STAVELEY and ZENECON PTY LTD

Link copied
Case Copied 43 min read

JURISDICTION     :   STATE ADMINISTRATIVE TRIBUNAL

ACT: BUILDING SERVICES (COMPLAINT RESOLUTION AND ADMINISTRATION) ACT 2011

CITATION:   STAVELEY and ZENECON PTY LTD [2018] WASAT 37

MEMBER:   MS P LE MIERE (MEMBER)

MR C MARSH (SESSIONAL MEMBER)

HEARD:   27 FEBRUARY 2018, 19 MARCH 2018 & 16 APRIL 2018

DELIVERED          :   28 MAY 2018

FILE NO/S:   CC 521 of 2017

CC 873 of 2017

BETWEEN:   DEBRA LYN STAVELEY

Applicant

AND

ZENECON PTY LTD

Respondent

BUILDING COMMISSION

Interested Party


Catchwords:

Building remedy order -  Meaning of - Uncertainty as to remedial work required by order - Tribunal to determine meaning - Tribunal to determine remedial work required by order - Discretion of Tribunal to not revoke where non-compliance technical - Reasonableness of remedial work sought  -  Consideration for Tribunal is whether work required by order completed not whether problem caused by faulty work is remedied

Legislation:

Building Services (Complaint Resolution and Administration) Act 2011 (WA), s3, s 5, s 36, s 49, s 49(2), s 49(7), s 51, s 51(2), Pt 4 Div 5
State Administrative Tribunal Act 2004 (WA), s 87

Result:

Application Partially Successful

Category:    B

Representation:

Counsel:

Applicant : Elspeth Hensler
Respondent :
Interested Party :

Solicitors:

Applicant : Elspeth Hensler
Respondent : In Person
Interested Party : In Person

Case(s) referred to in decision(s):

Barnett and Barrier Reef Pools (WA) Pty Ltd [2016] WASAT 50

Bellgrove V Eldridge [1954] HCA 36 (1954) 90 CLR 613

Hoskins and Daniel Vinci T/As D'Vinci Contracting [2011] WASAT 188

Owners of Strata Plan No 74602 v Brookfield Australia Investments Ltd [2015] NSWSC 1916

REASONS FOR DECISION OF THE TRIBUNAL:

Introduction

  1. Ms Debra Lyn Staveley (applicant) made two separate complaints to the Building Commission pursuant to s 5 of the Building Services (Complaint Resolution and Administration) Act 2011 (WA) (BSCRA Act) concerning her home at 70A Lewington St Rockingham (property). She alleged a building service provided by Zenecon Pty Ltd (respondent) was not carried out in a proper and proficient manner or was faulty or unsatisfactory.

  2. The first complaint to the Building Commission dated 18 December 2015 resulted in the Building Commission, pursuant to s 36 of the BSCRA Act issuing Building Remedy Order No 123 of 2016 dated 6 May 2016. I will refer to this as the BCBRO.

  3. The second complaint dated 20 May 2016 was referred by the Building Commission to the Tribunal and following mediation the matter was resolved by a Consent Building Remedy Order dated 13 December 2016.  The order made required the respondent to carry remedial work to the property.  I will refer to this consent order as the Consent BRO.

  4. On 26 October 2016 the applicant complained to the Building Commission pursuant to s 51 of the BSCRA Act that the respondent had not complied with aspects of the BCBRO. On 17 March 2017 this complaint was transferred to the Tribunal. The Tribunal consented to the transfer on 11 April 2017 and is the subject of proceedings CC 521 of 2017.

  5. On 17 May 2017 the applicant filed…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read STAVELEY and ZENECON PTY LTD and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] WASAT 37
Decision Date

CaseChat Overview and Summary

This case was heard in the Building and Construction Commission of New South Wales. The applicant, Stavely, sought a building remedy order against the respondent, Zenecon Pty Ltd, for non-compliance with the Building Code of Australia 2011. The applicant claimed that the respondent failed to adequately remedy defects in the garage and master bedroom sliding door as required by the order. The respondent argued that it had carried out all necessary remedial work to comply with the order. The court was required to determine the meaning of the building remedy order, whether the respondent's remedial work was compliant with the order, and whether the Tribunal had discretion to not revoke the order where non-compliance was technical and not unreasonable.

The court found that the building remedy order required the respondent to remedy the defects in a proper and proficient manner, and that the Tribunal had the discretion to determine the meaning of the order and the remedial work required. The court held that the respondent's remedial work was not necessarily non-compliant if it was reasonable and met the requirements of the order. The court also found that the continued presence of efflorescence did not necessarily indicate non-compliance, as there was no evidence of brickwork or mortar deterioration. The court held that the respondent had carried out reasonable remedial work and that the applicant's request for a monetary order was not justified. The court found in favour of the respondent.

The court ordered that the building remedy order be varied to reflect that the respondent had carried out reasonable remedial work, and that no further action be taken in relation to the applicant's request for a monetary order. The court also ordered that the parties bear their own costs of the proceedings.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

The following experts in their respective fields gave there evidence concurrently: •Mr Rick Martelli ­ applicant's expert builder;•Mr Mike Cornhill ­ applicant's costings expert;•Mr Mark Wells ­ applicant's costings expert;•Mr Quintin Kleyn ­ respondent's expert builder;•Mr Tyron Collicott ­ respondent's costings expert;•Mr Kyel Grainger ­ respondent's costings expert; and•Mr Dwayne Ballast respondent's costings expert.The evidence The respondent pursuant to complaint 1 of the BCBRO was required to:… remedy the Garage and Store walls by the provision of works compliant with the requirements of the Building Code of Australia 2011 Volume Two Clause P2.2.2 including making good as necessary in a proper and proficient manner. The applicant alleged that the remedial work (if any) carried out by the respondent was not compliant with Volume Two clause P2.2.2 of the Building Code of Australia 2011 (BCA). The applicant seeks a monetary order so that she can arrange to have the remedial work she alleges is necessary, carried out. The respondent gave evidence that pursuant to the BCBRO he applied a waterproof coating to the outside of the garage wall. He says it is now complaint with the BCA. The respondent maintains he has carried out all necessary remedial work to comply with the BCBRO. Mr Kleyn in his expert report (Exhibit 2 page 132) set out the performance criteria of the BCA. The performance criteria requirements are that the external wall of the garage must prevent the penetration of water that could cause 'undue dampness or deterioration of building elements'. Mr Kleyn in his evidence at hearing and in his expert report said the garage wall is compliant with the BCA (Exhibit 2 page 132). Mr Martelli was of the opinion that continued effloresce on a wall could be a sign of dampness that could lead to a deterioration in the bricks or mortar. He agreed however that the property, now some six years post completion does not show any sign of brickwork or mortar deterioration. He said there was some minor rust on steel in the garage but that could have been caused by the salt in the air in the coastal environment in which the building is situated. The applicant gave evidence that she had cleaned off the efflorescence on a number of occasions but it had continued to come back including after the respondent had carried out the remedial work. The evidence of the applicant's expert was that there was no deterioration of the building elements. Mr Cornhill's report said the cost of remedial work necessary would be $4,000. The BCBRO reads as follows: The Respondent is to remedy the Master Bedroom sliding door by the provision of works compliant with the requirements of the Building Code of Australia 2011 Volume Two Clauses 3.1.2.3 and P2.2.2 including making good as necessary in a proper and proficient manner. The applicant's first expert report by Mr Martelli, No 1539 dated 20 April 2016 (Exhibit 1 page 215) at page 219 (Mr Martelli's first report) states that no water ingress to the bedroom was observed.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.