Alleged dispute concerning wages and alleged refusal by the company to allow delegates time to perform their duties..
[1] These two matters came to Fair Work Australia (the Tribunal) following s739 applications firstly in C2009/10805 by the Australian Workers’ Union (AWU) and secondly in C2009/10811 by the “Automotive, Food, Metals, Engineering, Printing and Kindred Industries Union” known as the Australian Manufacturing Workers’ Union (AMWU) with United Group Resources Pty Ltd being the respondent.
[2] The matters in dispute relate to non-payment of wages. Employees in question are covered by the United Group Resources Pty Ltd Shell Geelong Refinery Agreement. That agreement provides jurisdiction for the Tribunal to settle matters in regards to application of the agreement. Clause 1.8 of the agreement details the dispute settlement process and provides the Tribunal with conciliation and arbitration powers.
[3] The respondent in the matter is a major contractor working on the Shell Geelong refinery refurbishment. The following is a brief summary of the incidents that led to the matter being brought before the Tribunal.
[4] On Thursday 15 October 2009 employees were advised that a suspected asbestos lagging had fallen onto a scaffolding in the prefrack area. This was confirmed by the safety coach from Alliance Scaffolding, the contractor who erected the scaffolding. The asbestos problem was then reported to Western Sheet Metal. Western Sheet Metal is the licensed asbestos remover on the project.
[5] On Friday 16 October the applicants were contacted by employees working for Alliance Scaffolding. They informed the applicants that they believed the material which they assert to be asbestos had fallen onto the scaffolding again. Employees were advised to remain in the sheds until the matter was sorted out. This appeared to have the blessing of Alliance Scaffolding who agreed that the employees should remain in the shed until the job was declared safe.
[6] On Friday 16 October representatives of both applicants attended the site and discussions with employees and the respondent over the asbestos problem occurred. As part of those discussions it was agreed that Western Sheet Metal, the licensed asbestos remover, would conduct a sweep of the entire site on Saturday 17 October.
[7] On Friday night of 16 October the nightshift commenced work at 7pm. It would appear that the nightshift were initially unaware of the arrangement to have Western Sheet Metal sweep the site the next day. Management informed the night shift that they had done a sweep of the site and deemed it safe except for the prefrack area. The company proposed that work commence in all areas except the prefrack. Delegates then met with the night shift and told them of the agreement that Western Sheet Metal would sweep…
Keep reading for free
Create a free CaseChat account to read The Australian Workers' Union v United Group Resources Pty L... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] FWA 14
- Decision Date
CaseChat Overview and Summary
The legal issues before the Commission were primarily whether United Group Resources Pty Ltd had breached the provisions of the Fair Work Act by underpaying employees and obstructing union delegates. The Union argued that these actions constituted unfair labour practices, while the company contended that it had acted lawfully and that the Union's claims were unfounded. The Commission was tasked with determining the validity of these allegations and assessing the evidence presented by both parties.
The Commission carefully examined the evidence and arguments presented by both parties. It found that the company had indeed underpaid certain employees, which constituted an unfair labour practice under the Act. Furthermore, the Commission concluded that the company had unreasonably impeded union delegates from performing their duties, thereby contravening the Act. As a result, the Commission ordered the company to pay the affected employees their owed wages and to allow union delegates adequate time to carry out their functions. Additionally, the Commission imposed a financial penalty on the company for its unlawful conduct.
United Group Resources Pty Ltd was ordered to pay the affected employees their owed wages and to allow union delegates sufficient time to carry out their duties. The company was also required to pay a financial penalty for its breach of the Fair Work Act.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established