Stralow D v North Sydney
[2004] NSWLEC 124
•03/24/2004
Land and Environment Court
of New South Wales
CITATION: Stralow D & Anor v North Sydney [2004] NSWLEC 124 PARTIES: APPLICANT
STRALOW D & ANORRESPONDENT
NORTH SYDNEY COUNCILFILE NUMBER(S): 11487 of 2003 CORAM: Hoffman C KEY ISSUES: Development Application :- heritage item
streetscape
building height plane
landscape area
front setback.LEGISLATION CITED: North Sydney Local Environment Plan 2001
North Sydney Development Control Plan 2002CASES CITED: DATES OF HEARING: 22 - 24/03/2004 DATE OF JUDGMENT: 03/24/2004 LEGAL REPRESENTATIVES:
APPLICANT
Mr B Hones (solicitor)
Hones LawyersRESPONDENT
Mr N Ogden (solicitor)
Mallesons Stephen Jacques
JUDGMENT:
1
11487of 2003 Hoffman C 24 March 2004IN THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH WALES
v North Sydney CouncilDouglas Stralow & Anor
Applicant
Respondent
Judgment
1 . This was a Class 1 Appeal 11487 of 2003 between D & E Stralow and North Sydney Council regarding the refusal of an application for a two-car garage at No. 8 Baden Road, Neutral Bay.
2 . The house was a two-storey Federation heritage item under the North Sydney Local Environment Plan 2001 . The council had already approved a single car garage in a similar position and design to the proposal. This earlier consent involved rebuilding the front veranda of the heritage item across the full front facade of the house because its brick balustrade wall had developed a lean outwards and had dropped. Cracks in the brick balustrade of the verandah revealed this. The house itself had no cracks.
3 . The veranda was not to be rebuilt the same as the existing curved full brick balustrade. It had been approved by Council with a brick sub floor and a timber balustrade between brick piers with stone caps. The approved single garage extended between the verandah and the south side boundary and came out to the street boundary where there was a rock face stone wall about 1½ to 2 m high across the full frontage at footpath level except for two sets of entry steps. The wall retained the soil in the front setback of the house; the soil was at the top of the wall and then sloped up a little to the front wall of the house.
4 . The proposed two car garage extended beneath the southern corner of the verandah and butted up to the south east corner of the two storey house. It was 2.4 m wider than the existing approved garage. It was to have stone faced external walls with a central stone pillar to match the existing stone front wall. Above the lintel the concrete roof slab was to have a stone faced edge and a planter box in matching stone about 500mm high to match a similar stone faced garage and planter on No.6A Baden Road.
5 . Vegetation would hang over the edge of the planter box and behind that was hedge type shrubs with a timber framed balustrade mounted on the rear wall of the planter. This balustrade was apparently to match the style of the new verandah balustrade approved with the single car garage although there were no details of the balustrades design, and there were no conditions to require the two to match. This was peculiar as the house was a heritage item under the statute and one would of thought that such details would be important.
6 . The new access path from the top of the entry steps to the front door approved as a ramped path in the single garage development application, was altered in this proposal to be level with 4 steps onto the garage roof slab. This necessitated a balustrade between the path and the lower set of steps to comply with the Building Code of Australia. None was shown on the plans, but this was not raised by the Respondent. Also the steps onto the roof slab were shown in a different place on the plan view to the elevation. This was not raised by the Respondent. There was a landscape plan and it showed the planter box and shrubs on top of the garage roof as previously mentioned. An existing set of steps up from the footpath and a concrete side path on the south of the house was to be dug up and made into a landscaped area. Also landscaping was to be done across the full frontage to the street, which was 21.67 m long. The proposed garage was 6.6 m wide, the approved single garage was 4.2 m to the outside of its walls.
7 . At the north end of the site, Baden Road came to a dead end and there was a concrete carpark and carports to several blocks of flats on battle axe lots beyond the end of the street. A 4 or 5 m high stonewall of similar appearance to No. 8’s stonewall was on the uphill side of these carparks. It supported the backyard of a house fronting the next street uphill of Baden Road.
8 . Baden Road was not a conservation area. No. 6 & 6A was a matching Federation house to No. 8 and both of those and No. 2 Baden Road were heritage items. No. 6 & 6A came from the subdivision of the house into 2 units and it had 2 garages at the street front approved by the Council recently and they had been built with planter boxes above the garage door openings and stone facing.
10 . The issues in the Appeal are:9 . No. 2 Baden Road was a Federation apartment building and had a row of eight garages at the street front with planter boxes above the doors.
1. Whether the proposed development should be approved given that the proposal breaches the building height plane (BHP) provisions of cl 18 of the North Sydney Local Environment Plan 2001(NSLEP 2001) which will result in an unacceptable bulk and scale inconsistent with neighbouring development on Baden Road.
2. Whether the Applicant’s objection pursuant to State Environmental Planning Policy No.1 , in this regard should be upheld. 3. Whether the proposed development should be approved given that the proposal breaches the building setback provisions of cl. 19 of the NSLEP 2001 which will result in unacceptable bulk and scale inconsistent with neighbouring development on Baden Road.· The proposal breaches the BHP by 2.6 metres on the Eastern Boundary.
4. Whether the proposed development should be approved given the lack of SEPP No. 1 objection with respect to the proposal’s non-compliance with clause 19. (The applicant at the hearing tendered an objection in this regard.) 5. Whether the proposed development should be approved having regard to the setback requirements of s 7.3 (f) of North Sydney Development Control Plan 2002.(NSDCP 2002)(a) The proposal breaches the setback control by 3.5 metres.
6. Whether the proposed development should be approved given that the proposal breaches the landscape area provisions of cl. 20 of NSLEP 2001.
7. Whether the Applicant’s SEPP No. 1 objection, in this regard, should be upheld. 8. Whether the proposed development should be approved having regard to the landscape area requirements of s 7.4(k) of the NSDCP 2002.(a) The proposal will result in a 15% non-compliance will the landscaped area control, given that the existing Site exhibits a defined landscaped area of 41.9% of the total site area and the proposal will result in a reduction of the landscaped area to 35% of the total site area.
9. Whether the proposed garage should be approved under the impact on the heritage item.(a) The proposal provides for only 66.5% soft landscaping when the control requires 80%.
(a) Cl. 14 of the NSLEP 2001 (Consistency with aims of plan, zone objectives and desired character) in that the proposed development fails to satisfy cl. 3(e) that being to identify and encourage the conservation of the heritage of North Sydney and to ensure that development does not adversely affect the significance of the heritage of North Sydney.
(b) Cl. 48(1)(a) and (c) of the NSLEP2001 in that the proposal compromises the heritage significance of the building,
(c) Cl. 48(7) of the NSLEP 2001 in that no structural engineers report has been submitted to Council demonstrating that the works can be undertaken in a practical manner to ensure that the heritage building and structures on neighbouring properties are not affected, or put at risk, by the works.
(d) S. 7.4(j) (iii) on the NSLEP 2001 in that the width and size of the double garage impacts upon the streetscape.
(e) Clause 39(1)(c) and 39(2) of the NSLEP 2001 in that the proposed double garage requires excavation that results in a detrimental impact upon the sandstone retaining wall.
(f) S. 7.2(a) of the NSDCP 2002 in that the proposal results in new ground levels that are greater than 500mm from the existing ground level, the proposal involves the partial removal of the sandstone retaining wall on the properties front boundary and excavation is proposed closer than 1 metre to this boundary.
(g) S. 8.8(c) (iv) of the NSDCP 2002 in that the proposal results in the demolition and removal of a section of the sandstone wall at the front of the site.
10. Whether the proposed development should be approved having regard to its inconsistency with the aims and objectives of cl. 14 and 16 of the NSLEP 2001 and s. 7.4 j (iii) and 8.1 of NSDCP 2002 of the South Cremorne Planning Area Character Statement (Kurraba Point South Neighbourhood).(h) S. 8.8(d) of the NSDCP 2002 in that the proposal develops the front garden area for carparking and does not retain a significant landscape feature of the site, being the front garden and the retaining wall.
(a) The proposal is inconsistent with clauses 14 & 16 of the NSLEP in that the development is of an unsatisfactory bulk and scale.
(b) The proposed width and size of the double garage compromises the streetscape.
11. Whether the proposed development is acceptable given built form requirements of s 7.3 of the NSDCP 2002:
(a) S 7.3(a) - context
(b) S 7.3(h) - form, massing, scale
(c) S 7.3(i) - built form character
(d) S 7.3(m) - colour and materials
11. The court heard the Respondent’s evidence from:
· Ms L Varley: landscape architect and Council’s conservation planner;
· Ms A Stuart: town planner – assessment officer for the council;
· Mr A Colenbrander: consultant Geotechnical Engineer.
12 . There were no objectors to the proposal and it had been publicly notified.
13. The applicant’s evidence was heard from:
· Mr G Brooks: charted architect and heritage expert;
· Mr G Goodyer: town planner and accountant;
· Ms N Sonter: landscape consultant who was not required for cross-examination but had prepared a plan that was in evidence.
14 . At the end of the hearing the parties agreed there were three threshold issues, being the three SEPP 1 objections being to;
· The building height plane
· The landscape area
· Building setback
16 . The applicant observed that;15. The Respondent pressed the fourth threshold issue being cl 48(7)(b) the need for a structural engineers report as defined in the NSLEP2001 to ensure the stability of the heritage item and associated with the requirements of cl 39 of the LEP regarding excavation of land.
· Both parties’ engineers agreed, after the Court directed a joint on site inspection and report, to a procedure of investigation and construction identified in exhibit L that would ensure the stability of the heritage item.
· The Council in approving the single garage had already approved the rebuilding of the front verandah of the heritage item.
· The application did not involve the demolition of the house applicable under cl 48(7).
· The appropriate clause was cl 48(4) for the subject proposal and all matters in that proposal were before the Court.
· Any concerns in relation to cl 39 were resolved by the joint findings of the engineers in exhibit L.
17 . The Court agrees with the applicant’s submission and evidence in that regard, and is satisfied with the engineer’s joint report. The report could be summarised as:
- contrary to the front verandah that had developed structural faults, the house had no cracks. The house was probably founded on rock, in which case the proposed garage could be easily built touching the house on one corner. The site and the house would remain stable. If investigations found the house was not on rock, then it would have to be underpinned in the relevant corner. There were no engineering concerns that this could not be done if required.
18 . On the building height plane breach, the Court finds that the definition of existing ground level in the LEP, is as identified in the applicants evidence – that is at the top of the street boundary retaining wall, and not at its bottom. Therefore the breach of the height plane occurs only at the opening in the wall for the existing side steps and that is the same breach that the Council approved in giving consent to the single car garage.
19 . The Court accepts the applicant’s SEPP1 objection in exhibit J. In spite of the breach, the underlying objectives of the building height plane standard are achieved for the reasons in cl 4 of the objection, and compliance is unreasonable and unnecessary in the circumstances and there is no conflict with the objectives of the Act.
20 . On the building setback SEPP1 objection the Court accepts the applicant’s contention that the garages, both single and double, all along both sides of Baden Road are at or near zero setback to the street including the garage on No. 6A adjoining the site. The latter abuts the proposed garage on the southern boundary of the site. Further, the 5m high stone wall at the northern boundary is defined as building under the relevant statute. Under cl 19 therefore, no SEPP1 objection is needed. However, if I am wrong on that, the only relevant objective of the standard that can apply is the need to minimise the streetscape impact.
21 . The facts are clear. The street is not a conservation area. The subject site is the only property left without a carport, garage or parking area at zero setback to the street. The proposal is consistent with the streetscape and compliance with the standard is unreasonable and unnecessary in the circumstances and there is no conflict with the objectives of the Act.
22 . The only other way streetscape impact needs to be considered is from a question of how the garage might adversely effect the significance of the heritage item and its bulk and scale. In relation to heritage item I shall deal with that later.
23 . The third SEPP1 objection was related to landscaped area. At the end of the hearing the town planners of both parties agreed that the existing allotment did not comply with the standard of 50% of the site to be landscaped. The existing status was agreed at 41% landscaped area as the site stood, and the proposal would reduce that to 35%. A mitigating circumstance, not strictly related to the consideration of a SEPP1 objection, is that the Council had already agreed to a single car garage that further depleted that landscape area. And, the location of the single and the two car proposed garage was at the location of the existing side access steps up from the street and a wide concrete path with little vegetation. Despite this, the steps and the path currently counted as landscaped area under the definition in the statute, but did not function as soft landscaping vegetation. The proposed garage, being a building, could not have the planter box vegetation counted in the landscaped area even though it would have vegetation in it. Further the side pathway that was currently wide concrete behind the garage would be removed and made landscaped area. It would be much better quality landscaped area than existing.
24 . Turning to the SEPP1 objection the Court is satisfied that for the reasons given in the objection, the objectives of the standard and the Act are sufficiently complied with, including the requirement for soft landscaping, given the existing house on the land and its existing non compliance with the landscaped area.
25 . In regard to the heritage provisions of the NSLEP. The question is the impact of the proposal on the heritage significance of the item.
26 . The heritage item is the whole of No.8 Baden Road including the front boundary stone wall. The Council has agreed to removal of about 3.8 m of the stone wall for the single garage. The proposal adds 2.4 m to that, out of a total frontage of 21.67 m. It can be seen that a substantial part of the original wall will remain and that is the section that is directly in front of the house.
27 . The Heritage Study Inventory sheet was tendered and it was noted by the applicant that it referred only to the house, as did the photographs attached to it. The Court accepts that the wall is part of the item, and in the presentation of the item to the observer on the street, the wall is important.
28 . The Court is satisfied on the evidence that the impact of the garage will not prevent the observer understanding the original context of the house. The proposed garage is below and to the side of the house, although partly attached. One corner of the full width verandah will rest on the garage roof. But this is a small part of the veranda. The two buildings, the garage and the house, will still be seen as completely separate and the garage will match in materials and general size and planter box vegetation, the garage on the sister house at No. 6 and 6A. This similar garage on No. 6A provides an excellent opportunity for the Court to understand the final impact of the proposal on both the streetscape and the heritage item. Its bulk and scale are subordinate to, and diminutive compared to the house which will remain intact except as already approved by Council to be altered.
29 . One could say the existing two garages on the sister house at No. 6 and 6A Baden Road, and the subject proposal, when all built more or less to match, will enable the original houses to be more recognisable for their heritage, with their garages seen as a more recent addition to accommodate modern means of personal transport.
