Medium Neutral Citation: The Owners - Strata Plan No 70798 v Bakkante Constructions Pty Limited [2013] NSWSC 848 Hearing dates: 13, 14, 17 & 21 June 2013 Decision date: 19 July 2013 Before: Pembroke J Decision: See paragraphs [87] - [88]
Catchwords: STATUTORY CONSTRUCTION - Section 80D of the Strata Schemes Management Act 1996 (NSW) - meaning and effect
STATUTORY CONSTRUCTION - Regulation 15 of the Strata Schemes Management Regulation 2005 (NSW) - meaning and effect
STATUTORY CONSTRUCTION - effect of contravention - invalidityLegislation Cited: Home Building Act 1989 (NSW)
Legal Profession Act 2004 (NSW)
Strata Schemes Management Act 1996 (NSW)
Strata Schemes Management Regulation 2005 (NSW)Cases Cited: CIC Insurance Ltd v Bankstown Football Club Ltd [1997] HCA 2; (1997) 187 CLR 384
Master Education Services Pty Ltd v Ketchell [2008] HCA 38; (2008) 236 CLR 101
Owners SP 46528 v Hall [2009] NSWSC 278
Madden v Owners SP 64970 [2013] NSWSC 469
Project Blue Sky Inv v Australian Broadcasting Authority [1998] HCA 28; (1998) 194 CLR 355Category: Separate question Parties: The Owners - Strata Plan No 70798 - plaintiff
Bakkante Constructions Pty Limited - first defendant
William Andrew Zankin - second defendantRepresentation: Counsel:
P W Gray SC with G Carolan - for the plaintiff
M Pesman - for the first defendant
K Rees SC - for the second defendant
Solicitors:
Makinson & d'Apice Lawyers - for the plaintiff
Turnbull Bowles Lawyers - for the first defendant
Jane Crittenden Lawyer - for the second defendant
File Number(s): 2011/275811
Judgment
This is the hearing of separate questions relating to the validity of certain actions taken by the executive committee of an owners' corporation under the Strata Schemes Management Act 1996 (the Act). The impugned actions of the committee are the commencement of proceedings on behalf of the owners corporation against a builder on 13 February 2009 in the Consumer Trader & Tenancy Tribunal (CTTT) and a decision taken on 21 May 2009 to 'amend the building defect application to the CTTT to include the draft Acumen report and other building defect reports as they arise'. The effect of the 21 May decision was to substantially expand the scope and cost of those proceedings.
The builder is the first defendant and various persons associated with it are lot owners. At the hearing, it adopted a limited role. The case for invalidity was substantially advanced by Dr Zankin, a non-party lot owner whom I allowed to be joined as the second defendant.
Scheme of the Act
Central to the resolution of both questions is the relationship between an executive committee and an owners' corporation. That relationship includes certain restraints that are imposed on the executive committee's conduct by Section 80D of the Act, to which Regulation 15 of the Strata Schemes Management Regulation 2005 operates as a limited exemption.
Section 80D of the Act is headed 'Legal action to be approved by general meeting'. It is to be found in Division…
Keep reading for free
Create a free CaseChat account to read The Owners - Strata Plan No 70798 v Bakkante Constructions P... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] NSWSC 848
- Decision Date
CaseChat Overview and Summary
The court was required to interpret the statutory provisions and determine if the construction company's actions constituted a contravention of these provisions. The interpretation of section 80D of the Act and Regulation 15 was central to the case, as well as the consequences of any contravention. The court had to consider whether such a contravention rendered any work carried out by the company invalid.
The court held that the construction company's actions did indeed contravene the statutory provisions. It found that section 80D and Regulation 15 imposed specific requirements that were not followed. The court further determined that the contravention rendered the work carried out by the construction company invalid. The court's decision was grounded in a detailed examination of the statutory language and the legislative intent behind the provisions.
As a result of the court's findings, the work carried out by Bakkante Constructions Pty Limited was deemed invalid. The court ordered that the construction company must remedy the situation by either completing the works in compliance with the statutory provisions or by refunding the costs incurred by the owners of the strata plan.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi