Medium Neutral Citation: The Owners – Strata Plan 70030 v Decon Australia [2016] NSWSC 19 Hearing dates: 1 February 2016 Date of orders: 01 February 2016 Decision date: 01 February 2016 Jurisdiction: Equity - Technology and Construction List Before: McDougall J Decision: Grant plaintiff leave to amend list statement and to rely upon further evidence.
Catchwords: PRACTICE AND PROCEDURE – Claim for defective work – Notice of Motion application to rely on Amended List Statement – Whether leave should be granted to plaintiff rely on Amended List Statement and further allegations of defective work – Whether leave should be granted to rely upon further export reports – Balance of justice weighted in favour of plaintiff – Leave granted Legislation Cited: Home Building Act 1989 (NSW) Cases Cited: Onerati v Phillips Constructions Pty Ltd (1989) 16 NSWLR 730 Category: Procedural and other rulings Parties: The Owners – Strata Plan No 70030 (Plaintiff)
Decon Australia Pty Ltd (First Defendant)
Eissa Soliman Tadros (Second Defendant)
Afaf Aziz Tadros (Third Defendant)
Shawki Hanna Gad (Fourth Defendant)
Lily Aziz Gad (Fifth Defendant)Representation: Counsel:
Solicitors:
D Feller SC / I D George (Plaintiff)
T J Davie (Second to Fifth Defendants)
Spinks Elphick Ho (Second to fifth defendants)
Peter Merity Solicitor Pty Limited (Plaintiff)
File Number(s): 2014/179564
Judgment (ex tempore – revised 1 february 2016)
-
HIS HONOUR: The plaintiff (the Owners Corporation) is the owners corporation of a strata title development at Narrabeen. The second to fifth defendants (the developers) are (or at least I assume that they may be regarded as) the "developers", for the purposes of the Home Building Act 1989 (NSW), for whom that development was undertaken. The first defendant (Decon) was the builder who carried out the work. It did so pursuant to a contract with the developers, who were at the relevant time the proprietors of the land on which the work was executed. The developers are, in proportions which it is unnecessary to set out, proprietors of some six of the fifteen residential lots in the development.
-
The Owners Corporation's claim is for defective work. It sues on the statutory warranties given by s18B of the Home Building Act.
-
The proceedings have a history which can best be described as appalling. Practical completion occurred on 11 February 2003. The occupation certificate was issued seven days later, and the strata plan was registered on 20 March 2003. The application was not filed until 24 August 2009. It was filed in the Consumer, Trader and Tenancy Tribunal (CTTT). A Mr Ian Jones acted for the Owners Corporation.
-
Notwithstanding the delayed commencement of proceedings (which might be thought to indicate some reflection by the Owners Corporation and Mr Jones upon the subject matters of their complaints), the Owners Corporation failed lamentably to comply with directions given from time to time by the CTTT. It appears to be uncontentious that the Owners Corporation failed to comply with directions given on nine occasions between 15 March 2010 and 17…
Keep reading for free
Create a free CaseChat account to read The Owners - Strata Plan 70030 v Decon Australia and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] NSWSC 19
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the plaintiff should be granted leave to rely on the Amended List Statement and the further allegations of defective work, and whether leave should be granted to rely upon the additional export reports. The defendant argued that these additional allegations and documents were not properly disclosed or allowed under the court's case management rules, and that allowing them would prejudice the defendant's right to a fair trial. The plaintiff, on the other hand, contended that the balance of justice favoured permitting the additional evidence, as it was necessary to fully address the issues at hand and ensure a just outcome.
The court considered the principles of case management and the overriding objective of achieving justice in the circumstances. It found that the balance of justice weighed in favour of granting the plaintiff leave to rely on the Amended List Statement and the further allegations of defective work, as well as the additional export reports. The court acknowledged that the defendant had been prejudiced to some extent by the late disclosure of these materials, but determined that the prejudice was not insurmountable and could be mitigated through appropriate orders. The court also considered the importance of allowing the plaintiff to present its full case and the potential for significant injustice if the additional evidence was not permitted.
Accordingly, the court granted leave to the plaintiff to rely on the Amended List Statement and further allegations of defective work, as well as the additional export reports. The court ordered that the defendant be given a reasonable opportunity to respond to the new evidence and that any necessary adjournments be scheduled to accommodate this. The court emphasised the importance of adhering to case management rules and timely disclosure of evidence, but recognised that exceptions may be warranted in the interests of justice. The court's decision ensured that the plaintiff could present its full case and that the defendant had a fair opportunity to address the new allegations and evidence.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.