30 . The Council’s DCP recognises this need by requiring 1.5 cars per 3 bedroom house or dual occupancy. The subject house is not subdivided but it has been modified to have 2 domiciles, one downstairs and one upstairs. Although the elderly occupants do not use all the bedrooms as such, they are capable of having 3 bedrooms each requiring 3 car spaces.
31 . The evidence was that the number of garage entries in Baden Road have reduced the number of on street parking spaces to perhaps 5 or 6. This is partly because it is a narrow street and it is not possible to have parking both sides. The location of the proposed garage is in a “No Parking” restricted zone so that the creation of a footpath crossing to the proposal does not reduce on street car parking spaces that are in great demand. In fact it reduces the demand by 2 spaces.
32 . The Council recently tried to assist local frail or disable persons by resolving to make one car space opposite the site into a disable driver’s space. Since that space is the closest parking place to the subject site, which currently has no onsite car parking, the proposal would free up that on street space for other residents and visitors of Baden Road.
33 . Turning to the Character Statement for the South Cremorne Planning area which is part of the DCP 2002, it requires new buildings to complement existing building forms in massing, composition, materials and colours and maintaining existing subdivision patterns.
34 . The proposal does all those things in respect of the immediate neighbouring garages. It is not in conflict with the conservation of the heritage item and the new landscaping will visually improve the setting of the heritage item in both heritage experts’ opinions, and improve the visibility of the item to the observer in the street. There is no unacceptable impact on the additional requirements of the character statement included in the Kurraba Point South neighbourhood.
35 . Ms Varley expressed the opinion that the landscape treatment could be even better if it matched to the existing landscape on No.’s 6 and 6A which she thought was very successful and suited to the age and heritage significance of the building. In the end the draft deferred commencement conditions put by the Respondent enabled Council to have some input to this, and to the final structural solution, and, to the matching of the garage facade heights and associated works and materials to the adjoining garage on No. 6A Baden Road.
36 . Amended plans No. DA 03C, 04C and O5C went some way towards illustrating these changes of construction detail but further clarification was needed. To ensure it is satisfactory to Council and its heritage expert, deferred commencement is the best course.
37 . The Court is satisfied that the proposal , subject to appropriate conditions will not compromise the streetscape, building form and landscaped area of the site or the neighbourhood and will not compromise the heritage significance of the heritage item. It is an acceptable proposal and should be approved.
1. The appeal is upheld.38 . Therefore the Orders of the Court are;
2. Deferred commencement consent is given for a two car garage at No. 8 Baden Road, Kurraba Point, North Sydney as shown in the drawings by Albion Architects and Builders in drawings, DA01B, DA02B, DA03C, DA04C, DA05C, DA06B and landscape plan by Botancia drawing LPO1/B Job No. 040201, all in accordance with, and as amended by, the conditions in Annexure A hereto.
3. The exhibits, are to be returned to the parties except exhibits A, B, L, M and 2, 7, 12 and 13.
- ___________
K G Hoffman
Commissioner of the Court
nm/rag
Appeal No: 11487 of 2003
Annexure “A”
Conditions of Deferred Commencement Consent
Douglas Stralow and Anor v North Sydney Council
DEVELOPMENT APPLICATION NO. D402/038 BADEN ROAD, NEUTRAL BAY
PART ABUILDING CODE OF AUSTRALIA CLASSIFICATION: Class 1a
DEFERRED COMMENCEMENT CONDITIONS
This consent shall not operate until the following deferred commencement conditions have been satisfied.
Evidence required to satisfy this condition must be submitted to Council within 1 year of the date of this consent, or the consent will lapse in accordance with Section 95 of the Environmental Planning and Assessment Regulation 2000.
AA1. To ensure the conservation of the heritage house upon the land, the Applicant will undertake the following to demonstrate the capacity for adequate support for the house: -Investigative works and certification
(b) Provide a management plan and construction sequence generally in accordance with the recommendations of Peter Allsopp Pty Ltd and GHD Longmac Pty Ltd, as contained in Site Instruction Sheet dated 22 March 2004 (Exhibit L).
(a) Excavate 2 test pits and provide Concept Sketches as recommended by Peter Allsopp Pty Ltd and GHD Longmac Pty Ltd by Site Instruction Sheet dated 22 March 2004 and marked plan 04033/2 (Exhibit L); and
- All details are to be certified by an appropriately qualified and practicing Structural Engineer and submitted to Council prior to the activation of this consent.
(Reason: To ensure the protection and structural integrity of the building is maintained).
Structural Adequacy of Adjoining Properties
AA2. A report certificate prepared by an independent appropriately qualified and practising structural engineer, at no cost to the Council, detailing the structural adequacy of adjoining properties No’s. 6 & 6a Baden Road, and certifying their ability to withstand the proposed excavation and any measures required to be incorporated into the work to ensure that no damage will occur to adjoining properties during the course of the works, shall be submitted to Council prior to the activation of this consent.
- (Reason: To ensure the protection and structural integrity of adjoining properties).
(Reason: To ensure the structural integrity of the building is maintained).Structural Adequacy of Existing Building
AA3. A report Certificate prepared by an independent appropriately qualified and practising structural engineer,, detailing certifying the structural adequacy of the property and its ability to withstand the proposed additional, or altered structural loads shall be submitted to Council prior to the activation of this consent.
Structural Stability- Components to be Retained
AA4. A detailed reportcertificate prepared by anappropriately qualified and independent appropriately qualified and practising structural engineer, shall separately certifying the structural stability of, and the means of support during all stages of construction, of, and all components to be retained and/or altered, having regard to the overall development proposed. This shall be provided to Council prior to the activation of this consent. Application. The certificate shall also include all details of the methodology to be employed in construction phases to achieve the above requirements satisfying the criteria detailed in this condition.
- (Reason: Heritage ConservationTo ensure that the development can be undertaken in accordance with accepted construction practices as indicated on the endorsed development plans, without the need for modification of the consent, and to ensure compliance with the terms of the development consent granted for the works).
AA5. The garages is to be provided with panel lift doors with recessive colouring, detailing and finishing treatments that break up the visual solid mass of the door openings, and are complimentary to the texture and appearance of the adjacent and existing sandstone walling. The doors are to be installed and operated in such a manner that at no time do they project onto the public footpath during their operation. s to have panelled doorss . Amended plans demonstrating compliance with this condition must be submitted to Council prior to the activation of this consent.
( Reason: To reduce the streetscape impact of an open void below the heritage listed dwelling, and ensure the heritage value of the property is not eroded by the development, and also to ensure appropriate pedestrian amenity and safety).
External façade of the garage
AA6. The proposed face brick to be amendedexternal façade of the garages must be provided with a weathered sandstone of a texture, colour and surface finish that is consistent and complementary with the form, condition and age of the existing sandstone walling at the front of the property. Also the height of the garage door, and the stone planter box above is to be matched to the heights of the same elements in the abutting garage in No. 6A Baden Road. to sandstone or sandstone cladding Amended plans demonstrating compliance with this condition must be submitted to Council prior to the activation of this consent.
(Reason: To ensure the cultural value of the heritage streetscape element is not adversely eroded by the proposed works by the provision of uncomplimentary building materials and elements of sandstone walling).
Concrete roof slab – street facade
AA7. The exposed concrete roof slab is not to be exposed at the street frontage, but and is to be fully obscured by weathered sandstone of a texture, colour and surface finish that is consistent and complementary with the form, condition and age of the existing sandstone walling at the front of the property. . Amended plans demonstrating compliance with this condition must be submitted to Council prior to the activation of this consent.
( Reason: To ensure the cultural value of the heritage streetscape element is not adversely eroded by the proposed works by the provision of uncomplimentary building materials and elements of sandstone walling).
Concrete roof slab – landscaping
AA8. The proposed lawn and pavers should be amended to thegarage roof must be reinstatement provided with landscaping elements generally in accordance with the landscape plan numbered Job. 040201 Drawing LP.01/B, dated 19 March 2003, prepared by Botanica, and shall have a planter box above the southern wall of the garage of approximately 1200mm in width to that of the eastern planter box, a minimum depth of 750mm, and be provided with a permanent irrigation system. Council’s Heritage Officer may request landscaping within the front setback area across the full frontage of the property to be amended to reflect greater sympathy, for the age and heritage significance of the heritage item, being No. 8 Baden Roadof garden shrubbery over the majority of the concrete slab. Amended plans demonstrating compliance with this condition must be submitted to Council prior to the activation of this consent.
(Reason: To retain the landscape setting of the dwelling, and to ensure that the plantings provided have sufficient soil and water conditions to ensure their long term survival and health).
Lattice screen on Common Boundary
C18.
AA9. The lattice screen panel on the southern boundary closest to Baden Road tomust be scaled tapered down in height from 1.8 metres to a maximum height of one metre at the front boundary of No. 8 Baden Road. Amended plans demonstrating compliance with this condition must be submitted to Council prior to the activation of the consent.
(Reason: To reduce the overall bulk and scale of the car structure).
Balustrade to front stairs
AA10. The Applicant will provide a balustrade wall compliant with the Building Code of Australia (BCA) for the proposed front stairs. This balustrade wall must be constructed with a weathered sandstone of a texture, colour and surface finish that is consistent and complimentary with the form, condition, and age of the existing walling at the front of the property. The balustrade design and dimensions are to be submitted to Council’s satisfaction. Amended plans demonstrating compliance with this condition must be submitted to Council prior to the activation of this consent.
(Reason: To ensure compliance with the BCA in a manner sympathetic to the heritage item).
PART B.
OPERATIONAL CONDITIONS
A. Conditions that Identify Approved PlansOnce the conditions in Part A have been complied with to council’s satisfaction under s. 80(3) of the Environmental Planning and Assessment Act 1979, the following conditions apply.
(Reason: Statutory)Development in Accordance with Plans
A1. The development being carried out in accordance with drawings numbered DA.01B,DA.02B, DA.03C, DA.04C, DA.05C, DA.06B by Albion Architects and Builders, and Landscape Plan by Botanica drawing LP.01/B Job No. 040201, as modified to be satisfactory to Council in Part ‘A’ above , and as further amended by the following conditions.
Plans on Site
A2. A copy of all stamped approved plans, specifications and documents (including the Construction Certificate if required for the work incorporating certification of conditions of approval) certification shall be kept on site at all times so as to be readily available for perusal by any officer of Council or the Principal Certifying Authority.
- (Reason: To ensure that the form of the development undertaken is in accordance with the determination of Council, Public Information and to ensure ongoing compliance)
No Demolition of Extra Fabric
A3. Alterations to, and demolition of the existing building shall be limited to that documented on the approved plans (by way of notation). No approval is given or implied for removal and/or rebuilding of any portion of the existing building which is shown to be retained.
- (Reason: To ensure compliance with the approved development)
A4. Landscaping works on the site are to be undertaken generally in accordance with the landscaping plan unnumbered LP.01/B job No. 040201, prepared by Botanica as amended to be satisfactory to Council in Part ‘A’ above.Albion Design and Construction Co
- (Reason: To ensure appropriate landscaped area and landscaping amenity at the stage of the development)
C. Conditions that Require Subsidiary Matters to be Completed Prior to Issue of a Construction Certificate
Damage to Public Infrastructure
C1. The applicant shall bear the cost of all restoration works to Council’s property damaged during the course of this development. The applicant shall advise Council, in writing, of any existing damage to Council property before commencement of the development. A dilapidation survey of Council’s assets, including photographs and written record, must be prepared by a suitably qualified person and submitted to Council prior to the submission of an application forissuing of any Construction Certificate.
- Note: This documentation will be used to resolve any dispute over damage to infrastructure. It is in the applicant’s interest for it to be as full and detailed as possible.
(Reason: To ensure the protection of existing built public infrastructure)
Damage Bond (Potential Damage)
C2. A Bond of $2,000.00 shall be deposited with Council, prior to the issue of any application for construction certificate, against the construction of drainage works that revert to Council’s care and control.against the potential for damage to Council’s footpath and road reserve infrastructure during the construction process.
- (Reason: To ensure appropriate security is in place for the pStatutoryrotection or repair of Public Infrastructure)
C3. The applicant shall design the vehicular access way in compliance with the following:
(a) The vehicular access way shall be designed to comply with AS 2890.1 to ensure that a B85 vehicle will not scrape/strike the surface of the carriageway, layback, vehicular crossing or garage floor.
(c) The crossing (between the layback and the property boundary) shall be placed on a single straight grade of approximately 4.5%, falling to the back of the layback.(b) The width of the vehicular layback shall be 6.3 metres (including the wings).
- (d) A certificate prepared by aAn appropriately qualified and practising Civil Engineer shall be provided to the Principal Certifying Authority a certificate that, where required, the architectural design drawing has been amended to certify compliancey with these requirements prior to the issuing of any Construction Certificate. Consent
A photocopy of the aforementioned certificate shall be presented with the Construction Certificate.
(Reason: To facilitate appropriate vehicular access to private sites, without disruption to pedestrian and vehicular traffic)
C4. A Bond of $4,000.00 shall be deposited with Council against any damage or failure to complete to the relevant specification the construction of a vehicular crossing prior to the issue of any Construction Certificate. (See schedule).
Bond for Engineering Construction Works (Vehicular Crossing)
- (Reason: To ensure appropriate security for works on public land and an appropriate quality for new Safety and Statutorypublic infrastructure)
C5. The applicant shall apply for a vehicle crossing permit and this shall incorporate demonstrate compliance with Council’s required and specified levels. The applicant shall construct (reconstruct) full-width concrete vehicular crossings to all entrances and exits in accordance with Council’s standard plans and specifications. Construction shall include all service adjustments and shall have regard of adjacent footpaths and kerb and gutter. Such A certificate is to be provided is to be certified by an appropriately qualified and practising Civil Engineer, with the proposed design, to certify compliance with the appropriate Australian Standards for vehicular access and Council’s Infrastructure Specification and Vehicular Access Application Guidelines and Specification . Details demonstrating how these requirements will be complied are to be submitted with the Construction Certificate.
- The vehicle-crossing permit must be obtained prior to any works commencing in relation to the construction of any driveway, associated vehicular crossing or parking facilities.
A Bond of $# (ENTER AMOUNT) shall be deposited with Council against the construction/reconstruction of the vehicular crossing prior to the issue of a construction certificate.
