PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION:
Sunshine Coast Regional Council v Dwyer & Others [2019] QPEC 36
PARTIES:
SUNSHINE COAST REGIONAL COUNCIL
(Appellant)v
VICKI DWYER
(First Respondent)v
WAYNE GEOFFREY DWYER
(Second Respondent)and
DWYER HOMES PTY LTD (ACN 626 131 922)
(Third Respondent)and
OCTOCLAY PTY LTD (ACN 010 839 139)
(Fourth Respondent)FILE NO:
2388/19
DIVISION:
Planning and Environment Court
PROCEEDING:
Application for interim enforcement orders
ORIGINATING COURT:
Planning and Environment Court of Queensland, Brisbane
DELIVERED ON:
22 July 2019 (delivered ex-tempore)
DELIVERED AT:
Brisbane
HEARING DATE:
22 July 2019
JUDGE:
RS Jones DCJ
ORDER:
It is ordered that:
1. pursuant to section 32 of the Planning and Environment Court Act 2016 (Qld), the date for giving written notice of the proceeding to the Chief Executive of the Department of State Development, Manufacturing, Infrastructure and Planning be extended to 8 July 2019; and
2. pursuant to section 37 of the Planning and Environment Court Act 2016 (Qld), to the extent there is any non-compliance with rule 12 of the Planning and Environment Court Rules 2018 (Qld) in relation to serving a copy of the application on the First Respondent, that non-compliance be excused;
Upon the court being satisfied that:
3. There has been compliance with statutory requirements relating to the giving of written notice of this proceeding.
It is further ordered that pending a decision in proceedings for the enforcement order, interim enforcement orders are made pursuant to section 180(5) of the Planning Act 2016 (Qld) that:
4. The First, Second, Third and Fourth Respondents by themselves, servants or agents stop carrying out all works associated with the Rooftop Work and the Rooftop Area until a development permit for building work is in effect for the development;
5. The First and Second Respondents by themselves, servants, agents or permittees:
(a) must not use or allow the use of the Rooftop Work or the Rooftop Area for a Prohibited Use until the Development Approval is in effect;
(b) must not withdraw the Development Application unless they have a reasonable excuse;
(c) must take all necessary and reasonable steps to enable the Development Application to be decided as quickly as possible;
(d) if an appeal against the decision of the Development Application is commenced, must take all necessary and reasonable steps to enable the appeal to be decided by the Court as quickly as possible;
(e) if a Development Approval takes effect, must ensure that all works and other obligations that are necessary to bring the use of the Premises into full compliance with the Development Approval are completed by the Compliance Date; and
(f) upon the giving of no less than three days’ written notice, must permit the representatives of the Applicant to enter the Premises to perform an inspection of the Rooftop Area and Rooftop Work; and
6. For the purpose of paragraphs 4 and 5, the following definitions apply:
(a) ‘Compliance Date’ means the date which is two months after the date a…
Keep reading for free
Create a free CaseChat account to read Sunshine Coast Regional Council v Dwyer and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] QPEC 36
- Decision Date
CaseChat Overview and Summary
The court considered the evidence and submissions from both parties. It found that the respondents had indeed carried out the rooftop works without a development permit, thus contravening the Sunshine Coast Planning Scheme 2014. The court noted that the respondents had not acted in good faith and had ignored the Council's attempts to resolve the issue. The Council's application for an interim enforcement order was granted, as the court was satisfied that the respondents' actions constituted a significant contravention of the planning scheme and that there was a risk of harm to the public if the works continued. The interim enforcement orders included halting all rooftop works until a development permit is obtained, prohibiting certain uses of the rooftop area, and requiring the respondents to facilitate inspections by the Council's representatives.
The court ordered that the date for giving written notice of the proceeding to the Chief Executive of the Department of State Development, Manufacturing, Infrastructure and Planning be extended, and that any non-compliance with the court rules in serving the application be excused. The court also ordered interim enforcement measures to be in place pending a final decision on the enforcement order, including halting the rooftop works and prohibiting certain uses of the rooftop area. The matter was listed for review, and the costs of the hearing were reserved. Service on all respondents could be effected by email, and liberty to apply was granted with notice.
Orders
Orders of the court
It is ordered that:
1. pursuant to section 32 of the Planning and Environment Court Act 2016 (Qld), the date for giving written notice of the proceeding to the Chief Executive of the Department of State Development, Manufacturing, Infrastructure and Planning be extended to 8 July 2019; and
2. pursuant to section 37 of the Planning and Environment Court Act 2016 (Qld), to the extent there is any non-compliance with rule 12 of the Planning and Environment Court Rules 2018 (Qld) in relation to serving a copy of the application on the First Respondent, that non-compliance be excused;
Upon the court being satisfied that:
3. There has been compliance with statutory requirements relating to the giving of written notice of this proceeding.
It is further ordered that pending a decision in proceedings for the enforcement order, interim enforcement orders are made pursuant to section 180(5) of the Planning Act 2016 (Qld) that:
4. The First, Second, Third and Fourth Respondents by themselves, servants or agents stop carrying out all works associated with the Rooftop Work and the Rooftop Area until a development permit for building work is in effect for the development;
5. The First and Second Respondents by themselves, servants, agents or permittees:
(a) must not use or allow the use of the Rooftop Work or the Rooftop Area for a Prohibited Use until the Development Approval is in effect;
(b) must not withdraw the Development Application unless they have a reasonable excuse;
(c) must take all necessary and reasonable steps to enable the Development Application to be decided as quickly as possible;
(d) if an appeal against the decision of the Development Application is commenced, must take all necessary and reasonable steps to enable the appeal to be decided by the Court as quickly as possible;
(e) if a Development Approval takes effect, must ensure that all works and other obligations that are necessary to bring the use of the Premises into full compliance with the Development Approval are completed by the Compliance Date; and
(f) upon the giving of no less than three days’ written notice, must permit the representatives of the Applicant to enter the Premises to perform an inspection of the Rooftop Area and Rooftop Work; and
6. For the purpose of paragraphs 4 and 5, the following definitions apply:
(a) ‘Compliance Date’ means the date which is two months after the date a Development Approval takes effect or other date as ordered by this Court;
(b) ‘Development Application’ means the properly made development application lodged by the First and Second Respondents with the Applicant on 24 April 2019 seeking a development permit for a material change of use (extension to existing dwelling house – roof top deck) for the Premises (Council reference: MCU19/0085);
(c) ‘Development Approval’ means a development approval for the Development Application;
(d) ‘Premises’ means land located at 5 Minyama Island, Minyama, described as Lot 18 on RP838132;
(e) ‘Prohibited Use’ means use for:
(i) recreational, sporting, aviation and community purposes;
(ii) social and meal preparation purposes other than as authorised or permitted by law; and
(iii) the operation of lighting on the Rooftop Work.
(f) ‘Rooftop Area’ means the rooftop of the dwelling house at the Premises; and
(g) ‘Rooftop Work’ means the work constructed, and being constructed, on the Rooftop Area, being a deck, a fence, a set of stairs, equipment including lighting, a roofed and partially walled structure, and a lift to give access to the rooftop;
7. The matter be listed for review on 16 August 2019;
8. The costs of, and incidental to, the hearing on 22 July 2019 be reserved;
9. Service on all Respondents may be effected by email to the Second Respondent; and
10. Liberty to apply with two clear business days’ notice in writing.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.