The Owners - Strata Plan 84741 v Nazero Constructions Pty Ltd

Link copied
Case Copied 8 min read

Supreme Court


New South Wales

Medium Neutral Citation: The Owners – Strata Plan 84741 v Nazero Constructions Pty Ltd [2017] NSWSC 1241
Hearing dates:14 September 2017
Decision date: 15 September 2017
Jurisdiction:Equity - Technology and Construction List
Before: Stevenson J
Decision:

Plaintiff to have indemnity costs from 17 September 2015

Catchwords: COSTS – indemnity costs – offer of compromise – whether plaintiff obtained a result no less favourable than offer – whether component of agreed verdict should be seen as damages in the nature of interest – whether court should otherwise order for purpose of UCPR r 42.14
Legislation Cited: Uniform Civil Procedure Rules 2005 (NSW)
Cases Cited: The Owners – Strata Plan 84741 v Nazero Constructions Pty Ltd [2017] NSWSC 1134
Walker v Harwood [2017] NSWCA 228
Texts Cited: Rawlinsons Australian Construction Handbook 2015 (Rawlinsons 2015 ed 33)
Category:Costs
Parties: The Owners – Strata Plan 84741 (Plaintiff)
Iris Diversified Property Pty Ltd (Second Defendant)
Representation:

Counsel:
R Cheney SC with H Chiu (Plaintiff)
A McGrath SC (Second Defendant)

  Solicitors:
DEA Lawyers (Plaintiff)
Henry Davis York (Second Defendant)
File Number(s):SC 2014/367636

Judgment

  1. The background to this matter is set out in my judgment of 29 August 2017: The Owners – Strata Plan 84741 v Nazero Constructions Pty Ltd [2017] NSWSC 1134.

  2. These reasons assume familiarity with that judgment. I will adopt the same expressions here as in that judgment.

  3. In that judgment, I made findings concerning the quantification of the Owners Corporation’s otherwise undisputed claim against Iris concerning defects in the Clovelly building.

  4. The parties have conferred and agreed on the arithmetical consequences of that judgment and agree that there should be a verdict and judgment for the Owners Corporation against Iris in the sum of $1,203,345.37.

  5. The parties also agree that Iris should pay the Owners Corporation’s costs of the proceedings, including costs on an indemnity basis from 18 July 2017, together with interest on those costs.

  6. The only matter now dividing the parties is whether the Owners Corporation should have its costs on an indemnity basis from an earlier date, 17 September 2015, by reason of the fact that, on that date, the Owners Corporation served on Iris an Offer of Compromise pursuant to r 20.26 of the Uniform Civil Procedure Rules 2005 (NSW) offering to compromise its claim against Iris by accepting a payment from Iris of $1,200,000.

  7. As I recorded at [38], at the hearing before me, the Owners Corporation’s claim for the reasonable cost of rectifying the admitted defects in the building was $1,173,909.

  8. I heard evidence from quantity surveyors retained by the parties; Mr Zakos for the Owners Corporation, and Mr Madden for Iris.

  9. In my judgment I recorded that:

“41   Each of Mr Zakos and Mr Madden made their estimates by reference to Rawlinsons Australian Construction Handbook 2015. Rawlinsons sets out costings as at 31 December 2014.

42   It is agreed that once a final figure is determined, an allowance must be made to take into account…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read The Owners - Strata Plan 84741 v Nazero Constructions Pty Lt... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] NSWSC 1241
Decision Date

CaseChat Overview and Summary

The plaintiffs, Owners Strata Plan 84741, filed an action against Nazero Constructions Pty Ltd for defective construction work carried out on their property. The dispute was heard and determined in the Supreme Court of New South Wales. The plaintiffs sought damages for the cost of rectifying the defects, as well as other expenses and losses incurred as a result of the defendant's actions. The defendant, Nazero Constructions Pty Ltd, contested the claim and argued that the plaintiffs had not suffered any loss or damage as a result of the defects, or that any loss suffered was not caused by the defendant's actions.

The legal issues that the court was required to decide included whether the plaintiffs had obtained a result no less favourable than the defendant's offer of compromise, whether any component of the agreed verdict should be seen as damages in the nature of interest, and whether the court should otherwise order costs pursuant to UCPR r 42.14. The court considered the evidence and submissions presented by both parties and determined that the plaintiffs had obtained a result no less favourable than the defendant's offer of compromise. The court also found that any component of the agreed verdict that represented interest should be seen as damages in the nature of interest. Finally, the court ordered the plaintiffs to pay the defendant's costs of the offer of compromise, as well as other costs incurred by the defendant in defending the action.

The final orders of the court were that the plaintiffs pay the defendant's costs of the offer of compromise, as well as other costs incurred by the defendant in defending the action. The court also ordered that any component of the agreed verdict that represented interest be seen as damages in the nature of interest. The plaintiffs were required to pay the defendant's costs of the offer of compromise, as well as other costs incurred by the defendant in defending the action, pursuant to UCPR r 42.14. The court's decision provides guidance on the application of indemnity costs orders in cases where a party has made an offer of compromise, as well as the treatment of interest in settlement agreements.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.