(Reason: To facilitate suitable vehicular access to private sites, without disruption to pedestrian and vehicular traffic)
C6. The following details must be submitted with the application for Construction Certificate:-
- (i) Longitudinal section along the extremities and centre-line of each driveway/access ramp at a scale of 1:50.
(iii) The sections shall show all relevant levels and grades (both existing and proposed) including those levels stipulated as boundary levels.
(iv) The sections shall show the calculated clearance to the underside of any overhead structure.
(v) A longitudinal section along the gutter line showing how it is intended to blend the vehicular crossing into the existing kerb and gutter.
(vi) All details of internal ramps between parking levels.
(Reason: To facilitate suitable vehicular access to private sites, without disruption to pedestrian and vehicular traffic)All details are to be certified by an appropriately qualified and practising Civil Engineer, as complying with Australian Standard AS 2890.1, Parking Facilities and Council’s standard specifications.
Road Works- Reconstruct Carriageway Shoulder
C7. The applicant must reconstruct/construct the carriageway shoulder (600mm wide strip adjacent to all new gutter works), layback, full frontage kerb/gutter (except for the location of the layback), crossing, grass verge, footpath pavement and transition works. The works shall be designed and constructed in compliance with the following:
a) All elements of the works within the road reserve is to be constructed in accordance with Council’s current documents Infrastructure Specification and Vehicular Access Application Guidelines and Specification.
b) All redundant laybacks must be reinstated as kerb and gutter.
c) The proposed kerb gutter and layback gutter alignment shall be raised on a parallel alignment to the existing gutter to ensure that the crossfall grade of the carriageway shoulder is no greater than 5.5% or less than 1.0% for a distance of 600mm, falling to the gutter, starting from the surface of the existing carriageway 1050mm from the existing face of kerb.
d) The footpath pavement and grass verge shall be placed on a single straight grade of 3.0% falling to the top of kerb.
f) Kerb/gutter transition works are required to ensure gentle changes in grade and longitudinal drainage between the existing and proposed kerb and gutter. These works have been assessed as:e) Footpath pavement transition works are required to ensure gentle changes in grade, drainage and no ‘trip’ hazards between the existing and proposed pavement. These works have been assessed as 1500mm in length or one pavement panel, whichever is the greatest.
ii) Downstream of the existing layback, the kerb/gutter must be reconstructed for a length of 1000mm or to an existing joint, whichever is the greatest.i) Upstream of the proposed layback, the kerb/gutter must be reconstructed for a length of 1000mm or to a point where a longitudinal gutter grade of 1.0% can be achieved or to an existing joint, whichever is the greatest.
g) A certificate prepared by an appropriately qualified and practising Civil Engineer, shall be provided to the Certifying Authority to certify compliance with these requirements prior to the issuing of the Construction Certificate.
- (Reason: To facilitate suitable vehicular access to private sites, without disruption to pedestrian and vehicular traffic and to ensure appropriate access and infrastructure protection that is integral with infrastructure on surrounding sites)
Footpath level at property boundary
C8. The property alignment levels shall match the existing levels except where modified for the vehicular crossing. Where modified by the vehicular crossing the footpath level of the property boundary shall be 500mm lower than the existing property alignment level.
Property Alignment Levels
C2. The property alignment levels shall match the existing levels except where modified for the vehicular crossing. Where modified by the vehicular crossing the property alignment shall be 50mm lower than the existing property alignment level so that the entry floor level of the garage is 50mm below the existing boundary level.
- (Reason: To facilitate suitable vehicular access to private sites, without disruption to pedestrian and vehicular traffic and to ensure appropriate access and infrastructure protection that is integral with infrastructure on surrounding sites)
C9. Where construction or excavation activity requires the disturbance of the soil surface and existing vegetation, details including plans and specifications shall be submitted to Council accompanying the Construction Certificate, which provide adequate measures for erosion and sediment control. As a minimum, control techniques are to be in accordance with North Sydney Council Guidelines on Erosion and Sediment Control, or a suitable and effective alternative method. The Control Plan shall incorporate and disclose:
- (a) All details of drainage to protect and drain the site during the construction processes;
(b) All sediment control devices, barriers and the like;
(c) Sedimentation tanks, ponds or the like;
(e) A schedule and programme of the sequence of the sediment and erosion control works or devices to be installed and maintained.(d) Covering materials and methods;
- Details from an appropriately qualified person showing that these design requirements have been met shall be submitted with the Construction Certificate and approved by the Certifying Authority prior to issuing of the Construction Certificate.
- (Reason: To protect the environment from the effects of sedimentation and erosion from development sites)
C10. A photographic survey of adjoining properties No’s. 6 & 6A Baden Road detailing the physical condition of those properties, both internally and externally, including such items as walls, ceilings, roof, structural members and other similar items, SHALL BE submitted to Council and the Principal Certifying Authority (where Council does not issue the Construction Certificate) prior to the issue of a Construction Certificate. This survey is to be prepared by an appropriately qualified independent person agreed to in writing by both the applicant and the owner of the adjoining property.
- On completion of the excavation and building works and prior to occupation of the building, a certificate prepared by the person agreed to by the parties to the effect that no damage has resulted to adjoining premises, is to be provided to Council or the Principal Certifying Authority.
- If damage is identified by the person agreed to by the parties which is considered to require rectification, the damage shall be rectified or a satisfactory agreement for rectification of the damage is to be made with the affected person/s as soon as possible and prior to occupation of the development.
In the event that access for undertaking the dilapidation survey is denied by an adjoining owner, the applicant MUST DEMONSTRATE, in writing, to Council that all reasonable steps have been taken to obtain access and advise the affected property owner of the reason for the survey and that these steps have failed.All costs incurred in achieving compliance with this condition shall be borne by the person entitled to act on this Consent.
- ( Note: This documentation is for record keeping purposes only, and may be used by an applicant or affected property owner to assist in any action required to resolve any dispute over damage to adjoining properties arising from the works. It is in the applicant’s and adjoining owner’s interest for it to be as full and detailed as possible.)
Waste Management Plan
C11. A Waste Management Plan is to be submitted with the Construction Certificate in accordance with the provisions of Section 19 of the North Sydney DCP 2002. The plans should include, but not be limited to, the estimated volume of waste and method of disposal for the construction and operation phases of the development, design of on-site waste storage and recycling area and administrative arrangements for waste and recycling management during the construction process.
- (Reason: To encourage the minimisation of waste and recycling of building waste)
Security Bond Schedule
C12. All fees and security bonds in accordance with the schedule below must be paid or in place prior to the lodgement of any application forissue of the required Construction Certificate:-
| SECURITY BOND & FEE SCHEDULE 8 BADEN ROAD, NEUTRAL BAY DEVELOPMENT APPLICATION NO. D402/03 |
| SECURITY BONDSAMOUNT $ |
Footpath Damage Bond Engineering Construction Bond$2,000.00$4,000.00 |
| TOTAL BONDS$6,000.00 |
- (Reason: Compliance with the development consent)
Bonds
C13. Council will accept a bank guarantee for the purpose of any security bond imposed by these conditions of consent. Such bank guarantee shall be in a form acceptable to the Council and shall be in place prior to the commencement of work and shall remain in place until the submission of the certificate required prior to the occupancy of the completed works.
(Reason: Information, Protection of infrastructure and the environment)
C17. The garage entry shall be 1500mm from the southern property boundary. Details demonstrating compliance with this condition must be submitted with the construction certificate.Parking Facility Garage
- (Reason: Ease of manoeuvrability)
C14. Plans indicating all engineering details relevant to the site regarding the collection and disposal of stormwater from the site, buildings, and adjacent catchments shall be submitted for approval with the Construction Certificate for construction works. Stormwater shall be conveyed by gravity (not a charged system) from the site to the nearest Council stormwater drainage system.
Stormwater and Seepage Water
a) Conveyed by gravity ( not a charged or pumped system ) to Council’s street kerbThat part of the stormwater drainage system that is to be reconstructed/constructed shall be designed and constructed in compliance with the following:
b) The stormwater drainage system shall be designed for an average recurrence interval (A.R.I.) of 1 in 20 years.
c) All redundant stormwater pipelines within the footpath area shall be removed and the footpath and kerb reinstated.
d) Pipelines within the footpath area shall be hot dipped galvanised steel hollow section with a minimum wall thickness of 4.0 millimetres and a section height of 100 millimetres.
e) All plumbing within the site shall be carried out in accordance with AS/NZ3500.3.2 1998, National Plumbing and Drainage Code.
f) Subsoil drains are to be provided on the upstream side of any pit or retaining wall.
(Reason: Local flooding, safety and amenity)Central pierg) Seepage/subsoil water shall be drained to Council’s street kerb via a suitable silt arrester pit.
D. Conditions That Must Be Addressed Prior To Any CommencementC18. The double garage to be separated into two garages with a central pierAmended plans.
Excavation/Demolition
D1. No demolition or excavation shall be carried out until a Construction Certificate has been issued.
(Reason: To ensure compliance with statutory provisions)
Disposal Schedule
a. those materials to be recycled;D1. A disposal schedule for waste materials arising from demolition and excavation shall be submitted to Council, prior to commencement of demolition or building works, identifying:
a. those materials to be reused;
a. those materials to be disposed of.
- A maximum amount of materials shall be recycled or reused.
- (Reason: Environmental Management Protection)
D2. Sandstone blocks (if any) removed from the site are to be either stored for re-use on site or offered to Council in the first instance.
(Reason: To allow for preservation of cultural resources within the North Sydney Council area)( NOTE : The provisions of the Heritage Act may also apply to altering any sandstone elements on any site)
D3. Where Council is acting as the Principal Certifying Authority and where an inspection of building, civil or landscape work is required by these conditions, inspection fees and component certification fees must be paid to Council before Council will undertake any inspections. These fees may be paid at the time of submission of the required Notice of Commencement of works (Form 7). This condition applies regardless of whether a Certificate fee is also payable.
- NOTE : The submission of a Notice of Commencement of works form ‘Form 7’ to Council at least two (2) days prior commencing works is a statutory requirement prior to the commencement of any works on site.
- (Reason: Information with Section 608 (6) of the Local Government Act 1993)
D4. A cigarette butt receptacle is to be provided on the site for the duration of demolition/construction process, for convenient use of site workers.
Cigarette Butt Receptacle – Residential
- (Reason: To ensure adequate provision is made for builders’ waste)
D5. Any person or contractor undertaking works on public land must take out Public Risk Insurance with a minimum cover of $10 million in relation to the occupation of, and approved works within Council’s road reserve or public land, as approved in this consent. The Policy is to note, and provide protection for, Council as an interested party and a copy of the Policy must be submitted to Council prior to commencement of the works. The Policy must be valid for the entire period that the works are being undertaken on public land.
Public Liability Insurance – Works on Public Land
(Reason: To ensure the community is protected from the cost of any claim for damages arising from works on public land)Note: Applications for hoarding permits, vehicular crossings etc will require evidence of insurance upon lodgement of the application.
E. Conditions that Must be Complied With During Demolition and Building Work
(a) After excavation for, and prior to the placement of any footings.Progress Inspections
J1. The Principal Certifying Authority SHALL BE given two (2) working days notice for inspection of the following:
(b) Prior to pouring any in-situ reinforced concrete building element.
(c) Prior to covering of the framework for any floor, wall roof or other building element.
- (d) Prior to covering waterproofing or damp proofing in any wet areas.
(e) After the building work has been completed and prior any occupation certificate being issued in relation to the building.
Notes :
- 1. Where North Sydney Council is acting as the Principal Certifying Authority for the project, notice is to be given by telephone to a Planning and Development Services Administration Officer and an appointment made for the relevant inspection. Failure to advise Council at the stages of construction identified above will result in fines being imposed.
- 2. Failure to advise the Principal Certifying Authority of the need for MANDATORY INSPECTIONS at the critical stages of construction detailed above may result in fines being imposed, works being required to be demolished, or delays experienced in obtaining final certification and occupation of the development in order to resolve issues.
(Reason: Compliance, Health and Safety)
(Reason: Statutory requirement)Replacement of Principal Certifying Authority
J2. If the person exercising the benefits of a development consent changes or replaces the Principal Certifying Authority (PCA) during works on the site, the replacement PCA must notify North Sydney Council within two (2) days of appointment.
Final Compliance Certificate
J3. Within seven (7) days of completion of the building works and prior to occupation or the issue of an Occupation Certificate a Certificate of Compliance under Section 109C (1) (a) of the Environmental Planning and Assessment Act 1979 must be provided by the Principal Certifying Authority. This Compliance Certificate must certify that the completed work complies with the relevant Plans and Specifications and with the following conditions of this development consent: A1, F1, G1, G2, G3, G4, G5.
- (Reason: To ensure compliance with the terms of this development consent)
(Reason: To ensure compliance with the terms of this development consent)Removal of Extra Fabric
J4. Should any portion of the existing building, trees, or curtilage of the site which is indicated on the approved plans to be retained be damaged for whatever reason, all the works in the area of the damaged portion are to cease and written notification given to Council. No work is to resume until the written approval of Council is obtained. Failure to comply with the provisions of this condition will result in the Council institutinge immediate legal proceedings.
Noise
J5. Noise emissions and vibration must be minimised where possible and work is to be carried out in accordance with Environment Protection Authority guidelines for noise emissions from construction/demolition works and must also comply with the provisions of the Protection of the Environment Operations Act 1997.Noise emissions must comply with applicable standards under the Protection of the Environment Operations Act 1997. Vibration from the works must not be felt on any adjoining property.
- (Reason: To ensure residential amenity is maintained in the immediate vicinity)
J6. Materials must not be burnt on the site.
Dust suppression measures must be carried out to minimise wind-borne emissions in accordance with the NSW Department of Housing’s 1998 guidelines - Managing Urban Stormwater: Soils and Construction. Odour suppression measures must be carried out so as to prevent nuisance occurring at adjoining properties.Vehicles entering and leaving the site with soil or fill material must be covered.
- (Reason: To ensure residential amenity is maintained in the immediate vicinity)
(Reason: To ensure residential amenity is maintained in the immediate vicinity)Vibration from Works
J7. Vibration from works is to be undertaken in accordance with industry best practice, and to ensure excessive levels of vibration do not occur and to minimise adverse effects experienced on any adjoining land.
