Land and Environment Court
New South Wales
Medium Neutral Citation: Sunland No. 35 Pty Ltd v Camden Council [2019] NSWLEC 1391 Hearing dates: 17-19 June 2019; Conditions filed 1 July 2019 Date of orders: 21 August 2019 Decision date: 21 August 2019 Jurisdiction: Class 1 Before: Smithson C Decision: The orders of the Court are:
(1) Leave is granted to amended engineering and landscaping plans as comprising part of the application as amended.
(2) The appeal is upheld.
(3) Development Application DA 2017/1193/1 for a multi-dwelling housing and community title subdivision at 1-5 Main Street, Mount Annan is approved subject to the conditions in Annexure ‘A’.
(4) The exhibits are returned with the exception of Exhibits 1, A, C, G, T and U.Catchwords: DEVELOPMENT APPLICATION – multi-dwelling housing in a community title subdivision – solar access to private open space – urban design considerations including street activation and clustering – adequacy of road design and access including acceptable road widths and speed mitigation measures – provision for public access through the site – community objections Legislation Cited: Camden Local Environmental Plan 2010
Environmental Planning and Assessment Act 1979Cases Cited: Landco (NSW) Pty Ltd v Camden Council [2017] NSWLEC 1694
Mount Annan 88 Pty Ltd v Camden Council [2016] NSWLEC 1072
Trinvass Pty Ltd v Council of the City of Sydney [2015] NSWLEC 151Texts Cited: AMCORD 1995
Apartment Design Guide
Australian Standard AS1428.1
Austroads Guide to Traffic Management 2016
Camden Development Control Plan 2011
Low Rise Medium Density Design Guide for Development Applications 2018
Medium Density Design Guide (Draft) 2017Category: Principal judgment Parties: Sunland No. 35 Pty Ltd (Applicant)
Camden Council (Respondent)Representation: Counsel:
Solicitors:
A Galasso SC (Applicant)
A Pearman (Respondent)
Hall & Wilcox Lawyers (Applicant)
Bartier Perry (Respondent)
File Number(s): 2018/139569 Publication restriction: No
Judgment
-
COMMISSIONER: This is an appeal lodged under s 8.7(1) of the Environmental Planning and Assessment Act 1979 (the EPA Act) against the deemed refusal of Development Application DA 2017/1193/1 (the application) for a multi-dwelling housing and community title subdivision (the estate) on vacant land at Lot 206 in DP 1070297, known as 1-5 Main Street, Mount Annan (the site).
-
The site was the subject of a 2016 decision of the Court: Mount Annan 88 Pty Ltd v Camden Council [2016] NSWLEC 1072 (Mount Annan 88) in which the Court considered an appeal for a development comprising 246 x 3 storey dwellings. That appeal was dismissed as the height of the development exceeded the height standard under the Camden Local Environmental Plan 2010 (the LEP) and Commissioner Brown was not satisfied that the height breach was justified as required by cl 4.6 of the LEP. Commissioner Brown also noted a number of design issues that would need to be addressed in order to grant consent had he been satisfied with the height breach.
-
The application that came before the Court, as amended with leave in February 2019, seeks approval for the construction of 139 x 2 storey dwellings…
Keep reading for free
Create a free CaseChat account to read Sunland No. 35 Pty Ltd v Camden Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] NSWLEC 1391
- Decision Date
CaseChat Overview and Summary
The central legal issues revolved around whether the development application satisfied all necessary legislative requirements, including alignment with the Camden Local Environmental Plan 2013, the Environmental Planning and Assessment Act 1979, and other relevant planning instruments. Specifically, the court needed to determine if the proposed subdivision met the criteria for approval under the Act, considering both the physical and environmental implications of the development.
The court's reasoning focused on a detailed examination of the application, including the engineering and landscaping plans, the compliance with zoning and environmental laws, and the potential impacts on the surrounding area. The court found that the application met all relevant criteria and that the refusal by the council was not justified. Consequently, the appeal was upheld, and the development application was approved subject to specified conditions. These conditions are detailed in Annexure ‘A’ to the judgment.
Orders
Orders of the court
The orders of the Court are:
(1) Leave is granted to amended engineering and landscaping plans as comprising part of the application as amended.
(2) The appeal is upheld.
(3) Development Application DA 2017/1193/1 for a multi-dwelling housing and community title subdivision at 1-5 Main Street, Mount Annan is approved subject to the conditions in Annexure ‘A’.
(4) The exhibits are returned with the exception of Exhibits 1, A, C, G, T and U.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.