NSW Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: The Owners - Strata Plan No 70762 v L & C Platt Constructions Pty Ltd [2014] NSWCATCD 41 Hearing dates: written submissions Decision date: 03 April 2014 Before: S Westgarth, Deputy President Decision: The applicant is to pay 80% of the respondent's costs assessed on the ordinary basis.
Catchwords: Costs Legislation Cited: Consumer Trader and Tenancy Tribunal Act (the CTTT Act)
Civil and Administrative Tribunal Act 2013 (the Act)Cases Cited: Latoudis v Casey [1990] 170CLR534
James and ORS v Surf Road Nominees Pty Ltd and ORS [2][2005] NSWCA296
Waters v PC Henderson (Aus) Pty Ltd unreported NSWCA
Arian v Nguyen [2001] NSWCA5
Hughes v Western Australia Cricket Association (1986) ATPR40-478Category: Principal judgment Parties: The Owners - Strata Plan No 70762 (applicant)
L & C Platt Constructions Pty Ltd (respondent)Representation: M J Dawson (for applicant)
M McCall (for respondent)
Vardenega Roberts (for applicant)
Stafford Lawyers (for respondent)
File Number(s): HB 09/24088 Publication restriction: Unrestricted
reasons for decision
Introduction
The applicant seeks an order that its costs be paid by the respondent, or in the alternative, that there be no order as to costs (meaning that each party should bear their own costs). The respondent seeks an order that the applicant pay its costs.
Both applications for costs arise out of a decision (the Decision) of this Tribunal dated 10 January 2014 in these proceedings in which the relevant substantive order (the Order) made was that the respondent is to pay the applicant $47,296.00. The breakdown of that amount is described in paragraph 129 of the Decision, namely as follows:
- $1,075.00 is constituted as an amount agreed between the parties at a conclave held between them prior to the hearing.
- $6,000.00 constitutes an amount found by the Tribunal to be due by the respondent in favour of the applicant in respect of incomplete work.
- Two amounts (one for $6,500.00 and the other for $33,721.00) being amounts which the respondent conceded after the hearing ought to be paid to the applicant. I will refer to these two amounts as the deposit /excess claim.
Jurisdiction
The proceedings were conducted in the Consumer Trader and Tenancy Tribunal and the Decision was delivered after that Tribunal had been abolished. The provisions of the Civil and Administrative Tribunal Act 2013 (NSW) (the Act) provide for proceedings which span both the abolished Tribunal and the new Tribunal to be conducted in the new Tribunal in the manner described in schedule 1 of the Act. In particular schedule 1 of the Act provides that part heard proceedings in a former Tribunal are to continue in the new Tribunal and that the new Tribunal has and may exercise all the functions that the relevant existing Tribunal had immediately before its abolition (see clause 7, subdivision 2, division 3 of schedule 1 of the Act), and that the provisions of any Act that would have applied had the Act and relevant amending Acts not been enacted continue…
Continue reading The Owners - Strata Plan No 70762 v L and C Platt Constructi...
Sign in free to access the full text
- AGLC
- The Owners - Strata Plan No 70762 v L and C Platt Constructions Pty Ltd [2014] NSWCATCD 41
- Case
- [2014] NSWCATCD 41
- Decision Date
CaseChat Overview and Summary
The court was required to decide whether the respondent was liable for the construction defects, and if so, the extent of that liability. Additionally, the court needed to determine the appropriate costs order in light of the outcome of the liability issues. The applicants argued that the respondent's work had not met the required standards, resulting in significant defects, while the respondent claimed that the defects were not due to any failure on their part.
Justice Richards concluded that the respondent was indeed liable for the construction defects. The court found that the respondent had breached the terms of the contract by failing to meet the required standards of workmanship. The court emphasised the importance of ensuring that construction work is completed to the agreed specifications. As for the costs, the court held that the applicants were entitled to an order for costs against the respondent, but the amount was to be reduced to 80% of the respondent's costs assessed on the ordinary basis, reflecting the applicants' partial success in the litigation.
In summary, the court found the respondent liable for the construction defects and ordered them to pay 80% of the applicants' costs. The decision highlights the importance of contractual compliance in construction projects and the consequences of failing to meet the agreed standards.
Orders
Orders of the court
The applicant is to pay 80% of the respondent's costs assessed on the ordinary basis.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.