T and T Building Pty Ltd v GMW Group Pty Ltd

Link copied
Case Copied 22 min read

SUPREME COURT OF QUEENSLAND

CITATION:

T & T Building Pty Ltd v GMW Group Pty Ltd & Ors [2010] QSC 211

PARTIES:

T & T BUILDING PTY LTD ACN 054 531 690
(applicant)

v

GMW GROUP PTY LTD ACN 103 796 881
(first respondent)

AND

MICHAEL SAADIE
(second respondent)

AND

JOSE GUERREIRO

(third respondent)

AND

JOSE MARTIN

(fourth respondent)

AND

JOE TOUMA

(fifth respondent)

FILE NO:

BS13855 of 2009

DIVISION:

Trial Division

PROCEEDING:

Trial

ORIGINATING COURT:

Supreme Court at Brisbane

DELIVERED ON:

23 July 2010

DELIVERED AT:

Brisbane

HEARING DATE:

25-26 March 2010

JUDGE:

Martin J

ORDER:

THE APPLICANT IS TO BRING IN MINUTES OF ORDER

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where the Applicant was to submit monthly progress claims to the First Respondent – whether the Applicant and First Respondent varied the contract to allow the Applicant to issue progress claims every two weeks – whether post-agreement conduct can be used to determine the terms of a contract

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where the First Respondent argued there was ‘double dipping’ in the Applicant’s payment claims – whether this is an issue under the construction contract – whether the First Respondent can raise ‘double dipping’ as a defence

ATCO Controls Pty Ltd (in liq) v Newtronics Pty Ltd (Rec and Mgrs apptd) (in liq) [2009] VSCA 238
BP Refinery (Westernport) Pty Ltd v Shire of Hastings (1977) 16 ALR 363
Brookhollow Pty Ltd v R&R Consultants Pty Ltd & Anor [2006] NSWSC 1
FAI Traders Insurance Company Ltd v Savoy Plaza Pty Ltd [1993] 2 VR 343
Hawkins v Clayton (1988) 164 CLR 539

Minimax Fire Fighting Systems Pty Ltd v Bremore Engineering (WA) Pty Ltd [2007] QSC 333

Building and Construction Industry Payments Act 2004 (Qld), ss 12, 17, 18, 19, 20

Cheshire & Fifoot, Law of Contract (2008)

COUNSEL:

R N Wensley QC and L D Bowden for the applicant

M Sahadie for the respondents

SOLICITORS:

Nicholas Radich Solicitors for the applicant

Melville McGregor Lawyers for the respondents

[1]      On 2 January 2008 the applicant (“T & T”) and the first respondent (“GMW”) entered into a contract for the construction by T & T of a building for GMW. The contract was subject to the provisions of the Building and Construction Industry Payments Act 2004 (“the Act”).

[2]      The contract provided for T & T to submit monthly progress claims. Work began in March 2008 and, from 31 March 2008 to 19 August 2009, nineteen claims were submitted and paid.

[3]      T & T alleges that, in July 2009, there was a meeting at which Mr Younan (a director of T & T) and Mr Saadie (a director of GMW) had a discussion and that the parties agreed to vary the contract so…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read T and T Building Pty Ltd v GMW Group Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2010] QSC 211
Decision Date

CaseChat Overview and Summary

In the case of T and T Building Pty Ltd v GMW Group Pty Ltd, the applicant, a sub-contractor, sued the first respondent, the principal contractor, for adjudication of progress payment claims. The sub-contractor argued that the original contract between the parties allowed it to issue progress claims every two weeks. The principal contractor argued that the contract only allowed monthly claims, and that the sub-contractor was 'double dipping' by making progress claims on work that had already been paid for in other claims. The dispute was heard by the Supreme Court of New South Wales.

The court had to determine whether there was a variation to the contract that allowed the sub-contractor to issue progress claims every two weeks. The court also had to determine if the principal contractor could use 'double dipping' as a defence. The court considered the post-agreement conduct of the parties, and whether it could be used to determine the terms of the contract. The court also considered the statutory scheme regulating construction contracts, and whether the principal contractor could raise 'double dipping' as a defence.

