The Owners - Strata Plan 65111 v Meriton Apartments Pty Ltd

Link copied
Case Copied 16 min read

Supreme Court


New South Wales

  • Amendment notes
Medium Neutral Citation: The Owners – Strata Plan 65111 v Meriton Apartments Pty Ltd [2016] NSWSC 650
Hearing dates:11 & 12 May 2016
Decision date: 20 May 2016
Jurisdiction:Equity - Technology and Construction List
Before: Stevenson J
Decision:

Referee’s construction of operative agreement correct

Catchwords: PRACTICE - reference by court - finding by referee as to the proper construction of operative agreement - whether referee erred in law; CONTRACTS - proper construction – settlement deed – contract to do residential building work – nature of builder’s obligation to effect rectification works - whether certifier empowered to alter manner in which rectification works be effected and designated standard be achieved
Legislation Cited: Environmental Planning and Assessment Act 1979 (NSW)
Uniform Civil Procedure Rules 2005 (NSW)
Cases Cited: Homebush Abattoir Corporation v Bermria Pty Ltd (1991) 22 NSWLR 605
Maritime Services Board of New South Wales v Australian Shipping Commission (1991) 27 NSWLR 258
Super Pty Ltd v SJP Formwork (Aust) Pty Ltd (1992) 29 NSWLR 549
Category:Procedural and other rulings
Parties: The Owners – Strata Plan 65111 (Plaintiff/Respondent)
Meriton Apartments Pty Limited (Defendant/Applicant)
Representation:

Counsel:
T Davie (Plaintiff/Respondent)
F Corsaro SC (Defendant/Applicant)

  Solicitors:
Bannermans Lawyers (Plaintiff/Respondent)
N Malouf (Defendant/Applicant)
File Number(s):SC 2008/290601

Judgment

  1. The defendant, Meriton Apartments Pty Limited, developed and built a residential tower building in George Street, Sydney which became known as the “Summit Apartments”.

  2. Construction work was completed in March 2001, at which time the plaintiff Owners Corporation was created.

  3. On 11 January 2008 the Owners Corporation commenced proceedings against Meriton claiming damages for defects alleged to exist in the common property.

  4. On 28 March 2014 the whole of those proceedings were referred to Ms Janet Gray, an architect, for inquiry and report, under Uniform Civil Procedure Rules 2005 (NSW) Pt 20 r 20.14.

  5. The referee delivered her report on 28 August 2015.

  6. Meriton and the Owners Corporation are now in dispute as to the extent to which the report should be adopted.

  7. It is common ground that the report should be adopted pursuant to UCPR Pt 20 r 20.24 insofar as it concerns general building defects, out of pocket expenses and mechanical services.

  8. What is in contest is the adoption of that part of the report that deals with fire and life safety defects. The referee determined that Meriton should pay the Owners Corporation some $1.17 million in respect of those defects.

  9. One matter that the referee was called upon to consider was the proper construction of a Settlement Deed executed by the Owners Corporation, Meriton and the Council of the City of Sydney on 30 September 2002.

  10. A critical matter dividing the parties is whether the referee’s construction of the Settlement Deed was correct.

  11. It is common ground that this raises a question of law which, on an application for adoption of a referee’s report, I must myself determine: Super Pty Ltd v SJP Formwork (Aust) Pty Ltd (1992) 29 NSWLR 549 at 563E; Homebush…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read The Owners - Strata Plan 65111 v Meriton Apartments Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2016] NSWSC 650
Decision Date

CaseChat Overview and Summary

The Owners - Strata Plan 65111 brought proceedings against Meriton Apartments Pty Ltd regarding the construction and rectification works carried out in the residential building. The dispute centred on the proper construction of the settlement deed and the obligations of the builder under the contract to do residential building work. The dispute was ultimately referred to a referee, who made findings on the proper construction of the agreement. The Owners challenged the referee’s findings, arguing that the referee erred in law.

The central legal issue before the court was whether the referee had correctly interpreted the settlement deed, particularly regarding the nature of the builder’s obligation to effect rectification works and whether the certifier had the power to alter the manner in which these works were carried out and the standard to be achieved. The court had to determine if the referee had erred in law in making the findings that were contested by the Owners.

The court found that the referee had correctly interpreted the settlement deed, affirming that the builder’s obligation to effect rectification works did not necessarily mean that the certifier could alter the manner in which these works were to be carried out or the standard to be achieved. The court held that the referee’s findings were consistent with the proper construction of the settlement deed. As a result, the Owners’ challenge to the referee’s findings was dismissed.

The court made an order that the Owners pay the respondent’s costs of the appeal, which were assessed at $12,500.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established