State Environmental Planning Policy (Miscellaneous Consent Provisions) 2007 (NSW)
This Policy is State Environmental Planning Policy (Miscellaneous Consent Provisions) 2007.
This Policy commences on 26 October 2007.
The aims of this Policy are as follows:
(a) to provide that the erection of temporary structures is permissible with consent across the State,
(b) to ensure that suitable provision is made for ensuring the safety of persons using temporary structures,
(c) to encourage the protection of the environment at the location, and in the vicinity, of temporary structures by specifying relevant matters for consideration,
(d) to provide that development comprising the subdivision of land, the erection of a building or the demolition of a building, to the extent to which it does not already require development consent under another environmental planning instrument, cannot be carried out except with development consent.
This Policy applies to the State.
A word or expression used in this Policy has the same meaning as it has in the standard instrument prescribed by the Standard Instrument (Local Environmental Plans) Order 2006 unless it is otherwise defined in this Policy.
In this Policy:
(Repealed)
Notes in this Policy are provided for guidance and do not form part of this Policy.
The consent authority for development that may be carried out with consent under this Policy is:
(a) except as provided by paragraph (b), the council of the area in which the development is proposed to be carried out, or
(b) any public authority that under another environmental planning instrument has the function of determining development applications for that kind of development on the land on which it is proposed to be carried out.
Subject to section 74 (1) of the Act, in the event of an inconsistency between this Policy and another environmental planning instrument, whether made before or after the commencement of this Policy, this Policy prevails to the extent of the inconsistency.
(Repealed)
Development comprising the erection of a temporary structure may be carried out only with development consent, except as otherwise provided by any other environmental planning instrument that specifies that development as exempt or complying development.
Subclause (1) does not apply to development comprising the erection of a temporary structure that is exempt development or complying development, or is prohibited, under another environmental planning instrument.
For the purposes of subclause (2), the existing provisions of an environmental planning instrument are taken to prohibit development comprising the erection of a temporary structure only if, in doing so, temporary structures or a relevant class of temporary structures are expressly referred to.
In this clause:
(a) as in force immediately before 26 October 2007, or
(b) as amended on or after 26 October 2007, but before 26 October 2008, by some other environmental planning instrument that, immediately before 26 October 2007, was the subject of:
(i) a decision under section 3.32 of the Act, or
(ii) a direction under section 3.33 of the Act to make such a decision, or
(c) as inserted in the environmental planning instrument on or after 26 October 2007, but before 26 October 2008, by some other environmental planning instrument that, immediately before 26 October 2007, was the subject of:
(i) a decision under section 3.32 of the Act, or
(ii) a direction under section 3.33 of the Act to make such a decision.
Before granting consent to the erection of a temporary structure, the consent authority must consider the following matters:
(a) whether the number of persons who may use the structure at any one time should be limited,
(b) any adverse impact on persons in the vicinity of any noise likely to be caused by the proposed erection or use of the structure and any proposed measures for limiting the impact,
(c) whether the hours during which the structure is used should be limited,
(d) any parking or traffic impacts likely to be caused by the erection of the structure or its proposed use,
(e) the principles for minimising crime risk set out in Part B of the Crime Prevention Guidelines,
(f) whether the proposed location of the structure is satisfactory in terms of the following:
(i) the proposed distance of the structure from public roads and property boundaries,
(ii) the location of underground or overhead utilities,
(iii) vehicular and pedestrian access,
(g) whether it is necessary to provide toilets and washbasins in association with the use of the structure,
(h) whether the structure is proposed to be erected on land that comprises, or on which there is:
(i) an item of environmental heritage that is listed on the State Heritage Register, or that is subject to an interim heritage order, under the Heritage Act 1977, or
(ii) a place, building, work, tree, relic or Aboriginal object that is described as an item of environmental heritage or as a heritage item in another environmental planning instrument, or
(iii) land identified as a heritage conservation area, an archaeological site or a place of Aboriginal heritage significance in another environmental planning instrument,
(i) the duration for which the structure should be permitted to remain on the land concerned,
(j) whether any conditions should be imposed on the granting of consent in relation to the dismantling or removal of the structure in view of any safety issues.
Certain development under this Part may be exempt or complying development under another environmental planning instrument, for example, State Environmental Planning Policy (Exempt and Complying Development Codes) 2008.
This Part applies to land other than land to which a standard plan applies.
In this clause,
A person may subdivide land to which this Part applies, but only with development consent.
Development consent must not be granted for the subdivision of land on which a secondary dwelling is situated that would result in the secondary dwelling being on a different lot of land to the principal dwelling unless each proposed lot on which those dwellings would be situated would comply with the minimum lot size (if any) required by an environmental planning instrument applying to the land.
The standard instrument prescribed by the Standard Instrument (Local Environmental Plans) Order 2006 contains the following definitions of
(a) is established in conjunction with another dwelling (the
principal dwelling ), and(b) is on the same lot of land as the principal dwelling, and
(c) is located within, or is attached to, or is separate from, the principal dwelling.
A person may demolish a building or work on land to which this Part applies, but only with development consent.
A person may, only with development consent, change the use of a building on land to which this Part applies within a business zone:
(a) that is being lawfully used for a particular kind of office or business premises to another kind of office or business premises or to a shop, or
(b) that is being lawfully used for a particular kind of shop (other than a neighbourhood shop) to another kind of shop or to an office or business premises,
even though the proposed change of use is prohibited in that zone under another environmental planning instrument.
The consent authority must not grant development consent as referred to in this clause unless satisfied that the proposed change of use will not have more than a minor environmental effect and is in keeping with the objectives (if any) of the zone in which the relevant land is situated.
The consent authority must not grant development consent as referred to in this clause to the change of use of a building if it would result in the change of classification of the building under the Building Code of Australia.
The consent authority must not grant development consent as referred to in this clause to the change of use of a building for the purposes of sex services premises.
In this clause,
This clause applies to a fire alarm system that can be monitored by Fire and Rescue NSW or by a private service provider.
The following development may be carried out, but only with development consent:
(a) the conversion of a fire alarm system from connection with the fire alarm monitoring network of Fire and Rescue NSW to connection with the fire alarm monitoring network of a private service provider,
(b) the conversion of a fire alarm system from connection with the fire alarm monitoring network of a private service provider to the fire alarm monitoring network of another private service provider,
(c) the conversion of a fire alarm communication link from a connection with the fire alarm monitoring network of a private service provider to another fire alarm monitoring network of another private service provider.
In this clause: