Tarbuck and Anor v Robertson and Anor (Civil Dispute)

Link copied
Case Copied 36 min read

ACT CIVIL & ADMINISTRATIVE TRIBUNAL



TARBUCK & ANOR v ROBERTSON & ANOR (Civil Dispute) [2018] ACAT 115

XD 122/2018

Catchwords:              CIVIL DISPUTE – renovation works – application for balance owing on contract – counter-claim for cost of rectifying defective work – building work not in compliance with building standards – building work not conducted in a proper and skilful way

Legislation cited:      ACT Civil and Administrative Tribunal Act 2008 s 48

Building Act 2004 s 88

Fair Trading (Australian Consumer Law) Act1992 s 260, 267

Cases cited:Saltalmacchia v Tayser Automotive Group Pty Ltd trading as Naunawading Great Wall [2014] VCAT 1463

Boyd v Agrison [2014] VMC 23

Tribunal:Senior Member E Ferguson

Senior Member G Trickett

Date of Orders:  15 November 2018

Date of Reasons for Decision:         15 November 2018

AUSTRALIAN CAPITAL TERRITORY  )

CIVIL & ADMINISTRATIVE TRIBUNAL       )          XD 122/2018

BETWEEN:

MICHAEL TARBUCK AND DENNIS TARBUCK

Applicants

AND:

DON ROBERTSON AND NOELENE ROBERTSON

Respondents

TRIBUNAL:Senior Member E Ferguson

Senior Member G Trickett

DATE:15 November 2018

ORDER

The Tribunal orders that:

  1. Judgment for the applicants on the claim in the sum of $3,775.

  2. Judgment for the respondents on their counter claim in the sum of $25,150 comprised of:

    (a)Damages assessed at $25,000 being the jurisdictional limit of the tribunal’s jurisdiction; and

    (b)$150 being the filing fee.

  3. The amount payable by the respondents at order 1 shall be credited against the amount payable by the applicants at Order 2.

  4. The applicants shall pay to the respondents within 28 days the sum of $21,375 being the difference between the amounts payable at Orders 1 and 2.

………………………………..

Senior Member E Ferguson

Delivered for and on behalf of the Tribunal

REASONS FOR DECISION

Introduction

  1. In this decision a reference to the ‘tribunal’ or ‘ACAT’ refers to the ACT Civil and Administrative Tribunal generally and a reference to the ‘Tribunal’ refers to the presently constituted Tribunal.

  2. The applicants, Michael and his father Dennis Tarbuck, undertook renovations (the works) to the respondents’ home in the ACT (the property). The works consisted of renovations to the kitchen and laundry and the construction of a deck. Separate quotes were issued and accepted for each aspect of the works.

  3. The respondents paid the applicants a total of $85,475 for the works.[1] The applicant claims $12,425 for the balance owing for the works.

    [1] The parties agreed at the hearing that the respondents had paid the applicants $85,475.00; Transcript of proceedings, 2 August 2018, page 21

  4. The respondents dispute the agreed price of the works and liability for work not completed by the applicants.

  5. The respondents counter claim for damages for the cost of rectifying defective work and completing incomplete work. They rely on grounds of negligence as well as breach of statutory warranties and guarantees.

  6. The respondents say they suffered loss in excess of $50,000 but limit their counter-claim to $25,000 being the jurisdictional limit of the tribunal.

The hearing

  1. The Tribunal heard this matter on 2 August 2018. All…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Tarbuck and Anor v Robertson and Anor (Civil Dispute) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2018] ACAT 115
Decision Date

CaseChat Overview and Summary

The applicants, Tarbuck and Anor, brought an application against the respondents, Robertson and Anor, seeking the balance owing on a contract for renovation works. The respondents counter-claimed for the cost of rectifying defective work, alleging that the building work was not in compliance with building standards and was not conducted in a proper and skilful way. The matter was heard and determined by the Civil and Administrative Tribunal of New South Wales.

The legal issues before the Tribunal were whether the applicants were entitled to the balance owing on the contract and whether the respondents were entitled to damages for defective work. The applicants argued that they had completed the work in accordance with the contract and that the respondents had not provided a certificate of completion. The respondents argued that the work was defective and not in compliance with building standards and that they were entitled to damages for the cost of rectifying the defects.

The Tribunal found that the applicants had completed the work in accordance with the contract but that the work was not in compliance with building standards and was not conducted in a proper and skilful way. The Tribunal assessed the damages for the cost of rectifying the defects at $25,000, being the jurisdictional limit of the Tribunal’s jurisdiction. The Tribunal also ordered that the applicants pay the respondents the difference between the amounts payable on the claim and the counter-claim, being $21,375.

The Tribunal ordered that judgment be entered for the applicants on the claim in the sum of $3,775 and for the respondents on their counter-claim in the sum of $25,150, being the damages assessed plus the filing fee. The Tribunal further ordered that the amount payable by the respondents at Order 1 shall be credited against the amount payable by the applicants at Order 2, and that the applicants shall pay to the respondents within 28 days the sum of $21,375 being the difference between the amounts payable at Orders 1 and 2.

Orders

Orders of the court

The Tribunal orders that:

1.

Judgment for the applicants on the claim in the sum of $3,775.

2.

Judgment for the respondents on their counter claim in the sum of $25,150 comprised of:

(a) Damages assessed at $25,000 being the jurisdictional limit of the tribunal’s jurisdiction; and

(b) $150 being the filing fee.

3.

The amount payable by the respondents at order 1 shall be credited against the amount payable by the applicants at Order 2.

4.

The applicants shall pay to the respondents within 28 days the sum of $21,375 being the difference between the amounts payable at Orders 1 and 2.

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established