SUPREME COURT OF QUEENSLAND
CITATION:
T & T Building Pty Ltd v GMW Group Pty Ltd & Ors [2010] QSC 211
PARTIES:
T & T BUILDING PTY LTD ACN 054 531 690
(applicant)v
GMW GROUP PTY LTD ACN 103 796 881
(first respondent)AND
MICHAEL SAADIE
(second respondent)AND
JOSE GUERREIRO
(third respondent)
AND
JOSE MARTIN
(fourth respondent)
AND
JOE TOUMA
(fifth respondent)
FILE NO:
BS13855 of 2009
DIVISION:
Trial Division
PROCEEDING:
Trial
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
23 July 2010
DELIVERED AT:
Brisbane
HEARING DATE:
25-26 March 2010
JUDGE:
Martin J
ORDER:
THE APPLICANT IS TO BRING IN MINUTES OF ORDER
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where the Applicant was to submit monthly progress claims to the First Respondent – whether the Applicant and First Respondent varied the contract to allow the Applicant to issue progress claims every two weeks – whether post-agreement conduct can be used to determine the terms of a contract
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where the First Respondent argued there was ‘double dipping’ in the Applicant’s payment claims – whether this is an issue under the construction contract – whether the First Respondent can raise ‘double dipping’ as a defence
ATCO Controls Pty Ltd (in liq) v Newtronics Pty Ltd (Rec and Mgrs apptd) (in liq) [2009] VSCA 238
BP Refinery (Westernport) Pty Ltd v Shire of Hastings (1977) 16 ALR 363
Brookhollow Pty Ltd v R&R Consultants Pty Ltd & Anor [2006] NSWSC 1
FAI Traders Insurance Company Ltd v Savoy Plaza Pty Ltd [1993] 2 VR 343
Hawkins v Clayton (1988) 164 CLR 539Minimax Fire Fighting Systems Pty Ltd v Bremore Engineering (WA) Pty Ltd [2007] QSC 333
Building and Construction Industry Payments Act 2004 (Qld), ss 12, 17, 18, 19, 20
Cheshire & Fifoot, Law of Contract (2008)
COUNSEL:
R N Wensley QC and L D Bowden for the applicant
M Sahadie for the respondents
SOLICITORS:
Nicholas Radich Solicitors for the applicant
Melville McGregor Lawyers for the respondents
[1] On 2 January 2008 the applicant (“T & T”) and the first respondent (“GMW”) entered into a contract for the construction by T & T of a building for GMW. The contract was subject to the provisions of the Building and Construction Industry Payments Act 2004 (“the Act”).
[2] The contract provided for T & T to submit monthly progress claims. Work began in March 2008 and, from 31 March 2008 to 19 August 2009, nineteen claims were submitted and paid.
[3] T & T alleges that, in July 2009, there was a meeting at which Mr Younan (a director of T & T) and Mr Saadie (a director of GMW) had a discussion and that the parties agreed to vary the contract so…
Keep reading for free
Create a free CaseChat account to read T and T Building Pty Ltd v GMW Group Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] QSC 211
- Decision Date
CaseChat Overview and Summary
The court had to determine whether there was a variation to the contract that allowed the sub-contractor to issue progress claims every two weeks. The court also had to determine if the principal contractor could use 'double dipping' as a defence. The court considered the post-agreement conduct of the parties, and whether it could be used to determine the terms of the contract. The court also considered the statutory scheme regulating construction contracts, and whether the principal contractor could raise 'double dipping' as a defence.
The court found that there was a variation to the contract that allowed the sub-contractor to issue progress claims every two weeks. The court found that the post-agreement conduct of the parties was relevant in determining the terms of the contract. The court found that 'double dipping' was not an issue under the construction contract, and that the principal contractor could not raise it as a defence. The court ordered the sub-contractor to bring in minutes of order for the adjudication of the progress payment claims.
The court's decision is significant for sub-contractors and principal contractors in the construction industry. It highlights the importance of clear and unambiguous contract terms, and the relevance of post-agreement conduct in determining the terms of a contract. It also highlights the limited scope of defences available to principal contractors in disputes over progress payments. The decision will provide guidance to parties entering into construction contracts, and to courts adjudicating on disputes over progress payments.
Orders
Orders of the court
THE APPLICANT IS TO BRING IN MINUTES OF ORDER
Background
Background to the litigation
The Applicant sought adjudication of its payment claims under the building contract. The Adjudicator found in favour of the Applicant, ordering the First Respondent to make the payments claimed. The First Respondent then brought proceedings in the Supreme Court of New South Wales to set aside the Adjudicator's decision. The Supreme Court heard the matter and made orders that the Applicant was to bring in minutes of order.
Decision
Reasons for decision
1. Whether the Applicant and First Respondent varied the contract to allow the Applicant to issue progress claims every two weeks.
2. Whether post-agreement conduct can be used to determine the terms of a contract.
3. Whether the First Respondent can raise 'double dipping' as a defence to the Applicant's payment claims.
Held
1. The court held that the Applicant and First Respondent did not vary the contract to allow the Applicant to issue progress claims every two weeks. Consequently, the Applicant's entitlement to issue bi-weekly progress claims was not established.
2. The court held that post-agreement conduct can be used to determine the terms of a contract, provided it is clear and consistent. The conduct of the parties in this case did not support the Applicant's claim for bi-weekly progress claims.
3. The court held that the First Respondent could not raise 'double dipping' as a defence to the Applicant's payment claims. The court found that this was not an issue under the construction contract and therefore could not be used as a defence.
Ratio Decidendi
Legal Principle Established
The court began by examining whether the Applicant and the First Respondent had varied the contract to allow the Applicant to issue progress claims every two weeks. The court considered the conduct of the parties but found it did not clearly and consistently establish a variation to the contractual terms for bi-weekly claims. The court relied on the principle that any variation of a contract must be clear and unambiguous, and in this case, the conduct did not meet this standard. The court's reasoning was grounded in the established legal principle that variations to contracts must be explicitly agreed upon and evidenced by the parties' actions.
Next, the court addressed whether post-agreement conduct could be used to determine the terms of a contract. The court found that such conduct could be relevant if it clearly and consistently demonstrated an agreement to change the original terms. However, in this instance, the court determined that the conduct did not sufficiently reflect a mutual agreement to alter the monthly progress claim requirement. The authorities cited by the court supported the view that conduct must be unequivocal to be considered as evidence of contract variation.
Finally, the court considered the First Respondent's argument of 'double dipping' in the Applicant's payment claims. The court found that this was not an issue that could be raised under the construction contract, as it did not pertain to the statutory regulation of entitlement to and recovery of progress payments. The court relied on the principle that a defence must be directly related to the terms of the contract, and in this case, 'double dipping' did not fall within the scope of the contractual obligations. The court's decision reinforced the binding legal principle that defences must be strictly aligned with the contractual terms and statutory provisions governing construction contracts.