State Environmental Planning Policy (Mining, Petroleum Production and Extractive Industries) Amendment 2019 (2019-438) LW 30 August 2019 (NSW)
| New South Wales |
State Environmental Planning Policy (Mining,
Petroleum Production and Extractive
Industries) Amendment 2019
under the
Environmental Planning and Assessment Act 1979
Her Excellency the Governor, with the advice of the Executive Council, has made the following State environmental planning policy under the Environmental Planning and Assessment Act 1979.
ROBERT STOKES, MP
Minister for Planning and Public Spaces
State Environmental Planning Policy (Mining, Petroleum Production and Extractive Industries) Amendment
2019 [NSW]
State Environmental Planning Policy (Mining, Petroleum
Production and Extractive Industries) Amendment 2019
under the
Environmental Planning and Assessment Act 1979
1 Name of Policy
This Policy is State Environmental Planning Policy (Mining, Petroleum Production
and Extractive Industries) Amendment 2019.
2 Commencement
This Policy commences on the day on which it is published on the NSW legislation website.
3 Repeal of Policy
|
State Environmental Planning Policy (Mining, Petroleum Production and Extractive Industries) Amendment
2019 [NSW]
Schedule 1 Amendment of State Environmental Planning Policy (Mining, Petroleum Production and
Extractive Industries) 2007
| Schedule 1 | Amendment of State Environmental Planning |
| Policy (Mining, Petroleum Production and | |
| Extractive Industries) 2007 |
[1] Clause 17K
Omit the clause. Insert instead—
|
A gateway certificate remains current until—
| (a) | the day that is 5 years after the day on which the certificate was issued (or an earlier day specified in the certificate), or |
| (b) | if the certificate accompanies a development application made in respect of a proposed mining or petroleum development—that application is finally determined. |
[2] Clause 24
Insert after clause 23—
|
| (1) | Clause 17K, as substituted by the amending SEPP, extends to a gateway certificate that was current immediately before that substitution. |
| (2) | A gateway certificate that accompanied a development application made before the substitution of clause 17K by the amending SEPP and ceased to be current before the application was finally determined is taken to be a current gateway certificate until that application is finally determined. |
| (3) | In this clause— |
| amending SEPP means the State Environmental Planning Policy (Mining, Petroleum Production and Extractive Industries) Amendment 2019. |
[3] Schedule 1 Prohibited development
Insert at the end of Schedule 1—
Open cut mining within the area identified as “Land where open-cut mining is prohibited” on the map named State Environmental Planning Policy (Mining, Petroleum Production and Extractive Industries) 2007