Starline Interiors Pty Ltd v Tomkins Commercial and Industrial Builders Pty Ltd

Link copied
Case Copied 34 min read

DISTRICT COURT OF QUEENSLAND

CITATION:

Starline Interiors Pty Ltd v Tomkins Commercial and Industrial Builders Pty Ltd [2025] QDC 63

PARTIES:

STARLINE INTERIORS PTY LTD
(ACN 617887297)

(applicant)

v
TOMKINS COMMERCIAL AND INDUSTRIAL BUILDERS PTY LTD
(ACN 061732778)

(respondent)

FILE NO/S:

BD372/25

DIVISION:

Civil

PROCEEDING:

Application

ORIGINATING COURT:

District Court Brisbane

DELIVERED ON:

11 April 2025

DELIVERED AT:

Brisbane

HEARING DATE:

4 April 2025

JUDGES:

Kent KC DCJ

ORDER:

1.    The Respondent pay the Applicant $191,287.70 inclusive of (a) GST and (b) $14,212.75 on account of interest to and including 10 April 2025.

2.    The Respondent’s cross application is dismissed.

3.    The Respondent pay the Applicant’s costs of both proceedings as agreed or assessed.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – RENUMERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – PAYMENT CLAIMS – where the applicant entered into a subcontract with the respondent for the applicant to install plasterboard walls and ceilings, supply and install fire rated walling systems and undertake carpentry work – where the applicant issued a payment claim under the Building Industry Fairness (Security of Payment) Act 2017 (Qld) – where the respondent issued a payment schedule in response – where the respondent partially paid the applicant in respect of the payment schedule – whether the payment claim is defective under the requirements of s 68 of the Act – where the respondent argues that the notice of intention to start proceedings is deficient under s 99 of the Act – where the applicant argues that the payment schedule falls within the meaning of ‘certificate’ under the subcontract – where the respondent seeks to set off monies owed under the subcontract – where the respondent applies for injunctive relief or stay – whether injunctive relief is justified

Acts Interpretation Act 1954 (Qld), s 48A
Building Industry Fairness (Security of Payment) Act 2017 (Qld), ss 3, 68, 76, 77, 78, 99, 100
District Court of Queensland Act 1967 (Qld), ss 68, 69
Uniform Civil Procedure Rules 1999 (Qld), r 800

Iris Broadbeach Business Pty Ltd (as trustee for Iris Broadbeach Business Trust) v Descon Group Australia Pty Ltd [2024] QSC 16
Iris Broadbeach Business Pty Ltd v Descon Group Australia Pty Ltd & Anor [2023] QSC 290
KDV Sport Pty Ltd v Muggeridge Constructions Pty Ltd [2019] QSC 178
Minimax Fire Fighting Systems Pty Ltd v Bremore Engineering (WA Pty Ltd) & Ors [2007] QSC 333
MWB Everton Park Pty Ltd as trustee for MWB Everton Park Unit Trust v Devcon Building Co Pty Ltd [2024] QCA 94
Neumann Contractors Pty Ltd v Peet Beachton Syndicate Ltd [2009] QSC 376
Project Blue Sky Inc & Ors v Australian Broadcasting Authority (1998) 194 CLR 355
Re Galaxy Investments (Qld) Pty Ltd [1993] QSC 231
T & M Buckley Pty Ltd v 57 Moss Road Pty Ltd [2010] QCA 381
Taringa Property Group Pty Ltd v Kenik Pty Ltd [2024] QSC 298

Virgtel Ltd & Anor v Zabusky & Ors (No 2) [2009] QCA…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Starline Interiors Pty Ltd v Tomkins Commercial and Industri... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2025] QDC 63
Decision Date

CaseChat Overview and Summary

The case between Starline Interiors Pty Ltd and Tomkins Commercial and Industrial Builders Pty Ltd concerns a dispute over the recovery of a progress payment under a subcontract for work on a high-rise project in Main Beach, Queensland. The applicant, Starline Interiors, entered into a subcontract with the respondent, Tomkins Commercial and Industrial Builders, to install plasterboard walls and ceilings, supply and install fire-rated walling systems, and undertake carpentry work. The applicant issued a payment claim for $681,035.62 under the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (the BIF Act). The respondent issued a payment schedule, certifying $542,074.95 as owing, and partially paid this amount to the applicant. The applicant seeks judgment for the balance of the amount claimed, either under the BIF Act or as a contractual claim. The respondent resists the application and seeks an interlocutory injunction or stay of proceedings, arguing that the payment claim is defective and that set-offs have extinguished any debt owed to the applicant.

The court was required to determine several legal issues. Firstly, whether the payment claim was defective under the BIF Act, particularly whether it sufficiently identified the work or goods and services claimed. Secondly, whether the payment schedule issued by the respondent complied with the statutory requirements and whether it had the effect of creating a debt that could be recovered by the applicant. Thirdly, whether the respondent's set-offs had the effect of extinguishing any debt owed to the applicant. Fourthly, whether injunctive relief or a stay of proceedings was justified in the circumstances.

The court found that the payment claim was not defective under s 68(1)(a) of the BIF Act as it sufficiently identified the work or goods and services claimed, as evidenced by the respondent's detailed response using its own chosen payment system, Payapps. The payment claim was reasonably comprehensible to the respondent and met the requirements of the Act. The court also found that the payment schedule created a debt which could be recovered by the applicant under s 76(3) of the BIF Act. Regarding the set-offs, the court held that they did not extinguish the debt owed to the applicant. Lastly, the court dismissed the respondent's application for injunctive relief or a stay of proceedings, finding that the applicant had a strong arguable case and that the balance of convenience favoured granting judgment to the applicant.

The court ordered that the respondent pay the applicant $191,287.70 inclusive of GST and interest to and including 10 April 2025. The court also dismissed the respondent's cross application and ordered that the respondent pay the applicant's costs of both proceedings as agreed or assessed.

Orders

Orders of the court

1. The Respondent pay the Applicant $191,287.70 inclusive of (a) GST and (b) $14,212.75 on account of interest to and including 10 April 2025.

2. The Respondent’s cross application is dismissed.

3. The Respondent pay the Applicant’s costs of both proceedings as agreed or assessed.

Background

Background to the litigation

The applicant claims judgment in the sum of $177,074.95 (including GST) pursuant to s 78(2) of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (the BIF Act). This is said to be a sum owed as a debt arising pursuant to the BIF Act alternatively it is claimed as a progress payment under a subcontract. Background The respondent is a builder who at the relevant time was undertaking works on a high rise project at Main Beach in Queensland. On 10 November 2023, the respondent, as head contractor and the applicant, as subcontractor entered into a subcontract for the applicant to install plasterboard walls and ceilings, supply and install fire rated walling systems and undertake general carpentry work (the subcontract). On 25 July 2024, the applicant issued the respondent a payment claim for $681,035.62 (including GST) (the payment claim). On 8 August 2024, the respondent, pursuant to the procedures in the BIF Act, issued a payment schedule certifying $542,074.95 (including GST) as being owing pursuant to the claim (the payment schedule). Subsequently between 13 September and 13 December 2024, the respondent paid to the applicant $365,000.00 (including GST) in respect of the payment schedule, leaving the balance owing. The application was filed on 14 February 2025 and various supporting affidavits were filed. The respondent filed a cross application on 27 March 2025 seeking an interlocutory injunction restraining the applicant from enforcing the alleged debt, either under the BIF Act or under the contract, alternatively a stay of proceedings. This comes about because the respondent, who resists the application for a number of reasons, also now asserts various set offs which it argues has the effect of extinguishing any debt claimed by the applicant.The issuesValidity of payment claim The applicant submits that it may recover under the statutory remedies in s 78 of the BIF Act, alternatively as a contractual claim under Clause 37.2 of the subcontract. Section 78 is in Chapter 3 of the BIF Act, Progress Payments, and Part 3 thereof, Claiming Progress Payments. It applies to the situation where a respondent has not paid a payment claim for a progress payment in full on or before the due date and refers to an “amount owed”. This is defined in subsection (5) as including the situation where a respondent responds to a payment claim with a payment schedule as required by s 76 – the scheduled amount becomes an amount owed. Section 76(3) of the BIF Act provides that where the respondent gives the claimant a payment schedule, it must pay the claim and the amount proposed in the payment schedule no later than the due date for the relevant progress payment to which the schedule relates. That is, it creates a debt which may be recovered. The BIF Act has the main purpose of helping people working in the building and construction industry in being paid for their work; s 3(1). Section 3(2) sets out that the main purpose is to be achieved primarily by inter alia: “(b) granting an entitlement to progress payments, whether or not the relevant contract makes provision for progress payments; and (c) establishing a procedure for – (i) making payment claims; and (ii) responding to payment claims; and…(iv) the recovery of amounts claimed…”