(1) On-street mobile plantSpecial Permits
J8. Unless otherwise specifically approved in writing by Council, all works, processes, storage of materials, loading and unloading associated with the development are to occur entirely on the property. The applicant, owner or builder must apply for specific permits available from Council’s Customer Service Centre for the undermentioned activities on Council’s property pursuant to S138 of the Roads Act. A minimum of forty-eight (48) hours notice is required for any permit:-
- E.g. cranes, concrete pumps, cherry-pickers, etc. - restrictions apply to the hours of operation, the area of operation, etc. Separate permits are required for each occasion and each piece of equipment. It is the applicant’s, owner’s and builder’s responsibilities to take what ever steps are necessary to ensure that the use of any equipment does not violate adjoining property owner’s rights.
- (Reason: Proper management of public land)
(2) Hoardings
- Permits are required to erect Class A and Class B hoardings. If an ‘A’ Class hoarding is to alienate a section of Council’s property, that section will require a permit for the occupation of Council’s property.
- (Reason: Proper management of public land)
- (3) Storage of building materials and building waste containers (skips) on Council’s property
- Permits to utilise Council property for the storage of building materials and building waste containers (skips) are required for each location. Failure to obtain the relevant permits will result in the building materials or building waste containers (skips) being impounded by Council with no additional notice being given. Storage of building materials and waste containers on open space reserves and parks is prohibited.
- (Reason: Proper management of public land)
- (4) Kerbside restrictions, construction zones
- The applicant’s attention is drawn to the existing kerbside restrictions adjacent to the development. Should the applicant require alteration of existing kerbside restrictions, or the provision of a construction zone, the appropriate application must be made and the fee paid. Applicants should note that the alternatives of such restrictions may require referral to Council’s Traffic Committee and may take considerable time to be resolved. An earlier application is suggested to avoid delays in construction programs.
- (Reason: Proper management of public land)Soil Depth
(Reason: Maintenance of environmental amenity)
J1. Planting beds over concrete slabs (basements, roofs, etc) shall provide a minimum depth of soil of 750 mm. Wherever possible, trees and shrubs are to be planted in unexcavated soil. A reduced planting depth of 500 mm is acceptable in areas proposed to be turfed.
Noxious Plants
J9. All lantana, privet, rubber trees, parateria, and other declared noxious plants on the site, shall be eradicated before the commencement of landscape works.
- (Reason: To ensure that plants identified as weed species are not allowed to proliferate or interfere with a quality landscaping outcome)
J10. Building construction shall be restricted to within the hours of 7.00 am to 5.00 pm Monday to Friday and on Saturday to within the hours of 8.00 am to 1.00 pm inclusive, with no work on Sundays and Public Holidays.
- Demolition and excavation works shall be restricted to within the hours of 8.00 am to 5.00 pm Monday to Friday only. (Excavation work includes the use of any excavation machinery and the use of jackhammers, rock breakers, excavators, loaders and the like, regardless of whether the activities disturb or alter the natural state of the existing ground stratum or are breaking up/removing materials from the site).
- The builder and excavator shall display, on-site, their twenty-four (24) hour contact telephone number which is to be clearly visible and legible from any public place adjoining the site.
- (Reason: To ensure that works do not interfere with reasonable amenity expectations of residents and the community)
J11. The work must satisfy applicable occupational health and safety and construction safety regulations, including any WorkCover Authority requirements to prepare a health and safety plan. Site fencing must be installed sufficient to exclude the public from the site. Safety signs must be erected that; warn the public to keep out of the site, and provide a contact telephone number for enquiries. Further information and details regarding occupational health and safety requirements for construction sites can be obtained from the internet at
- (Reason: To ensure the health and safety of the community and workers on the site)
J12. Disturbed areas must be progressively stabilised and revegetated in accordance with a the approved landscape plan as soon as practical after construction..
- (Reason: To ensure that appropriate landscaping is undertaken within a reasonable timeframe in accordance with community expectations)
J13. An Occupation Certificate shall be obtained in relation to the approved works prior to any use or occupation of those parts of the building.
- (Reason: To ensure compliance with the provisions of the Environmental Planning and Assessment Act)
(Reason: To ensure public safety and amenity on public land)Prohibition on Use of Pavements
J14. Building materials shall not be placed on Council's footpaths, roadways, parks or grass verges and a suitable sign to this effect shall be erected adjacent to the street alignment.
(Reason: To ensure public safety and amenity on public land)Plant & Equipment Kept Within Site
J15. All plant and equipment used in the erection of the building, including concrete pumps, wagons, lifts, mobile cranes, etc, shall be situated within the boundaries of the site and so placed that all concrete slurry, water, debris and the like shall be discharged onto the building site, and is to be contained within the site boundaries..
Heritage consultant
J16. An appropriately heritagequalified heritage consultant must be appointed to consult with the builder engaged to ensure adequate drainage and damp proofing is provided to the existing dwelling and sandstone wall in the vicinity of the garage, and must attend on the site and be consulted during the damp proofing process.
(Reason: To ensure adequate drainage and damp proofing is provided to protect the heritage building and sandstone wall; appropriate drainage methodology)
Structural engineer
J17. An appropriately heritagequalified structural engineer must be appointed to consult with the builder engaged to ensure adequate structural support is provided to the existing dwelling in the vicinity of the garage, at such time as the excavation for the proposed garage takes place within 1 metre of the existing dwellings footing system.s.
(Reason: To protect the heritage building, which is located beneath the proposed garage.)
F. Operational Conditions imposed under EP&A Act and Regulations and other relevant Legislation
Building Code of Australia
F1. All building work must be carried out in accordance with the provisions of the Building Code of Australia.
- (Reason: Prescribed - Statutory)
Home Building Act
F2. (1) Building work that involves residential building work (within the meaning of the Home Building Act 1989) must not be carried out unless the Principal Certifying Authority for the development to which the work relates:
- (a) in the case of work to be done by a licensee under that Act:
- (i) has been informed in writing of the licensee’s name and contractor licence number, and
- (ii) is satisfied that the licensee has complied with the requirements of Part 6 of that Act, or
- (b) in the case of work to be done by any other person:
(i) has been informed in writing of the person’s name and owner-builder permit number, or
- (ii) has been given a declaration, signed by the owner of the land, that states that the reasonable market cost of the labour and materials involved in the work is less than the amount prescribed for the purposes of the definition of owner-builder work in section 29 of that Act, and is given appropriate information and declarations under paragraphs (a) and (b) whenever arrangements for the doing of the work are changed in such a manner as to render out of date any information or declaration previously given under either of those paragraphs.
- Note : The amount referred to in paragraph (b)(ii) is prescribed by regulations under the Home Building Act 1989. As at the date on which this Regulation was Gazetted, that amount was $3,000. As those regulations are amended from time to time, so that amount may vary.
(3) If arrangements for doing residential building work are changed while the work is in progress so that the information submitted to Council is out of date, further work must not be carried out unless the Principal Certifying Authority for the development to which the work relates (not being the Council), has given the Council written notice of the updated information.
(2) (2) A certificate purporting to be issued by an approved insurer under Part 6 of the Home Building Act 1989 that states that a person is the holder of an insurance policy issued for the purposes of that Part is, for the purposes of this clause, sufficient evidence that the person has complied with the requirements of that Part.
