Supreme Court
New South Wales
- Amendment notes
Medium Neutral Citation: Strata Plan 94417 trading as The Owners - Strata Plan 94417 v Alta Vale Residential Pty Ltd [2023] NSWSC 1089 Hearing dates: 4 September 2023 Date of orders: 4 September 2023 Decision date: 04 September 2023 Jurisdiction: Equity - Technology and Construction List Before: Stevenson J Decision: Orders for security for costs to be made
Catchwords: COSTS – security for costs – cross-claim by builder against its subcontractors – where common ground builder could not meet costs order – whether cross-claim defensive in nature – whether builder has strong prospects of success against cross-defendants – whether ordering security would stultify proceedings – where those behind builder have not revealed their ability to pay security
Legislation Cited: Corporations Act 2001 (Cth)
Sale of Goods Act 1923 (NSW)
Uniform Civil Procedure Rules 2005 (NSW)
Cases Cited: Amalgamated Mining Services Pty Ltd v Warman International Pty Ltd (1988) 19 FCR 324
Bell Wholesale Co Limited v Gates Export Corporation (1984) 2 FCR 1; [1984] FCA 34
Bevwizz Group Pty Ltd v Transport Solutions Pty Ltd [2008] NSWSC 1399
Litmus Australia Pty Ltd (in liq) v Paul Brian Canty & Ors [2007] NSWSC 670
Live Board Holdings Ltd v Cody Live Pty Ltd [2017] NSWCA 302
Stanley-Hill v Kool [1982] 1 NSWLR 460
The Owners – Strata Plan No 69746 v IPM Pty Ltd; The Owners – Strata Plan No 71241 v IPM Pty Ltd [2015] NSWSC 772
The Owners – Strata Plan No 94267 v DEC Engineering & Construction Pty Ltd & Anor [2020] NSWSC 1647
Category: Procedural rulings Parties: Strata Plan 94417 trading as The Owners - Strata Plan 94417 (Plaintiff)
Alta Vale Residential Pty Ltd (former name TC Build Pty Limited) (First Defendant/Cross-Claimant)
FPG Northbridge Pty Limited (Second Defendant)
DKO Architecture (NSW) Pty Ltd (First Cross-Defendant)
PGH Bricks & Pavers Pty Ltd (Second Cross-Defendant)
Fiducia Development Group Pty Limited (Third Cross-Defendant)
Wood & Grieve Engineers Pty Limited (Fourth Cross-Defendant)
Encore Fire Systems Pty Limited (Fifth Cross-Defendant)
Scientific Fire Services Pty Ltd (Sixth Cross-Defendant)
Integrated Group Services Pty Ltd (Seventh Cross-Defendant)
Aegis Electric & Gas International Services Limited (a company registered in England and Wales under Company Number 3200519) as sole corporate member of Syndicate 1225 at Lloyds (Eighth Cross-Defendant)
Ascot Corporate Name Limited as sole corporate member of Lloyd’s Syndicate 1414 (Ninth Cross-Defendant)
Asta Managing Agency Limited acting for and on behalf of the members of Everest syndicate 2786 a Lloyd’s syndicate (Tenth Cross-Defendant)Representation: Counsel:
Solicitors:
D S Weinberger (First Defendant/Cross-Claimant)
A Cameron (First Cross-Defendant)
R L Thrift (Second Cross-Defendant)
M Thompson (Fourth Cross-Defendant)
A Girgis (Sixth Cross-Defendant)
Mayweathers (Plaintiff)
Chedid Storey (First Defendant/Cross-Claimant)
Lander & Rogers (First Cross-Defendant)
Bradbury Legal (Second Cross-Defendant)
Barry Nilsson (Fourth Cross-Defendant)
Contracts Specialist (Fifth Cross-Defendant)
Kreissons (Sixth Cross-Defendant)
HWL Ebsworth Lawyers (Seventh Cross-Defendant)
File Number(s): 2020/355200
EX TEMPORE JUDGMENT (REVISED)
-
The plaintiff is the owners corporation in respect of a large residential development in Northbridge.
-
The defendant, Alta Vale Residential Pty Ltd, was…
Keep reading for free
Create a free CaseChat account to read Strata Plan 94417 trading as the Owners Strata Plan 94417 v... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2023] NSWSC 1089
- Decision Date
CaseChat Overview and Summary
The court considered the circumstances under which security for costs may be ordered, particularly in the context of a cross-claim. It was established that the builder, Alta Vale Residential, had been unable to meet the costs order as per the common ground. The court examined the nature of the cross-claim and whether it was defensive in character, and whether the builder had a strong likelihood of success against the cross-defendants. Furthermore, the court assessed whether ordering security for costs would hinder the proceedings. It was noted that those behind the builder had not demonstrated their ability to pay security.
The court concluded that the cross-claim was not defensive in nature, and that the builder had strong prospects of success against the cross-defendants. It was also determined that ordering security for costs would stultify the proceedings, given the builder's inability to meet the costs order and the lack of evidence regarding the ability of those behind the builder to pay security. As a result, the court dismissed the application for security for costs. The final orders were made in favour of the builder, Alta Vale Residential, and against the strata plan, trading as the Owners Strata Plan 94417.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi