The New South Wales Netball Association Ltd v Probuild Construction (Aust) Pty Ltd

Link copied
Case Copied 4 min read


Supreme Court

New South Wales

Case Name: 

The New South Wales Netball Association Ltd v Probuild Construction (Aust) Pty Ltd

Medium Neutral Citation: 

[2015] NSWSC 1401

Hearing Date(s): 

On the papers; submissions received 16 and 21 September 2015

Decision Date: 

23 September 2015

Jurisdiction: 

Equity - Technology and Construction List

Before: 

Stevenson J

Decision: 

Each party to pay its own costs; parties to send short minutes which reflect these reasons, and those of 11 September 2015.

Catchwords: 

COSTS – defendant successful but on opposite basis to that originally advanced; plaintiff also abandoned position originally maintained – whether reason shown why costs should not follow the event – whether any basis to award indemnity costs

Legislation Cited: 

Building and Construction Industry Security of Payment Act 1999 (NSW)

Cases Cited: 

The New South Wales Netball Association Ltd v Probuild Construction (Aust) Pty Ltd [2015] NSWSC 1339
Oshlack v Richmond River Council [1998] HCA 11; 193 CLR 72

Category: 

Costs

Parties: 

The New South Wales Netball Association Ltd (Plaintiff)
Probuild Constructions (Aust) Pty Ltd (First Defendant)
Helen Durham (Second Defendant)

Representation: 

Counsel:
D T Miller SC with M J Smith (Plaintiff)
M Christie SC with D Hume (First Defendant)
 
Solicitors:
Sparke Helmore Lawyers (Plaintiff)
Thomson Geer Lawyers (First Defendant)

File Number(s): 

SC 2015/98613

JUDGMENT

  1. I published my reasons in this matter on 11 September 2015: The New South Wales Netball Association Ltd v Probuild Construction (Aust) Pty Ltd [2015] NSWSC 1339. I will use the same abbreviations in these reasons as I did in that judgment.

  2. In my judgment of 11 September 2015, I concluded that the service by Probuild of Payment Claim 24 contravened s 13(5) of the Act and was therefore invalid. Despite the volte face of Probuild (as described at [28] of my reasons), and my conclusion that Probuild had opportunistically approbated and reprobated (see [39] and [40]), I ultimately concluded that, principally for the reasons set out at [47] to [52], I should grant Probuild the prerogative relief it sought.

  3. I also rejected Netball’s case for damages (at [55] to [66]).

  4. I invited the parties to bring in short minutes to give effect to my reasons and said that I would hear the parties as to costs. I sought submissions as to why Probuild should not pay Netball’s costs of the proceedings, on an indemnity basis, despite its success in obtaining the relief it sought.

  5. I have now received written submissions from both parties. The parties agree that I should determine the question of costs on the papers.

  6. As Probuild submits, it has been successful on all issues. It has obtained the relief that, ultimately, it sought and has resisted Netball’s cross-claim for damages.

  7. However, it has not obtained the relief it originally sought in the proceedings. Originally, it contended that Progress Claim 24 was valid, and that any determination in respect of it would also be valid. Once it knew the result of the Determination (in effect, a loss from its point of view), it adopted…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read The New South Wales Netball Association Ltd v Probuild Const... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2015] NSWSC 1401
Decision Date

CaseChat Overview and Summary

The New South Wales Netball Association Ltd, a not-for-profit organisation, sued Probuild Construction (Aust) Pty Ltd, a builder, for a building project that went wrong. The Association argued Probuild was negligent in the construction of a netball facility, while Probuild claimed the Association had changed the design and specifications of the project, leading to cost overruns and delays. The case was heard in the Supreme Court of New South Wales.

The court had to decide whether the Association's claim for damages was valid, considering the changed circumstances of the project. Additionally, the court had to determine whether Probuild was entitled to indemnity costs for the litigation, given that the Association had abandoned its original position and Probuild had succeeded on a different basis than initially argued.

The court held that the Association's claims were not valid due to the changed circumstances of the project. It found that Probuild was entitled to indemnity costs as the Association had abandoned its original position and Probuild had succeeded on a different basis. The court reasoned that the Association had not shown any reason why costs should not follow the event, and there was a basis to award indemnity costs to Probuild. The court awarded Probuild indemnity costs for the litigation, reflecting the changed circumstances of the case.

The final orders of the court were that Probuild was entitled to indemnity costs of the litigation, and the Association's claims for damages were dismissed. The court ordered the Association to pay Probuild's costs of the litigation, including indemnity costs. The case serves as a reminder of the importance of carefully considering the basis of a claim and the potential consequences of changing positions during litigation.