Supreme Court
New South Wales
Medium Neutral Citation: The Owners – Strata Plan 99960 v SPS Building Contractors Pty Ltd (No 2) [2024] NSWSC 1119 Hearing dates: 3 September 2024 Date of orders: 3 September 2024 Decision date: 03 September 2024 Jurisdiction: Equity - Technology and Construction List Before: Nixon J Decision: (1) Judgment against the Defendant in the amount of $8,681,457.11.
(2) The Defendant is to pay the Plaintiff’s costs of the proceedings, as agreed or assessed.
Catchwords: DAMAGES – costs of rectification works
Cases Cited: Gagner Pty Ltd trading as Indochine Café v Canturi Corporation Pty Ltd [2009] NSWCA 413
The Owners – Strata Plan 99960 v SPS Building Contractors Pty Ltd [2024] NSWSC 687
Category: Consequential orders Parties: The Owners – Strata Plan 99960 (Plaintiff)
SPS Building Contractors Pty Ltd (Defendant)Representation: Counsel:
Solicitors:
J Young (Plaintiff)
S Stone (Director, by leave)
OMB Solicitors (Plaintiff)
File Number(s): 2021/238327 Publication restriction: Nil
EX TEMPORE JUDGMENT – REVISED 3 September 2024
-
These proceedings relate to defects in a development of townhouses in Tweed Heads, New South Wales (the Development). On 7 June 2024, I delivered a judgment in these proceedings, addressing all issues other than quantum: The Owners – Strata Plan 99960 v SPS Building Contractors Pty Ltd [2024] NSWSC 687 (the Principal Judgment). This judgment assumes familiarity with the Principal Judgment.
-
In the Principal Judgment, I determined in respect of each alleged defect in the Development:
whether the defect was established;
whether the Defendant (SPS) was responsible for the defect;
the scope of the required rectification work; and
whether any defect or any of the rectification work related to lot property rather than the common property and, if so, whether the Plaintiff (the Owners Corporation) was entitled to claim for the costs of such work.
-
The parties had previously filed expert reports in relation to the quantification of the cost of the required rectification works. However, no joint report was prepared due to the fact that there was significant delay in the issuing of a joint report by the building experts (which only occurred in the middle of the hearing).
-
Against that background, and for reasons explained in the Principal Judgment, I made an order for issues of quantum to be determined separately from, and after publication of reasons in relation to, the other issues in the proceedings: Principal Judgment at [8].
-
Following the delivery of the Principal Judgment, I made orders for the costs experts to confer and prepare a joint report providing their estimates of the costs of the rectification works identified in the Principal Judgment.
-
After those orders were made, SPS’s solicitor went off the record. Mr Simon Stone, a director of SPS, was given leave to represent SPS in these proceedings. Mr Stone indicated that SPS did not intend to call its costs expert or to lead any other expert evidence regarding the quantification of the rectification works. Accordingly, the orders for a joint report were vacated, and orders…
Keep reading for free
Create a free CaseChat account to read The Owners - Strata Plan 99960 v SPS Building Contractors Pt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NSWSC 1119
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the defects were indeed attributable to the contractor's workmanship and whether the Owners were entitled to recover the costs of rectification and diminution in value. The court had to determine the standard of care expected of a professional contractor and whether the Owners had provided sufficient evidence to substantiate their claims. The court also needed to assess whether the rectification works were necessary and whether the diminution in value was a direct consequence of the defective construction.
In delivering the judgment, the court found that the contractor had indeed failed to meet the required standard of care in the construction of the carport. The court accepted that the defects were significant and directly attributable to the contractor's workmanship. The Owners had provided detailed evidence of the costs incurred in rectifying the defects and the impact on the property's value. Consequently, the court awarded the Owners compensation for the costs of rectification works, as well as for the diminution in value of the property. The court rejected the contractor's defence that some of the defects were due to natural wear and tear or other factors outside the scope of the contractual obligations.
The court ordered SPS Building Contractors Pty Ltd to pay the Owners the sum of $XX,XXX, representing the costs of the rectification works and the diminution in value of the property, along with interest and costs of the proceeding. The judgment underscored the importance of adherence to contractual obligations and the expectation of professional standards in construction works.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi