The Environment Centre Northern Territory v The Northern Territory Environment Protection Authority

Link copied
Case Copied 40 min read

CITATION:The Environment Centre Northern Territory v The Northern Territory Environment Protection Authority and Anor [2019] NTSC 69

PARTIES:THE ENVIRONMENT CENTRE NORTHERN TERRITORY

v

NORTHERN TERRITORY ENVIRONMENT PROTECTION AUTHORITY

and

THE ENVIRONMENT CENTRE NORTHERN TERRITORY

v

PASTORAL LAND BOARD OF THE NORTHERN TERRITORY

TITLE OF COURT:  SUPREME COURT OF THE NORTHERN TERRITORY

JURISDICTION:  SUPREME COURT exercising Territory jurisdiction

FILE NO:123 of 2017 (21759813) and 124 of 2017 (21759816)

DELIVERED:  4 September 2019

HEARING DATES:  6, 7 and 14 December 2018

JUDGMENT OF:  Barr J

CATCHWORDS:

ADMINISTRATIVE LAW – MEETINGS – ‘Proposed action’ – proposed land clearing on pastoral property – Authority charged with deciding whether a public environmental report (PER) or environmental impact statement (EIS) necessary – ‘meeting’ took place by exchange of emails over several days – motion not put to a vote – analysis of email communications – chairperson wrongly determined majority decision not to require EIS – decision not “determined by the majority vote of members present and voting” – no decision made as to necessity for PER – non-compliance with  mandatory legislative requirements – orders in the nature of certiorari and mandamus granted

Environmental Assessment Act 1982, s 3, s 4, s 7(1)

Northern Territory Environment Protection Authority Act 2012, s 6, s 7, s 8(1)(b), s 8(4), s 10(2), s 16, s 17, s 18, s 20(1), s 20(2) s 22, s 23,

Environmental Assessment Administrative Procedures, cl 6(1), cl 6(2), cl 8(1), cl 8(2)

Interpretation Act 1978, s 48A (2),

Minister for Natural Resources v New South Wales Aboriginal Land Council and anor (1987) 9 NSWLR 154; Minister for Immigration and Citizenship v Yucesan and Another [2008] FCAFC 110; 247 ALR 443; Lee v Napier and ors [2013] FCA 236, referred to

Everett v Griffiths [1924] 1 K.B. 941; The King v Hendon Rural District Council; Ex parte Thorley [1933] 2 K.B. 696, distinguished

REPRESENTATION:

Counsel:

Plaintiff:H Hutton; P Bellach

Defendants:S Brownhill SC, Solicitor-General;      L Peattie

Solicitors:

Plaintiff:Environmental Defenders Office (NT) Inc.

Defendants:Solicitor for the Northern Territory

Judgment category classification:    B

Judgment ID Number:  Bar1910

Number of pages:  33

IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWIN

The Environment Centre Northern Territory v The Northern Territory Environment Protection Authority and anor [2019] NTSC 69

No. 123 of 2017 (21759813) and 124 of 2017 (21759816)

BETWEEN:

THE ENVIRONMENT CENTRE NORTHERN TERRITORY

Plaintiff

AND:

NORTHERN TERRITORY ENVIRONMENT PROTECTION AUTHORITY

Defendant

AND BETWEEN:

THE ENVIRONMENT CENTRE NORTHERN TERRITORY

Plaintiff

AND:

PASTORAL LAND BOARD OF THE NORTHERN TERRITORY

Defendant

CORAM:    BARR J

REASONS FOR JUDGMENT

(Delivered 4 September 2019)

  1. Central to this litigation is a decision purportedly made by the Northern Territory Environment Protection Authority that the environmental impacts and risks of proposed vegetation clearing at Maryfield Station were not sufficiently significant to warrant environmental impact assessment under the Environmental Assessment Act 1982. I will refer to that decision as “the purported decision”.

  2. For reasons which follow, I find that the purported decision was not…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read The Environment Centre Northern Territory v The Northern Ter... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2019] NTSC 69
Decision Date

CaseChat Overview and Summary

The Environment Centre Northern Territory sought judicial review of a decision by the Northern Territory Environment Protection Authority (NT EPA) concerning a proposed land clearing project on pastoral property. The dispute centred on whether the NT EPA properly convened a meeting to make the decision, whether the decision was made in accordance with legislative requirements, and whether the decision was lawful. The case was heard by the Federal Court of Australia.

The primary legal issue was whether the NT EPA's decision was properly made, considering the statutory requirements for decision-making processes. Specifically, the court had to determine if the decision was made at a formal meeting where members were present and voted, as required by the Northern Territory Environment Protection Authority Act 2012. The court also considered whether the NT EPA's decision to not require an environmental impact statement (EIS) was compliant with the Environmental Assessment Act.

The court found that the decision was not properly made as it did not comply with the mandatory legislative requirements for a formal meeting. The decision was made through an exchange of emails over several days rather than at a convened meeting where members were physically present and voted. The NT EPA's internal procedures allowed for out-of-session consideration of papers, but this did not satisfy the statutory requirement for a majority vote at a convened meeting. The court held that because the decision was not made in accordance with the statutory requirements, it was invalid. The court also noted that the decision did not address the necessity for a public environmental report (PER), leaving this aspect unresolved.

The Federal Court granted orders in the nature of certiorari and mandamus, quashing the NT EPA's decision and directing the NT EPA to make a new decision in compliance with the statutory requirements. The court emphasised the importance of adhering to legislative mandates for decision-making processes to ensure transparency and accountability in administrative actions.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established

The purported decision was not made at a formal meeting at which members gathered together or attended in person. Rather, as described in [12] above, it involved consideration of an “Out-of-Session Briefing Paper”. The Authority was permitted to determine its own procedures by s 16 Northern Territory Environment Protection Authority Act 2012, and had previously issued a document entitled “Meeting Procedures and Processes” which made provision for “NT EPA Out-of-Session Process” and the consideration of “NT EPA Out-of- Session papers”.[17] The quorum for deliberation and decision about Out-of-Session papers was stated to be “a majority of members entitled to participate in the deliberation and/or decision of the Out-of-Session paper”. That appears to be consistent with the statutory quorum requirement in s 18 and the majority vote requirement in s 20 of the Act.[18]Consideration of the “Out-of-Session Briefing Paper” The briefing paper referred to in [12] and [19] recommended that the Authority decide that the Maryfield Station Land Clearing Project did not require assessment under the Environmental Assessment Act, for reasons which it was recommended the Authority approve.[19] The draft suggested statement of reasons concluded as follows:[20] Conclusion The NT EPA considers that the Project does not require further assessment under the EA Act and has provided recommendations to the PLB to ensure that impacts can be appropriately managed and responsibilities under other relevant legislation can be met. DECISION The proposed action, which was referred to the NT EPA by the Pastoral Land Board, has been examined by the NT EPA and preliminary investigations and inquiries conducted. The NT EPA has decided that the potential environmental impacts and risks of the proposed action are not so significant as to warrant an environmental impact assessment by the NT EPA under provisions of the Environmental Assessment Act. However, the proposed action will require assessment and approvals under the Pastoral Land Act to ensure the environmental issues associated with the proposed action are effectively managed.This decision is made in accordance with clause 8(2) of Environmental Assessment Administrative Procedures, and subject to clause 14A the administrative procedures are at an end with respect to the proposed action. On Wednesday 11 October 2017 at 10:25 AM, the following message was sent by email to all members of the Authority:Good Morning MembersPlease see attached OOS/2017-369-Maryfield Station Land Clearing Project, for decision, approval and notingYour response would be appreciated via reply email by Wednesday 18 October. If you have any major comments, please cc all in the email. The email was sent by Amanda Waa, executive officer to the Authority. The document(s) she referred to were not actually attached to the email but were uploaded to the ‘members only’ portal. Login details were provided to enable the recipients to access over 220 pages of documents which had been posted, comprising (inter alia) the “Out-of-Session Briefing Paper”, Agency comments, and draft suggested statement of reasons.[21] It appears (and there is no evidence to the contrary) that the recommended decision and the draft statement of reasons had been prepared by Departmental officers without previous input from the chairperson or the other members of the Authority. Members probably first learnt of the proposed action when they had access to the ‘members only’ portal after receiving the email from Ms Waa referred to in [21].