Stockland v Sunshine Coast Regional Council

Link copied
Case Copied 78 min read

PLANNING & ENVIRONMENT COURT
OF QUEENSLAND

CITATION:

Stockland v Sunshine Coast Regional Council & Ors [2013] QPEC 79

PARTIES:

STOCKLAND DEVELOPMENT PTY LTD

(appellant)

v

SUNSHINE COAST REGIONAL COUNCIL

(respondent)

and

CHIEF EXECUTIVE, DEPARTMENT OF TRANSPORT AND MAIN ROADS

(first co-respondent)

and

CHIEF EXECUTIVE, DEPARTMENT OF ENVIRONMENT AND RESOURCE MANAGEMENT

(second co-respondent)

and

MARK PERISSINOTTO

(third co-respondent)

and

THERESE LUCAS

(fourth co-respondent)

and

DEVELOPMENT WATCH INC

(fifth co-respondent)

and

TWIN WATERS RESIDENTS ASSOCIATION INC

(sixth co-respondent)

FILE NO/S:

2282/09

DIVISION:

Planning and Environment

PROCEEDING:

Appeal

ORIGINATING COURT:

Brisbane

DELIVERED ON:

13 December  2013

DELIVERED AT:

Brisbane

HEARING DATE:

11 February 2013 to 6 March 2013, further evidence received on 28 November 2013 and on 11 December 2013 and further submissions received on 11 December 2013

JUDGE:

Rackemann DCJ

ORDER:

The appeal is dismissed

CATCHWORDS:

Planning and Environment – Applicant appeal – Application for preliminary approval overriding the planning scheme – Proposed urban residential development for approximately 950 lots on disused sugarcane farming land – Where site within the urban footprint pursuant to the regional plan but not planned for urban expansion under either the existing or draft planning schemes – Whether planning scheme overtaken by events – Flooding – Good quality agricultural land – Visual amenity and character – Town planning and community need – Public benefit – Sufficiency or otherwise of grounds to approve notwithstanding conflict

COUNSEL:

DR Gore QC, BD Job and JG Lyons for the appellant

CL Hughes SC and MA Williamson for the respondent

SOLICITORS:

Clayton Utz for the appellant

Sunshine Coast Regional Council Legal Services for the respondent

Table of contents

Table of contents
The parties
The site and locality
The proposal
The public submissions
The issues
The assessment criteria
The planning documents

(i) Maroochy Plan 2000
(ii) The SEQRP
(iii)  The Draft Planning Scheme
(iii)  State Planning Policies

Flooding
GQAL, the Mill closure, agricultural utility otherwise and proximity to residential development
Visual Amenity and Landscape Character

Need

Benefit
Sufficiency of Grounds

Conclusion

The parties

  1. The appellant is the owner of ten contiguous allotments, with an area of approximately 103ha, located north of the Maroochy River and east of the Sunshine Motorway. Its appeal is against the respondent’s refusal of its development application for a preliminary approval overriding the planning scheme. If granted, the approval would facilitate the development of the site for urban residential purposes.

  1. The first and second co-respondents by election were among the relevant referral agencies. Neither took an active part in the hearing. Indeed proposed conditions of any approval have been agreed to the satisfaction of all referral agencies. The other co-respondents were adverse submitters in respect of the development application, but also took no active part in the hearing.

The site and locality

  1. The site is a mostly cleared and entirely disused former sugar cane farm. There are areas of remnant vegetation towards its centre and at its south-eastern corner.  The land has not been cultivated since approximately 2003, when the Moreton Sugar Mill closed. For the past five years…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Stockland v Sunshine Coast Regional Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] QPEC 79
Decision Date

CaseChat Overview and Summary

In the case of Stockland v Sunshine Coast Regional Council, the applicant, Stockland, sought preliminary approval to develop a residential estate comprising approximately 950 lots on land previously used for sugarcane farming. The land in question is situated within the urban footprint as defined in the regional plan but was not earmarked for urban expansion under either the existing or draft planning schemes. The Sunshine Coast Regional Council refused the application, leading Stockland to appeal to the court. The court was tasked with determining whether the planning scheme had been rendered obsolete by intervening events, such as flooding, and whether the development would result in a public benefit despite the land being considered good quality agricultural land. Additionally, the court had to consider the visual amenity and character of the area, as well as the broader town planning and community needs.

The court examined the statutory criteria for granting planning permission, including the need to ensure that planning schemes are responsive to changing circumstances and the necessity to balance development with the preservation of agricultural land. The court assessed whether the proposed development would create a public benefit, despite its conflict with existing planning provisions. The court also evaluated the visual impact of the development on the surrounding area and its potential to preserve the character of the region. After a thorough analysis, the court concluded that the planning scheme had not been overtaken by events and that the proposed development did not sufficiently justify approval in light of the statutory criteria.

The court found that while the land was within the urban footprint, it had not been designated for urban expansion in the existing or draft planning schemes. The court determined that the applicant had not provided sufficient grounds to warrant approval, particularly given the conflict with the planning scheme and the potential impact on the agricultural land. The visual amenity and character of the area, as well as the broader town planning and community needs, were not sufficiently addressed by the proposed development. Consequently, the appeal was dismissed, and the decision of the Sunshine Coast Regional Council was upheld.

Orders

Orders of the court

The appeal is dismissed

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established