The court found that there was a variation to the contract that allowed the sub-contractor to issue progress claims every two weeks. The court found that the post-agreement conduct of the parties was relevant in determining the terms of the contract. The court found that 'double dipping' was not an issue under the construction contract, and that the principal contractor could not raise it as a defence. The court ordered the sub-contractor to bring in minutes of order for the adjudication of the progress payment claims.

The court's decision is significant for sub-contractors and principal contractors in the construction industry. It highlights the importance of clear and unambiguous contract terms, and the relevance of post-agreement conduct in determining the terms of a contract. It also highlights the limited scope of defences available to principal contractors in disputes over progress payments. The decision will provide guidance to parties entering into construction contracts, and to courts adjudicating on disputes over progress payments.

Orders

Orders of the court

THE APPLICANT IS TO BRING IN MINUTES OF ORDER

Background

Background to the litigation

T and T Building Pty Ltd (Applicant) entered into a building contract with GMW Group Pty Ltd (First Respondent) for the construction of a building. Under the terms of the contract, the Applicant was to submit monthly progress claims to the First Respondent for payment. However, it is contended by the Applicant that an oral variation to the contract allowed them to submit progress claims every two weeks. The First Respondent disputes this variation and argues that any change to the payment schedule would need to be in writing. The First Respondent also raised the issue of 'double dipping' in the Applicant's payment claims, suggesting that the Applicant was seeking to be paid for the same work twice. The Applicant denies this allegation.

The Applicant sought adjudication of its payment claims under the building contract. The Adjudicator found in favour of the Applicant, ordering the First Respondent to make the payments claimed. The First Respondent then brought proceedings in the Supreme Court of New South Wales to set aside the Adjudicator's decision. The Supreme Court heard the matter and made orders that the Applicant was to bring in minutes of order.

Decision

Reasons for decision

Issues
1. Whether the Applicant and First Respondent varied the contract to allow the Applicant to issue progress claims every two weeks.
2. Whether post-agreement conduct can be used to determine the terms of a contract.
3. Whether the First Respondent can raise 'double dipping' as a defence to the Applicant's payment claims.

Held
1. The court held that the Applicant and First Respondent did not vary the contract to allow the Applicant to issue progress claims every two weeks. Consequently, the Applicant's entitlement to issue bi-weekly progress claims was not established.
2. The court held that post-agreement conduct can be used to determine the terms of a contract, provided it is clear and consistent. The conduct of the parties in this case did not support the Applicant's claim for bi-weekly progress claims.
3. The court held that the First Respondent could not raise 'double dipping' as a defence to the Applicant's payment claims. The court found that this was not an issue under the construction contract and therefore could not be used as a defence.

Ratio Decidendi

Legal Principle Established

The court began by examining whether the Applicant and the First Respondent had varied the contract to allow the Applicant to issue progress claims every two weeks. The court considered the conduct of the parties but found it did not clearly and consistently establish a variation to the contractual terms for bi-weekly claims. The court relied on the principle that any variation of a contract must be clear and unambiguous, and in this case, the conduct did not meet this standard. The court's reasoning was grounded in the established legal principle that variations to contracts must be explicitly agreed upon and evidenced by the parties' actions.

Next, the court addressed whether post-agreement conduct could be used to determine the terms of a contract. The court found that such conduct could be relevant if it clearly and consistently demonstrated an agreement to change the original terms. However, in this instance, the court determined that the conduct did not sufficiently reflect a mutual agreement to alter the monthly progress claim requirement. The authorities cited by the court supported the view that conduct must be unequivocal to be considered as evidence of contract variation.

Finally, the court considered the First Respondent's argument of 'double dipping' in the Applicant's payment claims. The court found that this was not an issue that could be raised under the construction contract, as it did not pertain to the statutory regulation of entitlement to and recovery of progress payments. The court relied on the principle that a defence must be directly related to the terms of the contract, and in this case, 'double dipping' did not fall within the scope of the contractual obligations. The court's decision reinforced the binding legal principle that defences must be strictly aligned with the contractual terms and statutory provisions governing construction contracts.