Evidence

Evidence before the court

Decision

Reasons for decision

I note that in this case, and possibly as a further distinction from MWB, it seems that the use of percentages was not only contemplated, but positively invited, by the use of the respondent’s chosen payment system, Payapps. Mr Knezevic, the applicant’s project manager, deposes that he entered the percentages into Payapps which then automatically calculated the relevant value consistently with the subcontract. The line items in Payapps were controlled by the respondent, including the description and subcontract value. The respondent’s payment schedule, like the payment claim also sent through Payapps, referred to it being issued under the BIF Act.Conclusion as to s68(1)(a) issue Thus on the first issue the applicant argues that the payment claim sufficiently identified the construction work or related goods and services for the purposes of s 68(1)(a) of the BIF Act. Its basis was at the very least “reasonably comprehensible”. It is a factually different case from MWB or KDV, producing a different result. In my conclusion this submission must be accepted. In the circumstances set out, my findings are that the payment claim did sufficiently identify the work or goods and services as required by s 68(1)(a) and thus the basis of the claim was reasonably comprehensible to the respondent, as shown by its detailed response using its own chosen system. The challenge to the payment claim on this aspect fails.Failure to request payment of the claimed amount – s 68(1)(c) As to the requirement of s 68(1)(c) of the BIF Act, the applicant was required by the subcontract to use Payapps. It was required to input the values against each item of work claimed as described above and deposed to by Mr Knezevic. In MWB the words “amount due this claim” were rejected as being a request for payment. The phrase was held to be an identification by the builder of the progress payment which it claimed was payable but was not a request for payment under s 68(1)(c). Had the document been headed “Invoice” rather than “Project Summary”, this would have been sufficient because of s 68(3) of the BIF Act. No particular form of words is necessary (MWB at [35] referring to Minimax Fire Fighting Systems Pty Ltd v Bremore Engineering (WA Pty Ltd) & Ors [2007] QSC 333 at [20]) however something which amounts to a request for payment needs to be either express or necessarily and clearly implied. The applicant submits that the payment claim in this case is different from MWB and meets the required test. Its terms, on the first page, include the express description “payment claim” and it is said “the following payment claim has just been submitted by Erol Knezevic. This is a payment claim made under the Building Industry Fairness (Security of Payment) Act2017” (emphasis added). Similar words, referring to a claim under the BIF Act, were not present in the 30 June claim in MWB but were present in the 17 July claim which was accepted as valid. The applicant’s payment claim identified the claimant’s details, the project details, the gross and net payment claimed, the respondent’s details and further payment claim details including the date of the claim and the period to which it relates. There is, on the second page of the hard copy, a claimed contract summary including various tabulated items. One column is headed “Completed this Period” and the total for that column is described as “Amount Due including GST”. This is the amount of the claim.

Ratio Decidendi

Legal principle established