the initial offer was rejected

  CONTRACT – offer to settle litigation – where offer stated to be ‘on terms requiring each party to pay its own costs of the proceedings’ – whether the phrase ‘on terms’ incorporated an expectation that further terms were to be negotiated – where, after acceptance, defendant sought to require execution of a deed of release – where no mention of such a requirement in initial offer – usual expectation that a competent solicitor will specify in detail the terms on which an offer is made – result that a deed of release was not required
Legislation Cited: Interpretation Act 1987 (NSW)
Uniform Civil Procedure Rules 2005 (NSW)
Cases Cited: La Forrest v Ford [2001] QCA 455
Category:Principal judgment
Parties: The Owners – Strata Plan No 76502 (Plaintiff)
Waterpoint Shepherds Bay Pty Limited (First Defendant)
Billbergia Pty Limited (Second Defendant)
Representation:

Counsel:
J Knackstredt (Plaintiff)
J Crittenden (Solicitor) (First and Second Defendants)

  Solicitors:
Doyle Edwards Anderson Lawyers (Plaintiff)
Jane Crittenden Lawyer (First and Second Defendants)
File Number(s):2013/137922

Judgment   (ex tempore – revised 7 august 2015)

  1. HIS HONOUR: The plaintiff is the Owners Corporation of a strata title development at Meadowbank. The defendants were, respectively, the developer and builder. The plaintiff sued the defendants for alleged defects in construction.

Background

  1. There was a dispute resolution process followed through which did not in itself achieve a resolution of the dispute. However after that process had been engaged in, and as part of the course of preparation for a final hearing, the defendants’ solicitor Ms Crittenden sent to the plaintiff’s solicitor Mr Anderson by email a letter forwarding an expert witness’s report.

  2. That letter stated, among other things:

I am instructed to reject your client’s settlement offer of $100,000 inclusive of costs in full and final settlement of the matter. My client has offered to consent to a discontinuance of the proceedings on terms requiring each party to pay its own costs of the proceedings. This offer shall remain open for a period of 28 days from the date of this letter.

  1. It is common ground that the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read The Owners Strata Plan No 76502 v Waterpoint Shepherds Bay P... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2015] NSWSC 1129
Decision Date

CaseChat Overview and Summary

In the case of The Owners Strata Plan No 76502 v Waterpoint Shepherds Bay Pty Limited, the dispute arose from a strata plan where the plaintiff sought to enforce an offer to settle the litigation. The defendant had made a settlement offer, open for 28 days, which the plaintiff accepted on the 28th day. The central issue before the court was whether the timing of acceptance, being later in the day than the time of the offer, affected the validity of the acceptance under common law principles. Additionally, the court had to consider whether the plaintiff’s inquiry about a potentially better offer constituted a counter-offer, thereby rejecting the initial settlement proposal.

The court examined the common law position regarding the significance of fractions of days in the context of settlement offers. It concluded that the time of acceptance being slightly later on the 28th day did not invalidate the acceptance. The court also found that the plaintiff’s inquiry about a potentially better offer did not amount to a counter-offer that would have rejected the defendant’s initial settlement proposal. Instead, the inquiry was seen as a legitimate attempt to explore the possibility of a more favourable settlement. Furthermore, the court held that the phrase ‘on terms requiring each party to pay its own costs of the proceedings’ did not imply an expectation for further terms to be negotiated. Consequently, the requirement for a deed of release was not part of the initial offer, and the defendant’s insistence on such a document post-acceptance was not permissible.

In summary, the court upheld the validity of the settlement offer and its acceptance, dismissing the defendant's attempts to impose additional conditions post-acceptance. The court's ruling reinforced the importance of clarity in settlement offers and the consequences of overlooking detailed terms. The final orders of the court will reflect the enforcement of the settlement agreement as accepted by the plaintiff.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established