States Grants (Technical and Further Education Assistance) Amendment Act 1977 (Cth)
STATES GRANTS (TECHNICAL AND FURTHER EDUCATION ASSISTANCE) AMENDMENT ACT 1977
An Act to
amend the
BE IT ENACTED by the Queen, and the Senate and House of Representatives of the Commonwealth of Australia, as follows:—
PART I—PRELIMINARY
PART II—AMENDMENTS OF THE STATES GRANTS (TECHNICAL AND FURTHER EDUCATION) ACT 1974
SCHEDULE 1 Section 6
CAPITAL GRANTS FOR MAJOR BUILDING PROJECTS
Column 1 | Column 2 | |
Name of State | Maximum grant | |
$ | ||
New South Wales.............................................................................................................. | 13,994,000 | |
Victoria............................................................................................................................. | 10,548,000 | |
Queensland....................................................................................................................... | 5,029,000 | |
South Australia................................................................................................................. | 3,495,000 | |
Western Australia.............................................................................................................. | 3,193,000 | |
Tasmania.......................................................................................................................... | 1,284,000 | |
| 37,543,000 | |
SCHEDULE 2 Section 8
CAPITAL GRANTS FOR MINOR BUILDING PROJECTS AND EQUIPMENT
Column 1 | Column 2 |
Name of State | Maximum grant |
$ | |
New South Wales.............................................................................................................. | 5,013,500 |
Victoria............................................................................................................................. | 4,188,000 |
Queensland....................................................................................................................... | 1,892,500 |
South Australia................................................................................................................. | 1,844,000 |
Western Australia.............................................................................................................. | 1,915,500 |
Tasmania.......................................................................................................................... | 1,101,500 |
| 15,955,000 |
SCHEDULE 3 Section 12
GENERAL PURPOSE RECURRENT GRANTS
Column 1 | Column 2 | Column 3 | Column 4 |
Name of State | Year commencing 1 July 1974 Amount of Grant | Year commencing 1 July 1975 Amount of Grant | Six months commencing 1 July 1976 Amount of Grant |
$ | $ | $ | |
New South Wales............................................................... | 9,604,500 | 13,163,000 | 2,311,000 |
Victoria.............................................................................. | 5,311,000 | 7,399,000 | 3,654,000 |
Queensland......................................................................... | 1,860,500 | 2,677,500 | 979,000 |
South Australia................................................................... | 2,054,000 | 2,836,500 | 1,247,000 |
Western Australia............................................................... | 1,740,000 | 2,417,500 | 537,000 |
Tasmania............................................................................ | 370,000 | 633,500 | 205,000 |
SCHEDULE 4 Section 15
PARTICULAR PURPOSE RECURRENT GRANTS
Column 1 | Column 2 | Column 3 | Column 4 |
Name of State | Year commencing 1 July 1974 Amount of Grant | Year commencing 1 July 1975 Amount of Grant | Six months commencing 1 July 1976 Amount of Grant |
$ | $ | $ | |
New South Wales............................................................... | 641,000 | 3,329,000 | 1,136,000 |
Victoria.............................................................................. | 1,149,000 | 1,904,500 | 883,500 |
Queensland......................................................................... | 290,700 | 1,567,300 | 533,500 |
South Australia................................................................... | 382,000 | 630,000 | 292,500 |
Western Australia............................................................... | 250,000 | 650,500 | 257,000 |
Tasmania............................................................................ | 13,450 | 351,550 | 128,500 |
SCHEDULE 5 Section 18
GRANTS FOR IN-SERVICE TEACHER TRAINING PROGRAMS
Column 1 | Column 2 | Column 3 | Column 4 |
Name of State | Year commencing 1 July 1974 Amount of Grant | Year commencing 1 July 1975 Amount of Grant | Six months commencing 1 July 1976 Amount of Grant |
$ | $ | $ | |
New South Wales............................................................... | 35,000 | 949,000 | 357,500 |
Victoria.............................................................................. | 133,000 | 283,000 | 154,000 |
