[2012] TASSC 18
COURT: SUPREME COURT OF TASMANIA
CITATION: Tasmanian Conservation Trust Inc v Gunns Ltd [2012] TASSC 18
PARTIES: TASMANIAN CONSERVATION TRUST INC
v
GUNNS LTD
FILE NO/S: 953/2011
DELIVERED ON: 20 April 2012
DELIVERED AT: Hobart
HEARING DATE: 26, 29 and 30 March 2012
JUDGMENT OF: Holt AsJ
CATCHWORDS:
Procedure – Costs – Security for costs – Poverty – Lack of means – Incorporated Association – Exercise of discretion.
Aust Dig Procedure [668]
REPRESENTATION:
Counsel:
Plaintiff: D Kerr SC and A Browning
Defendant: D J Gunson SC
Solicitors:
Plaintiff: FitzGerald and Browne
Defendant: Shaun McElwaine
Judgment Number: [2012] TASSC 18
Number of paragraphs: 50
Serial No 18/2012
File No 953/2011
TASMANIAN CONSERVATION TRUST INC v GUNNS LIMITED
REASONS FOR JUDGMENT HOLT AsJ
20 April 2012
The application
The defendant has applied for an order requiring the plaintiff to give security for its costs, with the action to be stayed subject to the provision of such security.
Background
Pursuant to the Pulp Mill Assessment Act 2007 ("the Act"), a permit called the "Pulp Mill Permit" came into effect by resolution of each House of Parliament authorising the defendant to develop and operate a bleached kraft pulp mill in northern Tasmania.
The Pulp Mill Permit came into effect on 30 August 2007.
By virtue of the combined effect of ss8 and 9(1), reproduced below, the Pulp Mill Permit comprises each and every permit, licence or other approval which, but for the Act, would have been required under other legislation as specified in the Pulp Mill Permit. The other specified legislation includes the Land Use Planning and Approvals Act 1993, and the Water Management Act 1999.
The Act, ss7(1)(b), 8 and 9(1), are as follows:
"7 Approval of project
(1) The project is approved if –
…
(b) each House of Parliament, by resolution, accepts the Pulp Mill Permit.
…
8 Effect of approval
(1) If the project is approved under section 7 –
(a) the Pulp Mill Permit comes into effect; and
(b) notwithstanding any other Act, the project may proceed on the conditions specified in the Pulp Mill Permit; and
(c) a permit, licence or other approval is taken to have been issued under the Act specified in the Pulp Mill Permit in relation to each condition and that Act applies as if such a permit, licence or other approval had been issued on the conditions set out in the Pulp Mill Permit in relation to that Act; and
(d) the person, body or State Service Agency responsible for the enforcement of each condition must enforce the condition to the extent of its powers.
(2) If the conditions require the person proposing the project to apply for such other permits, licences or other approvals as may be necessary for the project, the person proposing the project must comply with that requirement.
(3) If the person proposing the project does not comply with a condition contained in the Pulp Mill Permit, the Pulp Mill Permit is suspended until…
Keep reading for free
Create a free CaseChat account to read Tasmanian Conservation Trust Inc v Gunns Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] TASSC 18
- Decision Date
CaseChat Overview and Summary
The central legal issues addressed by the court were whether the applicant's status as an incorporated association with limited financial resources constituted sufficient grounds for exemption from the requirement to provide security for costs and whether the court should exercise its discretion to grant such an exemption. The court considered the principles governing the imposition of security for costs, including the importance of ensuring that legal proceedings do not become a weapon for financially stronger parties against those with limited means, and the need to balance this with the respondent's right to protect its interests.
The court determined that the applicant's financial situation warranted a departure from the usual requirement for security for costs. It recognised the applicant's status as an incorporated association with limited resources and the potential chilling effect on the association's ability to participate in legal proceedings without such an exemption. The court exercised its discretion in favour of the applicant, granting the exemption from providing security for costs. This decision was based on the balance between the applicant's right to access justice and the respondent's interest in protecting its position.
The court ordered that Gunns Ltd was not to be required to provide security for costs in the proceedings, reflecting the court's consideration of the applicant's financial constraints and the need to facilitate access to justice for parties with limited means.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.