Team Tech Pty Ltd v Sutherland Shire Council

Link copied
Case Copied 33 min read

Land and Environment Court


New South Wales

Medium Neutral Citation: Team Tech Pty Ltd v Sutherland Shire Council [2020] NSWLEC 1033
Hearing dates: 17-18 October 2019; 6 December 2019; 16 December 2019
Date of orders: 24 January 2020
Decision date: 24 January 2020
Jurisdiction:Class 1
Before: Horton C
Decision:

The Court orders that:
(1)   The Applicant is granted leave to amend the application and rely upon amended plans in Exhibit A subject to the Applicant paying those costs of the Respondent thrown away, as agreed or assessed.
(2)   The appeal is dismissed.
(3)   Development consent for Development Application DA18/0627 seeking consent for the demolition of existing structures and construction of 14 townhouses and strata subdivision is refused.
(4)   All exhibits are returned, except for Exhibits 9, 10, 11, 12 and K, N and P.

Catchwords: DEVELOPMENT APPEAL – multi-dwelling housing in R2 zone – whether a lot is an internal lot – clause 4.6 written request to justify height exceedance – streetscape and built form
Legislation Cited: Environmental Planning and Assessment Act 1979
Land and Environment Court Act 1979
Sutherland Shire Local Environmental Plan 2015
Cases Cited: Initial Action Pty Ltd v Woollahra Municipal Council [2018] NSWLEC 118
Texts Cited: Sutherland Shire Development Control Plan 2015
Category:Principal judgment
Parties: Team Teach Pty (Applicant)
Sutherland Shire Council (Respondent)
Representation:

Counsel:
J Reid (Applicant)
J Cole (Solicitor) (Respondent)

  Solicitors:
Boskovitz Lawyers (Applicant)
HWL Ebsworth (Respondent)
File Number(s): 2018/234494
Publication restriction: No

Judgment

  1. COMMISSIONER: This Class 1 appeal concerns a development application brought before the Court under s 8.7 of the Environmental Planning and Assessment Act 1979 (EPA Act) against the deemed refusal by the Sutherland Shire Council (the Respondent) of Development Application DA18/0627 seeking consent for the demolition of existing structures and construction of 18 townhouses and strata subdivision.

  2. Leave was granted by the Court on 21 August 2019 for the Applicant to amend the application for development consent. Leave was also granted by the Court on 5 September 2019 for the Applicant to rely on an amended flood assessment.

  3. Leave was also granted by the Court at the commencement of the hearing for the applicant to amend the application for development consent subject to the Applicant paying those costs of the Respondent thrown away as a result of the amendment of the leave granted on 21 August 2019 when compared to the application in Exhibit A, as agreed or assessed.

  4. The amended plans and documents comprise:

  • Architectural plans marked Exhibit A, along with a schedule of amendments.

  • Landscape plans, marked Exhibit B.

  • Stormwater Plans, marked Exhibit C.

  • BASIX and NATHERS certification, marked Exhibit D.

  1. On the second day of the hearing, and prior to hearing the oral evidence of the experts, I directed that the experts further confer on the Exhibit A plans in relation to those matters arising from the joint reports already entered as Exhibits. The experts conferred and provided the Court with supplementary reports marked Exhibit 10, 11 and 12.

  2. The Applicant relied on the expert…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Team Tech Pty Ltd v Sutherland Shire Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2020] NSWLEC 1033
Decision Date

CaseChat Overview and Summary

Team Tech Pty Ltd applied to the Land and Environment Court of New South Wales to review the Sutherland Shire Council's decision to refuse development consent for a proposed development on land in Sutherland. The proposed development included the demolition of existing structures and the construction of 14 townhouses, along with a strata subdivision. The council's refusal was based on various grounds, including the impact on the local environment and the inadequacy of the applicant's plans.

The legal issues before the court were whether the applicant should be granted leave to amend its application and rely on amended plans, and whether the council's decision to refuse development consent was lawful. The applicant argued that the refusal was unreasonable and that the amended plans addressed the council's concerns. The council contended that the amended plans did not sufficiently address the environmental and other concerns that led to the initial refusal.

The court found that the applicant was entitled to amend its application and rely on the amended plans, subject to the payment of costs. However, the court held that the council's decision to refuse development consent was not unreasonable. The court was not satisfied that the applicant had addressed the environmental and other concerns that led to the initial refusal. The court also found that the proposed development would have significant adverse environmental impacts, including on the local vegetation and the potential for increased stormwater runoff. The appeal was dismissed, and development consent was refused. The court ordered that certain exhibits be returned to the applicant, while others were to be retained by the court.

Orders

Orders of the court

The Court orders that:

(1) The Applicant is granted leave to amend the application and rely upon amended plans in Exhibit A subject to the Applicant paying those costs of the Respondent thrown away, as agreed or assessed.

(2) The appeal is dismissed.

(3) Development consent for Development Application DA18/0627 seeking consent for the demolition of existing structures and construction of 14 townhouses and strata subdivision is refused.

(4) All exhibits are returned, except for Exhibits 9, 10, 11, 12 and K, N and P.

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established