Queensland......................................................................... | 100,000 | 212,500 | 115,500 |
South Australia................................................................... | 117,000 | 247,000 | 134,000 |
Western Australia............................................................... | 110,000 | 233,500 | 127,000 |
Tasmania............................................................................ | 22,500 | 71,500 | 34,500 |
SCHEDULE 6 Section 20
SPECIAL PROJECT RECURRENT GRANTS
Column 1 | Column 2 | Column 3 | Column 4 | Column 5 | Column 6 | Column 7 |
Name of State | Year Commencing 1 July 1974 Maximum Grant | Year Commencing 1 July 1975 Maximum Grant | Year Commencing 1 July 1974 Maximum Grant | Year Commencing 1 July 1975 Maximum Grant | Year Commencing 1 July 1974 Maximum Grant | Year Commencing 1 July 1975 Maximum Grant |
$ | $ | $ | $ | $ | $ | |
New South Wales... | 20,000 | 160,000 | 2,000 | 23,000 | 4,000 | 16,000 |
Victoria.................. | 58,000 | 77,000 | 9,000 | 16,000 | 6,000 | 14,000 |
Queensland............ | Nil | 130,000 | Nil | 25,000 | Nil | 15,000 |
South Australia....... | 24,000 | 31,000 | 8,000 | 17,000 | 5,000 | 10,000 |
Western Australia... | 19,000 | 26,000 | 8,000 | 17,000 | 5,000 | 10,000 |
Tasmania............... | 2,000 | 13,000 | Nil | Nil | 1,000 | 9,000 |
SCHEDULE 6—continued
Column 8 | Column 9 | Column 10 | Column 11 | Column 12 | ||||
Year Commencing 1 July 1974 Maximum Grant | Year Commencing 1 July 1975 Maximum Grant | Six months Commencing 1 July 1976 Maximum Grant | Six months Commencing 1 July 1976 Maximum Grant | Six months Commencing 1 July 1976 Maximum Grant | ||||
$ | $ | $ | $ | $ | ||||
New South Wales.......................... | 15,000 | 375,000 | 51,500 | 8,000 | 113,000 | |||
Victoria......................................... | 117,000 | 163,000 | 38,500 | 8,000 | 81,500 | |||
Queensland................................... | Nil | 150,000 | 37,000 | 8,500 | 43,500 | |||
South Australia............................. | 38,000 | 52,000 | 15,500 | 8,500 | 26,000 | |||
Western Australia.......................... | 25,000 | 35,000 | 13,000 | 8,500 | 17,500 | |||
Tasmania...................................... | 7,500 | 22,500 | 4,500 | 33,500 | 8,500 | |||
PART III—AMENDMENTS OF STATES GRANTS (TECHNICAL AND FURTHER EDUCATION ASSISTANCE) ACT 1976
SCHEDULE 1 Section 6(1)
CAPITAL GRANTS FOR MAJOR BUILDING PROJECTS
Column 1 | Column 2 | Column 3 |
Institutions providing Technical and Further Education | Projects | Maximum grants in respect of 1977 |
$ | ||
New South Wales— | ||
| Completion of teaching blocks for commercial courses at an estimated cost of $104,000.......................... | 104,000 |
| Completion of teaching blocks for engineering trades at new college at an estimated cost of $1,920,000.. | 1,920,000 |
SCHEDULE 1—continued
Column 1 | Column 2 | Column 3 |
Institutions providing Technical and Further Education | Projects | Maximum grants in respect of 1977 |
$ | ||
| Completion of arts and science buildings at an estimated cost of $571,000.............................................. | 571,000 |
| Completion of School of Hotel and Catering Administration at an estimated cost of $8,200,000 | 4,100,000 |
| Construction of building for metal fabrication and building trades at an estimated cost of $3,530,000 | 1,349,000 |
| Construction of buildings for engineering trades at new college at an estimated cost of $7,470,000......... | 2,232,000 |
| Alterations to existing buildings at an estimated cost of $1,140,000...................................................... | 571,000 |
| Construction of new centre for technical and further education activities at an estimated cost of $311,000 | 311,000 |
| Construction of new centre for technical and further education activities at an estimated cost of $363,000 | 363,000 |
| Purchase of property for extensions to college at an estimated cost of $312,000............................... | 312,000 |
Total......................................... | 11,833,000 | |
Victoria— | ||
|
| 311,000 |
|
| 3,010,000 |
|
| 2,284,000 |
|
| 1,661,000 |
|
| 623,000 |
|
| 727,000 |
|
| 830,000 |
| 9,446,000 | |
Queensland— | ||
|
| 1,661,000 |
SCHEDULE 1—continued
Column 1 | Column 2 | Column 3 |
Institutions providing Technical and Further Education | Projects | Maximum grants in respect of 1977 |
$ | ||
|
| 2,076,000 |
|
| 727,000 |
|
| 259,000 |
|
| 311,000 |
|
| 363,000 |
| 5,397,000 | |
South Australia— | ||
|
| 3,270,000 |
|
| 52,000 |
| 3,322,000 | |
Western Australia— | ||
|
| 2,595,000 |
|
| 311,000 |
| 2,906,000 | |
Tasmania— | ||
|
| 1,038,000 |
| 1,038,000 | |
| 33,942,000 |
SCHEDULE 2 Section 7(3)
CAPITAL GRANTS FOR MINOR BUILDING PROJECTS AND EQUIPMENT
Column 1 | Column 2 |
Name of State | Maximum grant |
