Sweeney v Coffey Pty Ltd

Case [1999] NSWCA 38


CITATION: SWEENEY & ANOR v COFFEY PTY LTD & ORS [1999] NSWCA 38
FILE NUMBER(S): CA 40750/96
HEARING DATE(S): 16 February 1999
JUDGMENT DATE:
16 February 1999

PARTIES :


GERALDINE SWEENEY & ANOR
R & D COFFEY PTY LIMITED & ORS
JUDGMENT OF: Mason P; Powell JA; Fitzgerald AJA
LOWER COURT JURISDICTION: Supreme Court - Common Law Division
LOWER COURT FILE NUMBER(S) : CL 16433/91
LOWER COURT JUDICIAL OFFICER: Hidden J
COUNSEL: A J Meagher SC/P J Dowdy (Appellant)
P R Callaghan SC/D M Lowenstein (1st Respondent)
F C Corsaro (2nd Respondent)
G M Watson (3rd Respondent)
SOLICITORS: James A Moustacas & Co (Appellant)
Hickson Wisewolds (1st Respondent)
Tress Cocks & Maddox (2nd Respondent)
Colin Biggers & Paisley (3rd Respondent)
CATCHWORDS: Contracts ; torts; negligence ; breach of duty to take reasonable care; Supreme Court Rules Part 72; referee’s report; damages for loss of use of house
DECISION: Appeal dismissed

THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF APPEAL
CA 40750/96
CL 16433/91


MASON P
POWELL JA
FITZGERALD AJA

16 February 1999

GERALDINE SWEENEY & ANOR v
R & D COFFEY PTY LIMITED & ORS

JUDGMENT


1 MASON P: A substantial house in Wentworth Avenue, Point Piper was under repair in late 1987. It was the home of the appellants and their children, the owner being the first appellant Mrs Sweeney.
2 The first respondent (“the contractor”) had contracted with Mrs Sweeney to perform repairs to the flat roof. The contractor was a specialist roofing contractor that had been retained on the recommendation of Mr Heyko-Porebski (“the architect”) who is the first of the second respondents.
3 In the week of 26 October 1987 the contractor’s employees commenced work. They removed the weatherproof membrane thereby exposing the totality of the roof surface. This disclosed that the topping to the slab was not structural. There was lightweight coke-like cement. The contractor submitted an amended quotation for the removal of the lightweight concrete topping as a preliminary to a different type of repair work than had originally been contemplated.
4 On 30 October a hole of 3-4 inches diameter was cut in the roof for the purpose of confirming its nature and structure. It was ascertained that the roof did not consist of a solid concrete slab with a lightweight concrete skin as had been believed, but was in fact composed of terra- cotta blocks and concrete forming a lightweight slab. Permission to cut the hole had been conveyed to the architect from Mr Sweeney. Having determined the state of the roof, the architect directed the contractor to cease work, to plug the hole and to have the area covered with tarpaulins. It would be up to the engineer in the first instance to determine what should be done next.
5 A strike of concrete workers had commenced on 28 October. Although expected to last for only one or two days, it continued much longer. On 10 and 11 November torrential rain caused extensive damage to the premises and their contents.…

Continue reading Sweeney v Coffey Pty Ltd

Sign in free to access the full text

Details
AGLC
Sweeney v Coffey Pty Ltd [1999] NSWCA 38
Case
[1999] NSWCA 38
Decision Date

CaseChat Overview and Summary

Sweeney (the plaintiff) brought proceedings against Coffey Pty Ltd (the defendant) in the Supreme Court of New South Wales, alleging negligence and breach of contract. The dispute concerned damage to the plaintiff's house, which the plaintiff claimed resulted from the defendant's actions. The matter proceeded to a referee's report, and the plaintiff sought damages for loss of use of the house.

The primary legal issues before the Court of Appeal were whether the referee's report was flawed, and consequently, whether the primary judge erred in adopting the referee's findings and awarding damages to the plaintiff. Specifically, the court had to consider the adequacy of the referee's assessment of the plaintiff's loss, particularly in relation to the claim for loss of use of the house.

The Court of Appeal, comprising Mason P, Powell JA, and Fitzgerald AJA, reviewed the referee's report and the primary judge's decision. The court found no error in the referee's approach to assessing the damages, including the award for loss of use. The principles applied centred on the court's power to adopt a referee's report under the Supreme Court Rules and the standard of review for such reports. The court determined that the referee had properly considered the evidence and applied the correct legal principles in reaching their conclusions.

The appeal was accordingly dismissed.

Orders

Orders of the court

Appeal dismissed

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.