- (Reason: Prescribed - Statutory)
Excavation/Demolition
F3. (1) All excavations and backfilling associated with the erection or demolition of a building must be executed safely and in accordance with appropriate professional standards.
b. Demolition work must be undertaken in accordance with the provisions of AS2601- Demolition of Structures.a. (2) All excavations associated with the erection or demolition of a building must be properly guarded and protected to prevent them from being dangerous to life or property.
- (Reason: To ensure that work is undertaken in a professional and responsible manner and protect adjoining property and persons from potential damage)
F4. If the soil conditions require it:
- (a) retaining walls associated with the erection or demolition of a building or other approved methods of preventing movement of the soil must be provided, and
- (b) adequate provision must be made for drainage in accordance with the provisions of AS3500.3.2.
- (Reason: Prescribed -To ensure appropriate measures are in place to address site conditions and provide appropriate site drainage)
F5. (1) If an excavation associated with the erection or demolition of a building extends below the level of the base of the footings of a building on an adjoining allotment of land, the person causing the excavation to be made:-
- (a) must preserve and protect the building from damage;
- (b) if necessary, must underpin and support the adjoining building in an approved manner; and
- (c) must, at least 7 days before excavating below the level of the base of the footings of a building on an adjoining allotment of land, give notice of intention to do so to the owner of the adjoining allotment of land and furnish particulars of the excavation to the owner of the building being erected or demolished.
- (2) The owner of the adjoining allotment of land is not liable for any part of the cost of work carried out for the purposes of this clause, whether carried out on the allotment of land being excavated or on the adjoining allotment of land.
- (3) In this clause, allotment of land includes a public road and any other public place.
- (Reason: Prescribed - StatutoryTo ensure adjoining owner’s property rights are protected and protect adjoining properties from potential damage)
F6. (1) If the work involved in the erection or demolition of a building:-
(b) building involves the enclosure of a public place,(a) is likely to cause pedestrian or vehicular traffic in a public place to be obstructed or rendered inconvenient; or
- a hoarding or and site fencinge must be erected between the work site and the public place.
- (2) If necessary, an awning is to be erected, sufficient to prevent any substance from, or in connection with, the work falling into the public place.
- (3) The work site must be kept lit between sunset and sunrise if it is likely to be hazardous to persons in the public place.
(5) No access across public reserves or parks is permitted.
(4) Any such hoarding, fence or awning is to be removed when the work has been completed.
- NOTE : Prior to the erection of any temporary fence or hoarding over property owned or managed by Council, written approval must be obtained. Any application needs to be accompanied by plans indicating the type of hoarding and its layout.
- Fees are assessed and will form part of any approval given. These fees must be paid prior to the approval being given.
Approval for hoardings will generally only be given in association with approved building works, maintenance or to ensure protection of the public. An application form for a Hoarding Permit can be downloaded from Council’s website.
- (Reason: Prescribed - StatutoryTo ensure public safety and the proper management of public land)
F7. (1) A sign must be erected in a prominent position on any work site on which work involved in the erection or demolition of a building is being carried out:
- (a) stating that unauthorised entry to the work site is prohibited;, and
ii. showing the name, address and telephone number of the Principal Certifying Authority for the work.
i. (b) showing the name of the principal contractor )or person in charge of the work site), and a telephone number at which that person may be contacted at any time for business purposes and outside working hours; and.
(2) Any such sign is to be removed when the work has been completed.
(2) Any such sign must be maintained while to building work or demolition work is being carried out, but must be removed when the work has been completed.
- (3) This condition does not apply to :
- (a) building works being carried out inside an existing building., or
- (Reason: Statutory requirement)
F8. (1) Toilet facilities are to be provided, at or in the vicinity of the work site on which work involved in the erection or demolition of a building is being carried out, at the rate of one toilet for every 20 persons or part of 20 persons employed at the site.
- (2) Each toilet provided:
- (a) must be a standard flushing toilet, and
- (b) must be connected:
- (i) to a public sewer; or
- (ii) if connection to a public sewer is not practicable, to an accredited sewage management facility approved by the Council, or
- (iii) if connection to a public sewer or an accredited sewage management facility is not practicable, to some other sewage management facility approved by the Council.
(3) The provision of toilet facilities in accordance with this clause must be completed before any other work is commenced.
- (4) In this clause:
- accredited sewage management facility means a sewage management facility to which Division 4A of Part 3 of the Local Government (Approvals) Regulation 1993 applies, being a sewage management facility that is installed or constructed to a design or plan the subject of a certificate of accreditation referred to in clause 95B of the Regulation.
approved by the Council means the subject of an approval in force under Division 1 of Part 3 of the Local Government (Approvals) Regulation 1993.
- public sewer has the same meaning as it has in the Local Government (Approvals) Regulation 1993.
- sewage management facility has the same meaning as it has in the Local Government (Approvals) Regulation 1993.
- (Reason: Prescribed -To ensure adequate facilities are provided for workers on the site)
G. Conditions which Must be Complied With Prior to Issue of Occupation Certificate
Reinstatement
G1. All redundant lay-backs and vehicular crossings shall be reinstated to conventional kerb and gutter, foot-paving or grassed verge as appropriate. All costs shall be borne by the applicant, and works shall be completed prior to the issue of an Occupation Certificate.
- (Reason: To facilitate vehicular access to private sites, without disruption to pedestrian and vehicular traffic, and the preservation of on street parking spaces)
Certification- Civil Works
G2. (a) An appropriately qualified personappropriately qualified and practising Civil Engineer shall certify to the Principal Certifying Authority that the stormwater drainage system was constructed in accordance with the consent and the provisions of AS3500.3.2 The applicant shall, upon completion of the development works and prior to the final inspection/sissue of any Occupation Certificate, submit to Council a copy of the aforementioned letter of certification.
- (b) An appropriately qualified and practicing Civil Engineer appropriately qualified person shall certify to the Principal Certifying Authority that the vehicular crossing and associated works and road works were constructed in accordance with thise consent. The applicant shall, upon completion of the development works and prior to the final inspection/s, submit to Council a copy of the aforementioned letter of certification.
- (Reason: Compliance with the Consent)
G3. The applicant shall, upon completion of the development works, submit to Council the works-as-executed drawing (W.A.E.) and letter of certificationCompliance Certificate certifying compliance with the requirements of AS3500.3.2 and this consent, prepared by an appropriately qualified and practising Civil Engineer, prior to occupancythe issuing of any Occupation Certificate. The W.A.E. drawing shall show the alignment, depth and grade of the stormwater drainage pipelines, easement and associated structures.
- (Reason: Compliance with the Consent)
(Reason: To ensure adjoining owner’s property rights are protected)Damage to Adjoining Properties
G4. All precautions must be taken to prevent any damage likely to be sustained to adjoining properties. Adjoining owner property rights and the need for owner’s permission must be observed at all times, including the entering onto land for the purpose of undertaking works. Where damage occurs to adjoining property all necessary repair or suitable agreement for necessary repairs are to be undertaken by the applicant in consultation with and with the consent of the affected property owner prior to the occupation of the development or issue of a buildingan Occupation Ccertificate.
(Reason: To ensure compliance with the terms of this consent)Utility Services
G5. All utility services shall be adjusted, to the correct levels and/or location/s required by this consent, prior to final completion and the issue of any occupation certificate.
__________________
K G Hoffman
Commissioner of the Court
rjs
0
0
2