District Court
New South Wales
Medium Neutral Citation: The Owners – Strata Plan 94800 v Aushome Construction Pty Ltd & Anor (No. 2) [2025] NSWDC 195 Hearing dates: On the papers Date of orders: 30 May 2025 Decision date: 30 May 2025 Jurisdiction: Civil Before: Abadee DCJ Decision: See paragraph [42].
Catchwords: JUDGMENTS AND ORDERS – final quantification of costs for rectification works – final orders for damages, interest and costs – no issue of principle
Legislation Cited: Civil Procedure Act2005 (NSW), ss 60, 61, 98
Home Building Act1989 (NSW), 92, Schedule 1 – s 2
Home Building Regulation 2014 (NSW), rr 5, 56
Uniform Civil Procedure Rules 2005 (NSW), r 42.1
Cases Cited: Oshlack v Richmond River Council (1998) 193 CLR 72
The Owners – Strata Plan 94800 v Aushome Construction Pty Ltd [2025] NSWDC 143
Texts Cited: Nil.
Category: Consequential orders Parties: The Owners – Strata Plan No 94800 (Plaintiff)
Aushome Construction Pty Ltd (ACN 114 033 055) (First Defendant)
South Summit Group Pty Ltd (ACN 166 478 431) (Second Defendant)Representation: Counsel:
Solicitors:
M Gunning (Plaintiff)
Madison Marcus (Plaintiff)
First Defendant (P Rao, Director of the First Defendant, in person)
Second Defendant (W Zhang, Director of the Second Defendant, in person)
File Number(s): 2023/00363237 Publication restriction: Nil.
REASONS FOR JUDGMENT
Background
-
On 28 April 2025, I delivered my reasons for judgment in the proceeding. [1] At the conclusion of the Reasons, I made the following orders:
1. The Owners – Strata Plan 94800 v Aushome Construction Pty Ltd [2025] NSWDC 143 (the ‘Reasons’).
“(1) Pursuant to s 61(2) of the Civil Procedure Act2005 (NSW):
(a) Mr George Dahrie (or some such other registered Design Practitioner as the defendants nominate) is to prepare, at the defendants’ cost, a Regulated Design to address the matters referred to by the building experts in items 4.3 and 31.1 in the plaintiff’s Updated Scott Schedule within 14 days of the date of these reasons and supply them to the parties.
(b) Mr Stephen Bolt, of the firm WT Partnership, is to prepare, at the shared costs of the parties, a report quantifying the costs of such Regulated Design within 7 days of receipt of the report referred to in (a) and to provide a copy of such report to the parties.
(2) Within 5 business days of its receipt of the report in order (1)(b) above, the plaintiff is to make submissions on:
(a) the quantification of costs specifically for items 4.3 and 31.1; and
(b) the final quantification of costs generally, as well as pre-judgment interest and costs in accordance with these reasons.
(3) Within a further 5 days of receipt of the plaintiff’s submissions the subject of orders 2(a)–(b) above, the defendants are to make submissions on:
(a) the quantification of costs for items 4.3 and 31.1 specifically; and
(b) the final quantification of costs generally, as well as pre-judgment interest and costs.
(4) All of the reports and submissions referred to in these orders are to…
Keep reading for free
Create a free CaseChat account to read The Owners - Strata Plan 94800 v Aushome Construction Pty Lt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] NSWDC 195
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the defendant's work was defective and, if so, the extent of the damages to be awarded to the plaintiff. The court needed to determine the quantum of the costs for the rectification works, as well as the interest on those costs, and the costs of the litigation. The court also had to consider whether the plaintiff's claims for damages and costs were substantiated by the evidence presented.
The court found that the defendant's work was indeed defective, leading to significant issues that required rectification. The court meticulously assessed the evidence and expert reports to quantify the costs of rectification. It determined that the plaintiff's claims were reasonable and proportionate to the defects found. Consequently, the court awarded the plaintiff damages for the rectification works, along with interest and legal costs. The court emphasised that the case did not present any novel legal principles but rather involved the application of established legal standards to the facts presented.
The final orders of the court included the award of damages for the rectification works, interest on those damages, and the costs of the litigation to be borne by the defendant. The court provided detailed calculations and reasoning for each component of the award, ensuring clarity and fairness in its decision.
Orders
Orders of the court
See paragraph [42].
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.