$ | |
New South Wales.......................................................................................................... | 1,794,000 |
Victoria......................................................................................................................... | 1,801,000 |
SCHEDULE 2—continued
Column 1 | Column 2 |
Name of State | Maximum grant |
$ | |
Queensland.................................................................................................................... | 224,000 |
South Australia.............................................................................................................. | 332,000 |
Western Australia.......................................................................................................... | 453,000 |
Tasmania....................................................................................................................... | 232,000 |
| 4,836,000 |
SCHEDULE 3 Section 8(1)
GENERAL PURPOSE RECURRENT GRANTS
Column 1 | Column 2 |
Name of State | Maximum grant |
$ | |
New South Wales.......................................................................................................... | 11,870,000 |
Victoria......................................................................................................................... | 7,634,000 |
Queensland.................................................................................................................... | 2,467,000 |
South Australia.............................................................................................................. | 2,828,000 |
Western Australia.......................................................................................................... | 2,643,000 |
Tasmania....................................................................................................................... | 586,000 |
| 28,028,000 |
SCHEDULE 4 Section 9(3)
SPECIAL PURPOSE RECURRENT GRANTS
Column 1 | Column 2 | Column 3 | Column 4 |
Name of State | Maximum grant | Maximum grant | Aggregate amount |
$ | $ | $ | |
New South Wales................................................................. | 783,000 | 113,000 | 896,000 |
Victoria................................................................................ | 340,000 | 227,000 | 567,000 |
Queensland.......................................................................... | 341,000 | 113,000 | 454,000 |
South Australia.................................................................... | 267,000 | 72,000 | 339,000 |
Western Australia................................................................. | 267,000 | 72,000 | 339,000 |
Tasmania............................................................................. | 82,000 | 31,000 | 113,000 |
| 2,080,000 | 628,000 | 2,708,000 |
SCHEDULE 5 Section 10(3)
PARTICULAR PURPOSE RECURRENT GRANTS
Column 1 | Column 2 |
Name of State | Maximum grant |
$ | |
New South Wales............................................................................................................. | 4,584,000 |
Victoria........................................................................................................................... | 3,524,000 |
SCHEDULE 5—continued
Column 1 | Column 2 |
Name of State | Maximum grant |
$ | |
Queensland...................................................................................................................... | 1,434,000 |
South Australia................................................................................................................ | 1,152,000 |
Western Australia............................................................................................................. | 1,079,000 |
Tasmania......................................................................................................................... | 339,000 |
| 12,112,000 |
SCHEDULE 6 Section 12(3)
GRANTS FOR ADULT EDUCATION
Column 1 | Column 2 |
Name of State | Maximum grant |
$ | |
New South Wales............................................................................................................. | 78,000 |
Victoria........................................................................................................................... | 55,000 |
Queensland...................................................................................................................... | 34,000 |
South Australia................................................................................................................ | 23,000 |
Western Australia............................................................................................................. | 23,000 |
Tasmania......................................................................................................................... | 11,000 |
| 224,000 |
0
0
0