Southern Region Pty Ltd v State of Victoria (No 2)

Link copied
Case Copied 20 min read
IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE

COMMERCIAL AND EQUITY DIVISION

BUILDING CASES LIST

No. 6457 of 2001

SOUTHERN REGION PTY LTD
(ACN 004 770 085)
Plaintiff
v
THE MINISTER FOR POLICE AND EMERGENCY SERVICES FOR AND ON BEHALF OF THE STATE OF VICTORIA Defendant

---

JUDGE:

Byrne J

WHERE HELD:

Melbourne

DATE OF HEARING:

28 September 2001

DATE OF JUDGMENT:

26 October 2001

CASE MAY BE CITED AS:

Southern Region Pty Ltd v State of Victoria (No.2)

MEDIUM NEUTRAL CITATION:

[2001] VSC 381

First Revision 23 November 2001

---

Building Contract – final payment claim – summary judgment application – whether separate defects liability period established – whether claim supported by evidence of amount claimed.
AS2124-1992 cll. 37, 42.1, 42.7.

---

APPEARANCES:

Counsel Solicitors
For the Plaintiff Dr C.L. Pannam QC
and Mr M.G. Roberts
Deacons
For the Defendant Mr P.N. Vickery QC
and Mr F.J.J. Tiernan
Minter Ellison

HIS HONOUR:

  1. This proceeding arises out of the construction of the Police and Courts Complex at Ballarat.  The plaintiff, Southern Region Pty Ltd ("the Contractor"), by writ filed on 27 June 2001, sues the defendant, the Minister for Police and Emergency Services for and on behalf of the State of Victoria ("the Principal"), for $7,698,951 being the amount of an uncertified claim made under a building contract dated 28 November 1997.  The Contractor also sues the Principal for damages for breach of certain express and implied terms of the building contract.  Before the court is a summons filed on behalf of the Contractor on 10 July 2001 seeking summary judgment for the sum uncertified.

The Facts

  1. The circumstances which give rise to the proceeding and the summary judgment application are unusual and a little complicated.  For the most part, however, they are not in dispute.  It is convenient that I set them out at this point. 

  1. On 28 November 1997 the Contractor entered into a contract for the demolition of existing buildings and the construction of the new Police and Courts Complex.  The contract price was $17,866,000.  The contract was based on the standard form agreement, AS2124-1992, with certain modifications. 

  1. The date for practical completion, as adjusted, was 18 August 1999 and the works were certified to have achieved that condition on 15 May 2000.  This had the consequence that the defects liability period would expire on 14 May 2001.

  1. Soon after practical completion the parties were in dispute.  On 30 June 2000 the Contractor lodged its progress payment claim number 30 seeking payment of about $5.6M.  Progress payment certificate number 32 issued by the Superintendent in response to this claim showed no amount due to the Contractor from the Principal nor to the Principal from the Contractor.  On 27 July 2000 the Contractor gave notice of dispute pursuant to cl. 47.1.  In substance, this dispute concerned the entitlement of the Contractor to payment of the sums sought in its progress payment claim number 30, to extensions of time for completion and to release of one half…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Southern Region Pty Ltd v State of Victoria (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2001] VSC 381
Decision Date

CaseChat Overview and Summary

Southern Region Pty Ltd, a building contractor, brought an action against the State of Victoria seeking payment for work performed under a building contract. The State of Victoria resisted the claim, arguing that the contractor had not established a separate defects liability period or provided sufficient evidence of the amount claimed. The dispute was heard in the Supreme Court of Victoria.

The primary legal issue before the court was whether the contractor had established a separate defects liability period for the final payment claim and whether the claim was supported by evidence of the amount claimed. The court had to interpret the contract and relevant clauses of AS2124-1992 to determine the obligations of both parties.

The court found that the contract did not establish a separate defects liability period for the final payment claim. Furthermore, the contractor had not provided sufficient evidence to support the amount claimed. The court held that the contractor's claim was not substantiated by the evidence provided, and the application for summary judgment was dismissed. The court found that the contractor had failed to meet the necessary burden of proof.

The court's final orders were that the defendant's application for summary judgment was dismissed, and the plaintiff was ordered to pay the defendant's costs of the application. The case was to proceed to a full hearing to determine the merits of the contractor's claim.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established