Teys Australia Beenleigh Pty Ltd
[2016] FWCA 2482
•19 APRIL 2016
| [2016] FWCA 2482 |
| FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.185 - Application for approval of a single-enterprise agreement
Teys Australia Beenleigh Pty Ltd
(AG2016/423)
TEYS BEENLEIGH PRODUCTION EMPLOYEES AGREEMENT
Meat Industry | |
DEPUTY PRESIDENT ASBURY | BRISBANE, 19 APRIL 2016 |
Application for approval of the Teys Beenleigh Production Employees Agreement.
[1] Teys Australia Beenleigh Pty Ltd applies for approval of an enterprise agreement known as the Teys Beenleigh Production Employees Agreement (the Agreement). The application was made pursuant to s.185 of the Fair Work Act 2009 (the Act). The agreement is a single-enterprise agreement.
[2] The Australasian Meat Industry Employees Union (the AMIEU) being a bargaining representative for the Agreement, has given notice under s.183 of the Act that this organisation wants the Agreement to cover it. In accordance with s.201(2) of the Act I note that the Agreement covers this organisation.
[3] On 15 March 2016, the Commission conducted a hearing/conference to consider issues raised by the AMIEU in relation to whether the Agreement passes the better off overall test (the BOOT). As a result, undertakings were discussed and agreed between the parties.
[4] On 31 March 2016 undertakings as agreed were provided by the Employer. Pursuant to s.190 of the Act, I accept the Employer’s undertakings. In accordance with s.201(3) of the Act I note that a copy of the undertakings is attached to the Agreement and forms part of the Agreement.
[5] The Agreement does not contain a consultation term that is consistent with the requirements in s.205 of the Act. Pursuant to s.205(2) of the Act, the model consultation term prescribed by the Fair Work Regulations 2009 is taken to be a term of the Agreement.
[6] The Agreement does not contain a flexibility clause that is consistent with the requirements in s203 of the Act. Pursuant s.202(4) of the Act, the model flexibility term prescribed by the Fair Work Regulations 2009 is taken to be a term of the Agreement.
[7] I am satisfied that each of the requirements of ss.186, 187 and 188 as are relevant to this application for approval have been met.
[8] The Agreement is approved, in accordance with s.54 of the Act, will operate from 26 April 2016. The nominal expiry date of the Agreement is 26 April 2017.
DEPUTY PRESIDENT
Printed by authority of the Commonwealth Government Printer
<Price code G, AE418645 PR579243>
0
0
0