LAND COURT OF QUEENSLAND
CITATION: Southedge Daintree Pastoral Company Pty Ltd and Anor v Kenneth Michael Wilson [2009] QLC 0122 PARTIES: Southedge Daintree Pastoral Company Pty Ltd and Weymouth Pastoral Company Pty Ltd
(applicants)v. Kenneth Michael Wilson
(respondent)FILE NOS: MRA 1356-08 and MRA 1357-08 DIVISION: General Division PROCEEDING: Application for compensation for mining lease DELIVERED ON: 19 August 2009 DELIVERED AT: Brisbane HEARD AT: Written submissions PRESIDENT: Mrs CAC MacDonald ORDER: 1. Compensation is determined in the sum of One Thousand, Four hundred and thirty Dollars ($1,430).
2. The respondent is ordered to pay the applicants' costs of and incidental to this matter, fixed in the sum of Two Hundred and Seventy-five Dollars ($275).
3. The respondent is ordered to pay the compensation of $1,430 and costs of $275 to the applicants within one month of the grant of the mining lease.
CATCHWORDS: Mining Lease – compensation – claim for partial loss of grazing rights by landowner – claim allowed in part – claim for fencing to exclude stock from lease and access to lease – not allowed – costs for preparation of claim allowed in part.
On 24 December 2008 I handed down my decision in respect of an application by Kenneth Michael Wilson for Mining Lease 20529. Objections to the grant of the lease had been filed by Southedge Daintree Co Pty Ltd and Weymouth Pastoral Co Pty Ltd, the owners of the land over which the Mining Lease was sought. That decision recommended to the Honourable the Minister for Mines and Energy that Mining Lease 20529 be granted over the application area for a term of five years and that the lease should be subject to certain special conditions as set out in the recommendation.
Southedge Daintree Pastoral Company Pty Ltd and Weymouth Pastoral Company Pty Ltd (the applicants) have now sought compensation from Kenneth Michael Wilson in respect of the proposed grant of the mining lease. The applicants' claim for compensation was supported by valuation evidence supplied by Ian James Anders, a property consultant of Cairns. Mr Anders is a registered valuer.
The applicants claim a total amount of $13,365 made up of compensation of $12,150 for grant of ML 20529 together with an additional 10% ($1,215) to be awarded under s.281(4)(e) of the Mineral Resources Act 1989 (the Act). In addition, pursuant to s.281(7) of the Act, the applicants have claimed $550 as the costs of formulating the claim for compensation, being the professional fees of Mr Anders.
Compensation
The claim for compensation is made up as follows -
Carrying capacity of mining lease area plus 5 metre wide access track, 7 head (adult equivalent) at an agistment rate of $2.50 per head per week -
7 head for the 5 year term of lease (7 x 2.50 x 52 x 5) $4,550
Cost of fencing to exclude stock -
Approximate length of lease boundary 1.9 kms. Estimated cost of fencing to full barbed cattle proof standard, including any line clearing, rocks etc…
Keep reading for free
Create a free CaseChat account to read Southedge Daintree Pastoral Company Pty Ltd v Kenneth Michae... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2009] QLC 122
- Decision Date
CaseChat Overview and Summary
The Tribunal concluded that the mining lease did result in a partial loss of grazing rights, thus entitling the applicant to compensation. However, the Tribunal found that the fencing costs were not recoverable as the applicant had not demonstrated a necessity for the fencing. The costs associated with preparing the claim were allowed only in part, as the Tribunal deemed some of the costs to be reasonable and necessary. The compensation was quantified at One Thousand, Four Hundred and Thirty Dollars ($1,430), and the Tribunal ordered the respondent to pay this amount along with the costs of the proceedings, fixed at Two Hundred and Seventy-five Dollars ($275). The respondent was also directed to pay the compensation and costs within one month of the grant of the mining lease.
In summary, the Tribunal allowed the applicant’s claim for compensation for the partial loss of grazing rights, partially allowed the costs for preparing the claim, and denied the claim for fencing costs. The respondent was ordered to pay the determined compensation and a portion of the costs within one month of the grant of the mining lease.
Orders
Orders of the court
1. Compensation is determined in the sum of One Thousand, Four hundred and thirty Dollars ($1,430).
2. The respondent is ordered to pay the applicants' costs of and incidental to this matter, fixed in the sum of Two Hundred and Seventy-five Dollars ($275).
3. The respondent is ordered to pay the compensation of $1,430 and costs of $275 to the applicants within one month of the grant of the mining lease.
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi