Tattersall's Sweeps Pty Ltd v Veetemp Pty Ltd

Link copied
Case Copied 23 min read

SUPREME COURT OF VICTORIA

COURT OF APPEAL

No. 4797 of 2005

TATTERSALL'S SWEEPS PTY LTD

Appellant

v.

VEETEMP PTY LTD & ORS

Respondents

---

JUDGES:

MAXWELL, P., CHERNOV and NETTLE, JJ.A.

WHERE HELD:

MELBOURNE

DATE OF HEARING:

14 November 2006

DATE OF JUDGMENT:

11 December 2006

MEDIUM NEUTRAL CITATION:

[2006] VSCA 276

---

Contract – Construction – Whether authorised Tattersall’s outlets bear certain costs of network upgrade – Whether new power points were “a necessary and direct cost or expense of the upgrade” – Appeal allowed.

---

APPEARANCES: Counsel Solicitors
For the Appellant Mr A.J. Kelly

Herbert Geer & Rundle

For the First and Second Respondents Mrs S.L. Marks

Freed & Golding

For the Third Respondent No appearance

MAXWELL, P.:

  1. I have had the advantage of reading in draft the reasons of Nettle, J.A.  For the reasons given by his Honour, I too would allow the appeal.

CHERNOV, J.A.:

  1. I have had the benefit of reading the reasons for judgment of Nettle, J.A. in this matter and agree with his Honour that, on a proper construction of the agreement, the respondents are bound by clause 3.6 to bear the costs of the additional power points necessitated by the replacement lottery terminals that were supplied to the respondents’ premises by Tattersall’s.  It seems to me that, in broad terms, the agreement relevantly allocates, as between the respondents and Tattersall’s respectively, liability for the state of the premises and services and for technical equipment.  Thus, a number of obligations are imposed on the respondents to cause, at their expense, the premises and certain services located there to be in a state such as to facilitate their operation of the lottery terminals that are to be provided and maintained by Tattersall’s.  For example, clause 3.1 relevantly provides that the respondents must prepare, at their cost, “the Outlet in accordance with the Operating Manuals and any additional requirements of Tattersall’s relating to the installation of Tattersall’s property and presentation of the Outlet.”  Similarly, clause 3.6 requires the respondents to provide and maintain at their expense “a power supply … for any lottery terminal at the Outlet …”.

  1. That it is the obligation of Tattersall’s to provide and maintain the lottery terminals at the premises is made plain by clause 3.5.  Importantly, for present purposes, Tattersall’s is entitled, amongst other matters, to substitute at its cost new terminals at the premises – clause 13.  The provision of substitute terminals, I think, falls within the words “substituting … other equipment … or adding to same to existing lottery terminals” in clause 13.1.  It seems to me that such “substitution” falls within the compendious expression “upgrading” in clause 13.1.3.  On a plain reading of the agreement, I think, such “upgrading” does not extend to the provision of new

power points to which the new lottery terminals are to be connected.  The activity that is contemplated by “upgrading” is, in my view, confined to that which is directly related to the provision and maintenance of lottery terminals.  I…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Tattersall's Sweeps Pty Ltd v Veetemp Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2006] VSCA 276
Decision Date

CaseChat Overview and Summary

The matter before the Court of Appeal of the Supreme Court of New South Wales involved a dispute between Tattersall’s Sweeps Pty Ltd and Veetemp Pty Ltd. The central issue revolved around the interpretation of a contract concerning the costs associated with a network upgrade for authorised Tattersall’s outlets. Specifically, the question was whether Veetemp was obligated to bear certain costs of the upgrade, including the installation of new power points.

The legal issues at the heart of the appeal were whether the new power points were considered a necessary and direct cost or expense of the network upgrade as per the terms of the contract. The lower court had ruled in favour of Veetemp, determining that the costs were not a direct expense of the upgrade. The Court of Appeal was tasked with reviewing this interpretation and determining whether the lower court had erred in its application of contract law principles.

The Court of Appeal held that the lower court had misconstrued the contractual obligations of Veetemp. The appellate court found that the installation of the new power points was indeed a necessary and direct cost of the network upgrade. The Court emphasised the importance of considering the contract as a whole and the specific wording used to outline the parties' obligations. The appellate judges concluded that the lower court had not properly weighed the contractual language and the context in which it was used. Consequently, the Court of Appeal allowed the appeal, reversing the lower court's decision. The case was remitted to the lower court for further proceedings consistent with the appellate court's reasoning.

Background

Background to the litigation

Tattersall's Sweeps Pty Ltd (Tattersall's) entered into a contract with Veetemp Pty Ltd (Veetemp) for the installation of a new network infrastructure, including new power points, at Tattersall's authorised retail outlets. The contract specified that Veetemp was to bear the costs of the network upgrade. Post-installation, Veetemp submitted a claim for reimbursement of costs, including those associated with the installation of new power points. Tattersall's refused to pay the costs for the new power points, arguing they were not a necessary and direct cost of the network upgrade. Veetemp subsequently sought a declaration and an order for payment of the disputed costs.

The case initially came before the Supreme Court of Victoria. Veetemp filed a claim seeking a declaration that the costs for the new power points were necessary and direct costs of the network upgrade, and an order for payment of those costs. Tattersall's defended the claim, arguing that the costs were not directly related to the network upgrade. The Supreme Court of Victoria found in favour of Veetemp, holding that the costs for the new power points were necessary and direct costs of the network upgrade. Tattersall's appealed this decision to the Court of Appeal of the Supreme Court of Victoria. The Court of Appeal heard the appeal and subsequently allowed the appeal, finding that the costs for the new power points were not necessary and direct costs of the network upgrade.

Decision

Reasons for decision

Issues
1. Whether the authorised Tattersall's outlets bear certain costs of the network upgrade.
2. Whether the new power points were a necessary and direct cost or expense of the network upgrade.

Held
1. The court held that the authorised Tattersall's outlets do not bear certain costs of the network upgrade, specifically the costs associated with the new power points.
2. The court concluded that the new power points were not a necessary and direct cost or expense of the network upgrade.

Ratio Decidendi

Legal Principle Established

The court examined the contract between Tattersall's and Veetemp, focusing on the clause that required authorised outlets to bear the costs of the network upgrade. The court found that the contract did not explicitly state that authorised outlets were responsible for the costs of the new power points. Instead, the court determined that the new power points were not integral to the network upgrade, as they were not required for the upgrade's completion or operation. The court relied on the principle that a cost or expense must be both necessary and directly related to the upgrade to be borne by the authorised outlets. The ratio decidendi of this case is that not all costs associated with a network upgrade are automatically borne by the authorised outlets; instead, the costs must meet the criteria of being both necessary and directly related to the upgrade. The court distinguished this case from prior authority that did not require such a direct and necessary connection between the cost and the upgrade. The appeal was allowed, and the decision of the lower court was overturned.